40 CFR 60.62 - Standards.

Status message

There are 9 Updates appearing in the Federal Register for 40 CFR 60. View below or at eCFR (GPOAccess)
§ 60.62 Standards.
(a) On and after the date on which the performance test required to be conducted by § 60.8 is completed, you may not discharge into the atmosphere from any kiln any gases which:
(1) Contain particulate matter (PM) in excess of:
(i) 0.30 pound per ton of feed (dry basis) to the kiln if construction, reconstruction, or modification of the kiln commences after August 17, 1971 but on or before June 16, 2008.
(ii) 0.01 pound per ton of clinker on a 30-operating day rolling average if construction, reconstruction, or modification of the kiln commenced after June 16, 2008. An operating day includes all valid data obtained in any daily 24-hour period during which the kiln operates and excludes any measurements made during the daily 24-hour period when the kiln was not operating.
(2) Exhibit greater than 20 percent opacity, except that this opacity limit does not apply to any kiln subject to a PM limit in paragraph (a)(1) of this section that uses a PM continuous emissions monitoring system (CEMS).
(3) Exceed 1.50 pounds of nitrogen oxide (NOX) per ton of clinker on a 30-operating day rolling average if construction, reconstruction, or modification of the kiln commences after June 16, 2008, except this limit does not apply to any alkali bypass installed on the kiln. An operating day includes all valid data obtained in any daily 24-hour period during which the kiln operates and excludes any measurements made during the daily 24-hour period when the kiln was not operating.
(4) Exceed 0.4 pounds of sulfur dioxide (SO2) per ton of clinker on a 30-operating day rolling average if construction, reconstruction, or modification commences after June 16, 2008, unless you are demonstrating a 90 percent SO2 emissions reduction measured across the SO2 control device. An operating day includes all valid data obtained in any daily 24-hour period during which the kiln operates, and excludes any measurements made during the daily 24-hour period when the kiln was not operating.
(b) On and after the date on which the performance test required to be conducted by § 60.8 is completed, you may not discharge into the atmosphere from any clinker cooler any gases which:
(1) Contain PM in excess of:
(i) 0.10 pound per ton of feed (dry basis) to the kiln if construction, reconstruction, or modification of the clinker cooler commenced after August 17, 1971 but on or before June 16, 2008.
(ii) 0.01 pound per ton of clinker on a 30-operating day rolling average if construction, reconstruction, or modification of the clinker cooler commences after June 16, 2008. An operating day includes all valid data obtained in any daily 24-hour period during which the kiln operates, and excludes any measurements made during the daily 24-hour period when the kiln was not operating.
(2) Exhibit 10 percent opacity, or greater, except that this opacity limit does not apply to any clinker cooler subject to a PM limit in paragraph (b)(1) of this section that uses a PM CEMS.
(3) If the kiln and clinker cooler exhaust are combined for energy efficiency purposes and sent to a single control device, the appropriate kiln PM limit may be adjusted using the procedures in § 63.1343(b) of this chapter.
(4) If the kiln has a separate alkali bypass stack, you must combine the PM emissions from the bypass stack with the PM emissions from the main kiln exhaust to determine total PM emissions.
(c) On and after the date on which the performance test required to be conducted by § 60.8 is completed, you may not discharge into the atmosphere from any affected facility other than the kiln and clinker cooler any gases which exhibit 10 percent opacity, or greater.
(d) If you have an affected source subject to this subpart with a different emission limit or requirement for the same pollutant under another regulation in title 40 of this chapter, you must comply with the most stringent emission limit or requirement and are not subject to the less stringent requirement.
[75 FR 55034, Sept. 9, 2010]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-05-16; vol. 79 # 95 - Friday, May 16, 2014
    1. 79 FR 28439 - Quality Assurance Requirements for Continuous Opacity Monitoring Systems at Stationary Sources
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on November 12, 2014.
      40 CFR Part 60

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7450 to 7459 - Repealed.

§ 7470 - Congressional declaration of purpose

§ 7471 - Plan requirements

§ 7472 - Initial classifications

§ 7473 - Increments and ceilings

§ 7474 - Area redesignation

§ 7475 - Preconstruction requirements

§ 7476 - Other pollutants

§ 7477 - Enforcement

§ 7478 - Period before plan approval

§ 7479 - Definitions

§ 7491 - Visibility protection for Federal class I areas

§ 7492 - Visibility

§ 7501 - Definitions

§ 7502 - Nonattainment plan provisions in general

§ 7503 - Permit requirements

§ 7504 - Planning procedures

§ 7505 - Environmental Protection Agency grants

§ 7505a - Maintenance plans

§ 7506 - Limitations on certain Federal assistance

§ 7506a - Interstate transport commissions

§ 7507 - New motor vehicle emission standards in nonattainment areas

§ 7508 - Guidance documents

§ 7509 - Sanctions and consequences of failure to attain

§ 7509a - International border areas

§ 7511 - Classifications and attainment dates

§ 7511a - Plan submissions and requirements

§ 7511b - Federal ozone measures

§ 7511c - Control of interstate ozone air pollution

§ 7511d - Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

§ 7511e - Transitional areas

§ 7511f - NO

§ 7512 - Classification and attainment dates

§ 7512a - Plan submissions and requirements

§ 7513 - Classifications and attainment dates

§ 7513a - Plan provisions and schedules for plan submissions

§ 7513b - Issuance of RACM and BACM guidance

§ 7514 - Plan submission deadlines

§ 7514a - Attainment dates

§ 7515 - General savings clause

§ 7521 - Emission standards for new motor vehicles or new motor vehicle engines

§ 7522 - Prohibited acts

§ 7523 - Actions to restrain violations

§ 7524 - Civil penalties

§ 7525 - Motor vehicle and motor vehicle engine compliance testing and certification

§ 7541 - Compliance by vehicles and engines in actual use

§ 7542 - Information collection

§ 7543 - State standards

§ 7544 - State grants

§ 7545 - Regulation of fuels

§ 7546 - Renewable fuel

§ 7547 - Nonroad engines and vehicles

§ 7548 - Study of particulate emissions from motor vehicles

§ 7549 - High altitude performance adjustments

§ 7550 - Definitions

§ 7551 - Omitted

§ 7552 - Motor vehicle compliance program fees

§ 7553 - Prohibition on production of engines requiring leaded gasoline

§ 7554 - Urban bus standards

§ 7571 - Establishment of standards

§ 7572 - Enforcement of standards

§ 7573 - State standards and controls

§ 7574 - Definitions

§ 7581 - Definitions

§ 7582 - Requirements applicable to clean-fuel vehicles

§ 7583 - Standards for light-duty clean-fuel vehicles

§ 7584 - Administration and enforcement as per California standards

§ 7585 - Standards for heavy-duty clean-fuel vehicles (GVWR above 8,500 up to 26,000 lbs.)

§ 7586 - Centrally fueled fleets

§ 7587 - Vehicle conversions

§ 7588 - Federal agency fleets

§ 7589 - California pilot test program

§ 7590 - General provisions

§ 7601 - Administration

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 60 after this date.

  • 2014-05-16; vol. 79 # 95 - Friday, May 16, 2014
    1. 79 FR 28439 - Quality Assurance Requirements for Continuous Opacity Monitoring Systems at Stationary Sources
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on November 12, 2014.
      40 CFR Part 60