§ 60.112a Standard for volatile organic compounds (VOC).
(a) The owner or operator of each storage vessel to which this subpart applies which contains a petroleum liquid which, as stored, has a true vapor pressure equal to or greater than 10.3 kPa (1.5 psia) but not greater than 76.6 kPa (11.1 psia) shall equip the storage vessel with one of the following:
(1) An external floating roof, consisting of a pontoon-type or double-deck-type cover that rests on the surface of the liquid contents and is equipped with a closure device between the tank wall and the roof edge. Except as provided in paragraph (a)(1)(ii)(D) of this section, the closure device is to consist of two seals, one above the other. The lower seal is referred to as the primary seal and the upper seal is referred to as the secondary seal. The roof is to be floating on the liquid at all times (i.e., off the roof leg supports) except during initial fill and when the tank is completely emptied and subsequently refilled. The process of emptying and refilling when the roof is resting on the leg supports shall be continuous and shall be accomplished as rapidly as possible.
(i) The primary seal is to be either a metallic shoe seal, a liquid-mounted seal, or a vapor-mounted seal. Each seal is to meet the following requirements:
(A) The accumulated area of gaps between the tank wall and the metallic shoe seal or the liquid-mounted seal shall not exceed 212 cm2 per meter of tank diameter (10.0 in 2 per ft of tank diameter) and the width of any portion of any gap shall not exceed 3.81 cm (11/2 in).
(B) The accumulated area of gaps between the tank wall and the vapor-mounted seal shall not exceed 21.2 cm2 per meter of tank diameter (1.0 in2 per ft of tank diameter) and the width of any portion of any gap shall not exceed 1.27 cm (1/2 in).
(C) One end of the metallic shoe is to extend into the stored liquid and the other end is to extend a minimum vertical distance of 61 cm (24 in) above the stored liquid surface.
(D) There are to be no holes, tears, or other openings in the shoe, seal fabric, or seal envelope.
(ii) The secondary seal is to meet the following requirements:
(A) The secondary seal is to be installed above the primary seal so that it completely covers the space between the roof edge and the tank wall except as provided in paragraph (a)(1)(ii)(B) of this section.
(B) The accumulated area of gaps between the tank wall and the secondary seal used in combination with a metallic shoe or liquid-mounted primary seal shall not exceed 21.2 cm2 per meter of tank diameter (1.0 in2 per ft. of tank diameter) and the width of any portion of any gap shall not exceed 1.27 cm (1/2 in.). There shall be no gaps between the tank wall and the secondary seal used in combination with a vapor-mounted primary seal.
(C) There are to be no holes, tears or other openings in the seal or seal fabric.
(D) The owner or operator is exempted from the requirements for secondary seals and the secondary seal gap criteria when performing gap measurements or inspections of the primary seal.
(iii) Each opening in the roof except for automatic bleeder vents and rim space vents is to provide a projection below the liquid surface. Each opening in the roof except for automatic bleeder vents, rim space vents and leg sleeves is to be equipped with a cover, seal or lid which is to be maintained in a closed position at all times (i.e., no visible gap) except when the device is in actual use or as described in pargraph (a)(1)(iv) of this section. Automatic bleeder vents are to be closed at all times when the roof is floating, except when the roof is being floated off or is being landed on the roof leg supports. Rim vents are to be set to open when the roof is being floated off the roof legs supports or at the manufacturer's recommended setting.
(iv) Each emergency roof drain is to be provided with a slotted membrane fabric cover that covers at least 90 percent of the area of the opening.
(2) A fixed roof with an internal floating type cover equipped with a continuous closure device between the tank wall and the cover edge. The cover is to be floating at all times, (i.e., off the leg supports) except during initial fill and when the tank is completely emptied and subsequently refilled. The process of emptying and refilling when the cover is resting on the leg supports shall be continuous and shall be accomplished as rapidly as possible. Each opening in the cover except for automatic bleeder vents and the rim space vents is to provide a projection below the liquid surface. Each opening in the cover except for automatic bleeder vents, rim space vents, stub drains and leg sleeves is to be equipped with a cover, seal, or lid which is to be maintained in a closed position at all times (i.e., no visible gap) except when the device is in actual use. Automatic bleeder vents are to be closed at all times when the cover is floating except when the cover is being floated off or is being landed on the leg supports. Rim vents are to be set to open only when the cover is being floated off the leg supports or at the manufacturer's recommended setting.
(3) A vapor recovery system which collects all VOC vapors and gases discharged from the storage vessel, and a vapor return or disposal system which is designed to process such VOC vapors and gases so as to reduce their emission to the atmosphere by at least 95 percent by weight.
(4) A system equivalent to those described in paragraphs (a)(1), (a)(2), or (a)(3) of this section as provided in § 60.114a.
(b) The owner or operator of each storage vessel to which this subpart applies which contains a petroleum liquid which, as stored, has a true vapor pressure greater than 76.6 kPa (11.1 psia), shall equip the storage vessel with a vapor recovery system which collects all VOC vapors and gases discharged from the storage vessel, and a vapor return or disposal system which is designed to process such VOC vapors and gases so as to reduce their emission to the atmosphere by at least 95 percent by weight.
[45 FR 23379, Apr. 4, 1980, as amended at 45 FR 83229, Dec. 18, 1980]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-05-16; vol. 79 # 95 - Friday, May 16, 2014
    1. 79 FR 28439 - Quality Assurance Requirements for Continuous Opacity Monitoring Systems at Stationary Sources
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on November 12, 2014.
      40 CFR Part 60

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7450 to 7459 - Repealed.

§ 7470 - Congressional declaration of purpose

§ 7471 - Plan requirements

§ 7472 - Initial classifications

§ 7473 - Increments and ceilings

§ 7474 - Area redesignation

§ 7475 - Preconstruction requirements

§ 7476 - Other pollutants

§ 7477 - Enforcement

§ 7478 - Period before plan approval

§ 7479 - Definitions

§ 7491 - Visibility protection for Federal class I areas

§ 7492 - Visibility

§ 7501 - Definitions

§ 7502 - Nonattainment plan provisions in general

§ 7503 - Permit requirements

§ 7504 - Planning procedures

§ 7505 - Environmental Protection Agency grants

§ 7505a - Maintenance plans

§ 7506 - Limitations on certain Federal assistance

§ 7506a - Interstate transport commissions

§ 7507 - New motor vehicle emission standards in nonattainment areas

§ 7508 - Guidance documents

§ 7509 - Sanctions and consequences of failure to attain

§ 7509a - International border areas

§ 7511 - Classifications and attainment dates

§ 7511a - Plan submissions and requirements

§ 7511b - Federal ozone measures

§ 7511c - Control of interstate ozone air pollution

§ 7511d - Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

§ 7511e - Transitional areas

§ 7511f - NO

§ 7512 - Classification and attainment dates

§ 7512a - Plan submissions and requirements

§ 7513 - Classifications and attainment dates

§ 7513a - Plan provisions and schedules for plan submissions

§ 7513b - Issuance of RACM and BACM guidance

§ 7514 - Plan submission deadlines

§ 7514a - Attainment dates

§ 7515 - General savings clause

§ 7521 - Emission standards for new motor vehicles or new motor vehicle engines

§ 7522 - Prohibited acts

§ 7523 - Actions to restrain violations

§ 7524 - Civil penalties

§ 7525 - Motor vehicle and motor vehicle engine compliance testing and certification

§ 7541 - Compliance by vehicles and engines in actual use

§ 7542 - Information collection

§ 7543 - State standards

§ 7544 - State grants

§ 7545 - Regulation of fuels

§ 7546 - Renewable fuel

§ 7547 - Nonroad engines and vehicles

§ 7548 - Study of particulate emissions from motor vehicles

§ 7549 - High altitude performance adjustments

§ 7550 - Definitions

§ 7551 - Omitted

§ 7552 - Motor vehicle compliance program fees

§ 7553 - Prohibition on production of engines requiring leaded gasoline

§ 7554 - Urban bus standards

§ 7571 - Establishment of standards

§ 7572 - Enforcement of standards

§ 7573 - State standards and controls

§ 7574 - Definitions

§ 7581 - Definitions

§ 7582 - Requirements applicable to clean-fuel vehicles

§ 7583 - Standards for light-duty clean-fuel vehicles

§ 7584 - Administration and enforcement as per California standards

§ 7585 - Standards for heavy-duty clean-fuel vehicles (GVWR above 8,500 up to 26,000 lbs.)

§ 7586 - Centrally fueled fleets

§ 7587 - Vehicle conversions

§ 7588 - Federal agency fleets

§ 7589 - California pilot test program

§ 7590 - General provisions

§ 7601 - Administration

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 60 after this date.

  • 2014-07-17; vol. 79 # 137 - Thursday, July 17, 2014
    1. 79 FR 41752 - Oil and Natural Gas Sector: Reconsideration of Additional Provisions of New Source Performance Standards
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule; Notice of Public Hearing.
      Comments. Comments must be received on or before August 18, 2014, unless a public hearing is requested by July 22, 2014. If a hearing is requested on this proposed rule, written comments must be received by September 2, 2014. Public Hearing. If anyone contacts the EPA requesting a public hearing by July 22, 2014 we will hold a public hearing on August 1, 2014. If a public hearing is requested by July 22, 2014, it will be held on August 1, 2014 at the EPA's Research Triangle Park Campus, 109 T.W. Alexander Drive, Research Triangle Park, NC 27711. The hearing will convene at 10:00 a.m. (Eastern Standard Time) and end at 5:00 p.m. (Eastern Standard Time). A lunch break will be held from 12:00 p.m. (Eastern Standard Time) until 1:00 p.m. (Eastern Standard Time). Please contact Virginia Hunt at (919) 541-0832, or at hunt.virginia@epa.gov to request a hearing, to determine if a hearing will be held and to register to speak at the hearing, if one is held. If a hearing is requested, the last day to pre-register in advance to speak at the hearing will be July 30, 2014. Additionally, requests to speak will be taken the day of the hearing at the hearing registration desk, although preferences on speaking times may not be able to be fulfilled. If you require the service of a translator or special accommodations such as audio description, please let us know at the time of registration. If no one contacts the EPA requesting a public hearing to be held concerning this proposed rule by July 22, 2014, a public hearing will not take place. If a hearing is held, it will provide interested parties the opportunity to present data, views or arguments concerning the proposed action. The EPA will make every effort to accommodate all speakers who arrive and register. Because these hearings are being held at U.S. government facilities, individuals planning to attend the hearing should be prepared to show valid picture identification (e.g., driver's license or government-issued ID) to the security staff in order to gain access to the meeting room. Please note that the REAL ID Act, passed by Congress in 2005, established new requirements for entering federal facilities. These requirements will take effect July 21, 2014. If your driver's license is issued by Alaska, American Samoa, Arizona, Kentucky, Louisiana, Maine, Massachusetts, Minnesota, Montana, New York, Oklahoma or Washington State, you must present an additional form of identification to enter the federal buildings where the public hearings will be held. Acceptable alternative forms of identification include: Federal employee badges, passports, enhanced driver's licenses and military identification cards. In addition, you will need to obtain a property pass for any personal belongings you bring with you. Upon leaving the building, you will be required to return this property pass to the security desk. No large signs will be allowed in the building, cameras may only be used outside of the building and demonstrations will not be allowed on federal property for security reasons. The EPA may ask clarifying questions during the oral presentations, but will not respond to the presentations at that time. Written statements and supporting information submitted during the comment period will be considered with the same weight as oral comments and supporting information presented at the public hearing. If a hearing is held on August 1, 2014, written comments on the proposed rule must be postmarked by September 2, 2014. Commenters should notify Ms. Hunt if they will need specific equipment, or if there are other special needs related to providing comments at the hearing. The EPA will provide equipment for commenters to show overhead slides or make computerized slide presentations if we receive special requests in advance. Oral testimony will be limited to 5 minutes for each commenter. Verbatim transcripts of the hearings and written statements will be included in the docket for the rulemaking. The EPA will make every effort to follow the schedule as closely as possible on the day of the hearing; however, please plan for the hearing to run either ahead of schedule or behind schedule. Information regarding the hearing (including information as to whether or not one will be held) will be available at: http://www.epa.gov/airquality/oilandgas/actions.html. Again, all requests for a public hearing to be held must be received by July 22, 2014.
      40 CFR Part 60