You must submit the reports specified in paragraphs (a) through (j) of this section. See Table 5 to this subpart for a summary of these reports.
(a) Notification of construction. You must submit a notification prior to commencing construction that includes the four items listed in paragraphs (a)(1) through (a)(4) of this section:
(1) A statement of intent to construct.
(2) The anticipated date of commencement of construction.
(3) All documentation produced as a result of the siting requirements of § 60.4805.
(4) Anticipated date of initial startup.
(b) Notification of initial startup. You must submit the information specified in paragraphs (b)(1) through (b)(5) of this section prior to initial startup:
(1) The maximum design dry sludge burning capacity.
(2) The anticipated and permitted maximum dry sludge feed rate.
(3) If applicable, the petition for site-specific operating limits specified in § 60.4855.
(4) The anticipated date of initial startup.
(5) The site-specific monitoring plan required under § 60.4880, at least 60 days before your initial performance evaluation of your continuous monitoring system.
(6) The site-specific monitoring plan for your ash handling system required under § 60.4880, at least 60 days before your initial performance test to demonstrate compliance with your fugitive ash emission limit.
(c) Initial compliance report. You must submit the following information no later than 60 days following the initial performance test.
(1) Company name, physical address, and mailing address.
(2) Statement by a responsible official, with that official's name, title, and signature, certifying the accuracy of the content of the report.
(3) Date of report.
(4) The complete test report for the initial performance test results obtained by using the test methods specified in Table 1 or 2 to this subpart.
(5) If an initial performance evaluation of a continuous monitoring system was conducted, the results of that initial performance evaluation.
(6) The values for the site-specific operating limits established pursuant to §§ 60.4850 and 60.4855 and the calculations and methods, as applicable, used to establish each operating limit.
(7) If you are using a fabric filter to comply with the emission limits, documentation that a bag leak detection system has been installed and is being operated, calibrated, and maintained as required by § 60.4850(b).
(8) The results of the initial air pollution control device inspection required in § 60.4875, including a description of repairs.
(d) Annual compliance report. You must submit an annual compliance report that includes the items listed in paragraphs (d)(1) through (d)(16) of this section for the reporting period specified in paragraph (d)(3) of this section. You must submit your first annual compliance report no later than 12 months following the submission of the initial compliance report in paragraph (c) of this section. You must submit subsequent annual compliance reports no more than 12 months following the previous annual compliance report. (You may be required to submit these reports (or additional compliance information) more frequently by the title V operating permit required in § 60.4920.)
(1) Company name, physical address, and mailing address.
(2) Statement by a responsible official, with that official's name, title, and signature, certifying the accuracy of the content of the report.
(3) Date of report and beginning and ending dates of the reporting period.
(4) If a performance test was conducted during the reporting period, the results of that performance test.
(i) If operating limits were established during the performance test, include the value for each operating limit and, as applicable, the method used to establish each operating limit, including calculations.
(ii) If activated carbon is used during the performance test, include the type of activated carbon used.
(5) For each pollutant and operating parameter recorded using a continuous monitoring system, the highest average value and lowest average value recorded during the reporting period, as follows:
(i) For continuous emission monitoring systems and continuous automated sampling systems, report the highest and lowest 24-hour average emission value.
(ii) For continuous parameter monitoring systems, report the following values:
(A) For all operating parameters except scrubber liquid pH, the highest and lowest 12-hour average values.
(B) For scrubber liquid pH, the highest and lowest 3-hour average values.
(6) If there are no deviations during the reporting period from any emission limit, emission standard, or operating limit that applies to you, a statement that there were no deviations from the emission limits, emission standard, or operating limits.
(7) Information for bag leak detection systems recorded under § 60.4910(f)(3)(iii).
(8) If a performance evaluation of a continuous monitoring system was conducted, the results of that performance evaluation. If new operating limits were established during the performance evaluation, include your calculations for establishing those operating limits.
(9) If you elect to conduct performance tests less frequently as allowed in § 60.4885(a)(3) and did not conduct a performance test during the reporting period, you must include the dates of the last two performance tests, a comparison of the emission level you achieved in the last two performance tests to the 75 percent emission limit threshold specified in § 60.4885(a)(3), and a statement as to whether there have been any process changes and whether the process change resulted in an increase in emissions.
(10) Documentation of periods when all qualified SSI unit operators were unavailable for more than 8 hours, but less than 2 weeks.
(11) Results of annual air pollution control device inspections recorded under § 60.4910(d) for the reporting period, including a description of repairs.
(12) If there were no periods during the reporting period when your continuous monitoring systems had a malfunction, a statement that there were no periods during which your continuous monitoring systems had a malfunction.
(13) If there were no periods during the reporting period when a continuous monitoring system was out of control, a statement that there were no periods during which your continuous monitoring system was out of control.
(14) If there were no operator training deviations, a statement that there were no such deviations during the reporting period.
(15) If you did not make revisions to your site-specific monitoring plan during the reporting period, a statement that you did not make any revisions to your site-specific monitoring plan during the reporting period. If you made revisions to your site-specific monitoring plan during the reporting period, a copy of the revised plan.
(16) If you had a malfunction during the reporting period, the compliance report must include the number, duration, and a brief description for each type of malfunction that occurred during the reporting period and that caused or may have caused any applicable emission limitation to be exceeded. The report must also include a description of actions taken by an owner or operator during a malfunction of an affected source to minimize emissions in accordance with § 60.11(d), including actions taken to correct a malfunction.
(e) Deviation reports.
(1) You must submit a deviation report if:
(i) Any recorded operating parameter level, based on the averaging time specified in Table 3 to this subpart, is above the maximum operating limit or below the minimum operating limit established under this subpart.
(ii) The bag leak detection system alarm sounds for more than 5 percent of the operating time for the 6-month reporting period.
(iii) Any recorded 24-hour block average emissions level is above the emission limit, if a continuous monitoring system is used to comply with an emission limit.
(iv) There are visible emissions of combustion ash from an ash conveying system for more than 5 percent of the hourly observation period.
(v) A performance test was conducted that deviated from any emission limit in Table 1 or 2 to this subpart.
(vi) A continuous monitoring system was out of control.
(vii) You had a malfunction (e.g., continuous monitoring system malfunction) that caused or may have caused any applicable emission limit to be exceeded.
(2) The deviation report must be submitted by August 1 of that year for data collected during the first half of the calendar year (January 1 to June 30), and by February 1 of the following year for data you collected during the second half of the calendar year (July 1 to December 31).
(3) For each deviation where you are using a continuous monitoring system to comply with an associated emission limit or operating limit, report the items described in paragraphs (e)(3)(i) through (e)(3)(viii) of this section.
(i) Company name, physical address, and mailing address.
(ii) Statement by a responsible official, with that official's name, title, and signature, certifying the accuracy of the content of the report.
(iii) The calendar dates and times your unit deviated from the emission limits, emission standards, or operating limits requirements.
(iv) The averaged and recorded data for those dates.
(v) Duration and cause of each deviation from the following:
(A) Emission limits, emission standards, operating limits, and your corrective actions.
(B) Bypass events and your corrective actions.
(vi) Dates, times, and causes for monitor downtime incidents.
(vii) A copy of the operating parameter monitoring data during each deviation and any test report that documents the emission levels.
(viii) If there were periods during which the continuous monitoring system malfunctioned or was out of control, you must include the following information for each deviation from an emission limit or operating limit:
(A) The date and time that each malfunction started and stopped.
(B) The date, time, and duration that each continuous monitoring system was inoperative, except for zero (low-level) and high-level checks.
(C) The date, time, and duration that each continuous monitoring system was out of control, including start and end dates and hours and descriptions of corrective actions taken.
(D) The date and time that each deviation started and stopped, and whether each deviation occurred during a period of malfunction, during a period when the system as out of control, or during another period.
(E) A summary of the total duration of the deviation during the reporting period, and the total duration as a percent of the total source operating time during that reporting period.
(F) A breakdown of the total duration of the deviations during the reporting period into those that are due to control equipment problems, process problems, other known causes, and other unknown causes.
(G) A summary of the total duration of continuous monitoring system downtime during the reporting period, and the total duration of continuous monitoring system downtime as a percent of the total operating time of the SSI unit at which the continuous monitoring system downtime occurred during that reporting period.
(H) An identification of each parameter and pollutant that was monitored at the SSI unit.
(I) A brief description of the SSI unit.
(J) A brief description of the continuous monitoring system.
(K) The date of the latest continuous monitoring system certification or audit.
(L) A description of any changes in continuous monitoring system, processes, or controls since the last reporting period.
(4) For each deviation where you are not using a continuous monitoring system to comply with the associated emission limit or operating limit, report the following items:
(i) Company name, physical address, and mailing address.
(ii) Statement by a responsible official with that official's name, title, and signature, certifying the accuracy of the content of the report.
(iii) The total operating time of each affected SSI during the reporting period.
(iv) The calendar dates and times your unit deviated from the emission limits, emission standards, or operating limits requirements.
(v) The averaged and recorded data for those dates.
(vi) Duration and cause of each deviation from the following:
(A) Emission limits, emission standard, and operating limits, and your corrective actions.
(B) Bypass events and your corrective actions.
(vii) A copy of any performance test report that showed a deviation from the emission limits or standard.
(viii) A brief description of any malfunction reported in paragraph (e)(1)(vii) of this section, including a description of actions taken during the malfunction to minimize emissions in accordance with 60.11(d) and to correct the malfunction.
(f) Qualified operator deviation.
(1) If all qualified operators are not accessible for 2 weeks or more, you must take the two actions in paragraphs (f)(1)(i) and (f)(1)(ii) of this section.
(i) Submit a notification of the deviation within 10 days that includes the three items in paragraphs (f)(1)(i)(A) through (f)(1)(i)(C) of this section.
(A) A statement of what caused the deviation.
(B) A description of actions taken to ensure that a qualified operator is accessible.
(C) The date when you anticipate that a qualified operator will be available.
(ii) Submit a status report to the Administrator every 4 weeks that includes the three items in paragraphs (f)(1)(ii)(A) through (f)(1)(ii)(C) of this section.
(A) A description of actions taken to ensure that a qualified operator is accessible.
(B) The date when you anticipate that a qualified operator will be accessible.
(C) Request for approval from the Administrator to continue operation of the SSI unit.
(2) If your unit was shut down by the Administrator, under the provisions of § 60.4835(b)(2)(i), due to a failure to provide an accessible qualified operator, you must notify the Administrator within 5 days of meeting § 60.4835(b)(2)(ii) that you are resuming operation.
(g) Notification of a force majeure. If a force majeure is about to occur, occurs, or has occurred for which you intend to assert a claim of force majeure:
(1) You must notify the Administrator, in writing as soon as practicable following the date you first knew, or through due diligence should have known that the event may cause or caused a delay in conducting a performance test beyond the regulatory deadline, but the notification must occur before the performance test deadline unless the initial force majeure or a subsequent force majeure event delays the notice, and in such cases, the notification must occur as soon as practicable.
(2) You must provide to the Administrator a written description of the force majeure event and a rationale for attributing the delay in conducting the performance test beyond the regulatory deadline to the force majeure; describe the measures taken or to be taken to minimize the delay; and identify a date by which you propose to conduct the performance test.
(h) Other notifications and reports required. You must submit other notifications as provided by § 60.7 and as follows:
(1) You must notify the Administrator 1 month before starting or stopping use of a continuous monitoring system for determining compliance with any emission limit.
(2) You must notify the Administrator at least 30 days prior to any performance test conducted to comply with the provisions of this subpart, to afford the Administrator the opportunity to have an observer present.
(3) As specified in § 60.4900(a)(8), you must notify the Administrator at least 7 days prior to the date of a rescheduled performance test for which notification was previously made in paragraph (h)(2) of this section.
(i) Report submission form.
(1) Submit initial, annual, and deviation reports electronically or in paper format, postmarked on or before the submittal due dates.
(2) As of January 1, 2012 and within 60 days after the date of completing each performance test, as defined in § 63.2, conducted to demonstrate compliance with this subpart, you must submit relative accuracy test audit (i.e., reference method) data and performance test (i.e., compliance test) data, except opacity data, electronically to EPA's Central Data Exchange (CDX) by using the Electronic Reporting Tool (ERT) (see http://www.epa.gov/ttn/chief/ert/ert_tool.html/) or other compatible electronic spreadsheet. Only data collected using test methods compatible with ERT are subject to this requirement to be submitted electronically into EPA's WebFIRE database.
(j) Changing report dates. If the Administrator agrees, you may change the semi-annual or annual reporting dates. See § 60.19(c) for procedures to seek approval to change your reporting date.

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-05-16; vol. 79 # 95 - Friday, May 16, 2014
    1. 79 FR 28439 - Quality Assurance Requirements for Continuous Opacity Monitoring Systems at Stationary Sources
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on November 12, 2014.
      40 CFR Part 60

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7450 to 7459 - Repealed.

§ 7470 - Congressional declaration of purpose

§ 7471 - Plan requirements

§ 7472 - Initial classifications

§ 7473 - Increments and ceilings

§ 7474 - Area redesignation

§ 7475 - Preconstruction requirements

§ 7476 - Other pollutants

§ 7477 - Enforcement

§ 7478 - Period before plan approval

§ 7479 - Definitions

§ 7491 - Visibility protection for Federal class I areas

§ 7492 - Visibility

§ 7501 - Definitions

§ 7502 - Nonattainment plan provisions in general

§ 7503 - Permit requirements

§ 7504 - Planning procedures

§ 7505 - Environmental Protection Agency grants

§ 7505a - Maintenance plans

§ 7506 - Limitations on certain Federal assistance

§ 7506a - Interstate transport commissions

§ 7507 - New motor vehicle emission standards in nonattainment areas

§ 7508 - Guidance documents

§ 7509 - Sanctions and consequences of failure to attain

§ 7509a - International border areas

§ 7511 - Classifications and attainment dates

§ 7511a - Plan submissions and requirements

§ 7511b - Federal ozone measures

§ 7511c - Control of interstate ozone air pollution

§ 7511d - Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

§ 7511e - Transitional areas

§ 7511f - NO

§ 7512 - Classification and attainment dates

§ 7512a - Plan submissions and requirements

§ 7513 - Classifications and attainment dates

§ 7513a - Plan provisions and schedules for plan submissions

§ 7513b - Issuance of RACM and BACM guidance

§ 7514 - Plan submission deadlines

§ 7514a - Attainment dates

§ 7515 - General savings clause

§ 7521 - Emission standards for new motor vehicles or new motor vehicle engines

§ 7522 - Prohibited acts

§ 7523 - Actions to restrain violations

§ 7524 - Civil penalties

§ 7525 - Motor vehicle and motor vehicle engine compliance testing and certification

§ 7541 - Compliance by vehicles and engines in actual use

§ 7542 - Information collection

§ 7543 - State standards

§ 7544 - State grants

§ 7545 - Regulation of fuels

§ 7546 - Renewable fuel

§ 7547 - Nonroad engines and vehicles

§ 7548 - Study of particulate emissions from motor vehicles

§ 7549 - High altitude performance adjustments

§ 7550 - Definitions

§ 7551 - Omitted

§ 7552 - Motor vehicle compliance program fees

§ 7553 - Prohibition on production of engines requiring leaded gasoline

§ 7554 - Urban bus standards

§ 7571 - Establishment of standards

§ 7572 - Enforcement of standards

§ 7573 - State standards and controls

§ 7574 - Definitions

§ 7581 - Definitions

§ 7582 - Requirements applicable to clean-fuel vehicles

§ 7583 - Standards for light-duty clean-fuel vehicles

§ 7584 - Administration and enforcement as per California standards

§ 7585 - Standards for heavy-duty clean-fuel vehicles (GVWR above 8,500 up to 26,000 lbs.)

§ 7586 - Centrally fueled fleets

§ 7587 - Vehicle conversions

§ 7588 - Federal agency fleets

§ 7589 - California pilot test program

§ 7590 - General provisions

§ 7601 - Administration

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 60 after this date.

  • 2014-07-17; vol. 79 # 137 - Thursday, July 17, 2014
    1. 79 FR 41752 - Oil and Natural Gas Sector: Reconsideration of Additional Provisions of New Source Performance Standards
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule; Notice of Public Hearing.
      Comments. Comments must be received on or before August 18, 2014, unless a public hearing is requested by July 22, 2014. If a hearing is requested on this proposed rule, written comments must be received by September 2, 2014. Public Hearing. If anyone contacts the EPA requesting a public hearing by July 22, 2014 we will hold a public hearing on August 1, 2014. If a public hearing is requested by July 22, 2014, it will be held on August 1, 2014 at the EPA's Research Triangle Park Campus, 109 T.W. Alexander Drive, Research Triangle Park, NC 27711. The hearing will convene at 10:00 a.m. (Eastern Standard Time) and end at 5:00 p.m. (Eastern Standard Time). A lunch break will be held from 12:00 p.m. (Eastern Standard Time) until 1:00 p.m. (Eastern Standard Time). Please contact Virginia Hunt at (919) 541-0832, or at hunt.virginia@epa.gov to request a hearing, to determine if a hearing will be held and to register to speak at the hearing, if one is held. If a hearing is requested, the last day to pre-register in advance to speak at the hearing will be July 30, 2014. Additionally, requests to speak will be taken the day of the hearing at the hearing registration desk, although preferences on speaking times may not be able to be fulfilled. If you require the service of a translator or special accommodations such as audio description, please let us know at the time of registration. If no one contacts the EPA requesting a public hearing to be held concerning this proposed rule by July 22, 2014, a public hearing will not take place. If a hearing is held, it will provide interested parties the opportunity to present data, views or arguments concerning the proposed action. The EPA will make every effort to accommodate all speakers who arrive and register. Because these hearings are being held at U.S. government facilities, individuals planning to attend the hearing should be prepared to show valid picture identification (e.g., driver's license or government-issued ID) to the security staff in order to gain access to the meeting room. Please note that the REAL ID Act, passed by Congress in 2005, established new requirements for entering federal facilities. These requirements will take effect July 21, 2014. If your driver's license is issued by Alaska, American Samoa, Arizona, Kentucky, Louisiana, Maine, Massachusetts, Minnesota, Montana, New York, Oklahoma or Washington State, you must present an additional form of identification to enter the federal buildings where the public hearings will be held. Acceptable alternative forms of identification include: Federal employee badges, passports, enhanced driver's licenses and military identification cards. In addition, you will need to obtain a property pass for any personal belongings you bring with you. Upon leaving the building, you will be required to return this property pass to the security desk. No large signs will be allowed in the building, cameras may only be used outside of the building and demonstrations will not be allowed on federal property for security reasons. The EPA may ask clarifying questions during the oral presentations, but will not respond to the presentations at that time. Written statements and supporting information submitted during the comment period will be considered with the same weight as oral comments and supporting information presented at the public hearing. If a hearing is held on August 1, 2014, written comments on the proposed rule must be postmarked by September 2, 2014. Commenters should notify Ms. Hunt if they will need specific equipment, or if there are other special needs related to providing comments at the hearing. The EPA will provide equipment for commenters to show overhead slides or make computerized slide presentations if we receive special requests in advance. Oral testimony will be limited to 5 minutes for each commenter. Verbatim transcripts of the hearings and written statements will be included in the docket for the rulemaking. The EPA will make every effort to follow the schedule as closely as possible on the day of the hearing; however, please plan for the hearing to run either ahead of schedule or behind schedule. Information regarding the hearing (including information as to whether or not one will be held) will be available at: http://www.epa.gov/airquality/oilandgas/actions.html. Again, all requests for a public hearing to be held must be received by July 22, 2014.
      40 CFR Part 60