40 CFR 61.151 - Standard for inactive waste disposal sites for asbestos mills and manufacturing and fabricating operations.

There is 1 rule appearing in the Federal Register for 40 CFR 61. Select the tab below to view, or View eCFR (GPOAccess)
§ 61.151
Standard for inactive waste disposal sites for asbestos mills and manufacturing and fabricating operations.
Each owner or operator of any inactive waste disposal site that was operated by sources covered under § 61.142, 61.144, or 61.147 and received deposits of asbestos-containing waste material generated by the sources, shall:
(a) Comply with one of the following:
(1) Either discharge no visible emissions to the outside air from an inactive waste disposal site subject to this paragraph; or
(2) Cover the asbestos-containing waste material with at least 15 centimeters (6 inches) of compacted nonasbestos-containing material, and grow and maintain a cover of vegetation on the area adequate to prevent exposure of the asbestos-containing waste material. In desert areas where vegetation would be difficult to maintain, at least 8 additional centimeters (3 inches) of well-graded, nonasbestos crushed rock may be placed on top of the final cover instead of vegetation and maintained to prevent emissions; or
(3) Cover the asbestos-containing waste material with at least 60 centimeters (2 feet) of compacted nonasbestos-containing material, and maintain it to prevent exposure of the asbestos-containing waste; or
(4) For inactive waste disposal sites for asbestos tailings, a resinous or petroleum-based dust suppression agent that effectively binds dust to control surface air emissions may be used instead of the methods in paragraphs (a) (1), (2), and (3) of this section. Use the agent in the manner and frequency recommended for the particular asbestos tailings by the manufacturer of the dust suppression agent to achieve and maintain dust control. Obtain prior written approval of the Administrator to use other equally effective dust suppression agents. For purposes of this paragraph, any used, spent, or other waste oil is not considered a dust suppression agent.
(b) Unless a natural barrier adequately deters access by the general public, install and maintain warning signs and fencing as follows, or comply with paragraph (a)(2) or (a)(3) of this section.
(1) Display warning signs at all entrances and at intervals of 100 m (328 ft) or less along the property line of the site or along the perimeter of the sections of the site where asbestos-containing waste material was deposited. The warning signs must:
(i) Be posted in such a manner and location that a person can easily read the legend; and
(ii) Conform to the requirements for 51 cm×36 cm (20″×14″) upright format signs specified in 29 CFR 1910.145(d)(4) and this paragraph; and
(iii) Display the following legend in the lower panel with letter sizes and styles of a visibility at least equal to those specified in this paragraph.
Legend Notation
Asbestos Waste Disposal Site 2.5 cm (1 inch) Sans Serif, Gothic or Block
Do Not Create Dust 1.9 cm (3/4 inch) Sans Serif, Gothic or Block
Breathing Asbestos is Hazardous to Your Health 14 Point Gothic.
Spacing between any two lines must be at least equal to the height of the upper of the two lines.
(2) Fence the perimeter of the site in a manner adequate to deter access by the general public.
(3) When requesting a determination on whether a natural barrier adequately deters public access, supply information enabling the Administrator to determine whether a fence or a natural barrier adequately deters access by the general public.
(c) The owner or operator may use an alternative control method that has received prior approval of the Administrator rather than comply with the requirements of paragraph (a) or (b) of this section.
(d) Notify the Administrator in writing at least 45 days prior to excavating or otherwise disturbing any asbestos-containing waste material that has been deposited at a waste disposal site under this section, and follow the procedures specified in the notification. If the excavation will begin on a date other than the one contained in the original notice, notice of the new start date must be provided to the Administrator at least 10 working days before excavation begins and in no event shall excavation begin earlier than the date specified in the original notification. Include the following information in the notice:
(1) Scheduled starting and completion dates.
(2) Reason for disturbing the waste.
(3) Procedures to be used to control emissions during the excavation, storage, transport, and ultimate disposal of the excavated asbestos-containing waste material. If deemed necessary, the Administrator may require changes in the emission control procedures to be used.
(4) Location of any temporary storage site and the final disposal site.
(e) Within 60 days of a site becoming inactive and after the effective date of this subpart, record, in accordance with State law, a notation on the deed to the facility property and on any other instrument that would normally be examined during a title search; this notation will in perpetuity notify any potential purchaser of the property that:
(1) The land has been used for the disposal of asbestos-containing waste material;
(2) The survey plot and record of the location and quantity of asbestos-containing waste disposed of within the disposal site required in § 61.154(f) have been filed with the Administrator; and
(3) The site is subject to 40 CFR part 61, subpart M.
[49 FR 13661, Apr. 5, 1984, as amended at 53 FR 36972, Sept. 23, 1988. Redesignated and amended at 55 FR 48429, Nov. 20, 1990]

Title 40 published on 2012-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-01-11; vol. 78 # 8 - Friday, January 11, 2013
    1. 78 FR 2333 - Approval of the Clean Air Act, Section 112(l), Authority for Hazardous Air Pollutants: Asbestos Management and Control; State of New Hampshire Department of Environmental Services
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule.
      This direct final rule will be effective March 12, 2013, unless EPA receives adverse comments by February 11, 2013. If adverse comments are received, EPA will publish a timely withdrawal of the direct final rule in the Federal Register informing the public that the rule will not take effect. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of March 12, 2013.
      40 CFR Parts 61 and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S.C. : Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7601 - Administration

§ 7602 - Definitions

Title 40 published on 2012-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 61 after this date.

  • 2013-01-11; vol. 78 # 8 - Friday, January 11, 2013
    1. 78 FR 2333 - Approval of the Clean Air Act, Section 112(l), Authority for Hazardous Air Pollutants: Asbestos Management and Control; State of New Hampshire Department of Environmental Services
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule.
      This direct final rule will be effective March 12, 2013, unless EPA receives adverse comments by February 11, 2013. If adverse comments are received, EPA will publish a timely withdrawal of the direct final rule in the Federal Register informing the public that the rule will not take effect. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of March 12, 2013.
      40 CFR Parts 61 and 63