§ 62.14105 Requirements for municipal waste combustor operator training and certification.
The owner or operator of an affected facility must comply with the municipal waste combustor operator training and certification requirements listed in paragraphs (a) through (g) of this section. For affected facilities, compliance with the municipal waste combustor operator training and certification requirements specified under paragraphs (a), (b), (d), and (g) of this section must be no later than 12 months after the effective date of this subpart.
(a) Each chief facility operator and shift supervisor must obtain and maintain a current provisional operator certification from either the American Society of Mechanical Engineers QRO-1-1994 or a State certification program in Connecticut and Maryland (if the affected facility is located in either of the respective States). If ASME certification is chosen, proceed in accordance with ASME QRO-1-1994, Standard for the Qualification and Certification of Resource Recovery Facility Operators. The Director of the Federal Register approves this incorporation by reference in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. You may obtain a copy from the American Society of Mechanical Engineers, Service Center, 22 Law Drive, Post Office Box 2900, Fairfield, NJ 07007. You may inspect a copy at the Office of Air Quality Planning and Standards Air Docket, EPA, Mutual Building, Room 540, 411 West Chapel Hill Street, Durham, NC 27701 or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
(b) Each chief facility operator and shift supervisor must have completed full certification or must have scheduled a full certification exam with either the American Society of Mechanical Engineers QRO-1-1994 or a State certification program in Connecticut and Maryland (if the affected facility is located in either of the respective States). If ASME certification is chosen, proceed in accordance with ASME QRO-1-1994, Standard for the Qualification and Certification of Resource Recovery Facility Operators. The Director of the Federal Register approves this incorporation by reference in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. You may obtain a copy from the American Society of Mechanical Engineers, Service Center, 22 Law Drive, Post Office Box 2900, Fairfield, NJ 07007. You may inspect a copy at the Office of Air Quality Planning and Standards Air Docket, EPA, Mutual Building, Room 540, 411 West Chapel Hill Street, Durham, NC 27701 or at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call 202-741-6030, or go to: http://www.archives.gov/federal_register/code_of_federal_regulations/ibr_locations.html.
(c) The owner or operator of an affected facility must not allow the facility to be operated at any time unless one of the following persons is on duty at the affected facility: a fully certified chief facility operator; a provisionally certified chief facility operator who is scheduled to take the full certification exam no later than 12 months after the effective date of this subpart; a fully certified shift supervisor; or a provisionally certified shift supervisor who is scheduled to take the full certification exam no later than 12 months after the effective date of this subpart. If one of the persons listed in this paragraph must leave the affected facility during their operating shift, a provisionally certified control room operator who is onsite at the affected facility may fulfill the requirement in this paragraph.
(d)
(1) Each chief facility operator, shift supervisor, and control room operator at an affected facility must complete the EPA municipal waste combustor operator training course or the State municipal waste combustor operator training course in Connecticut (if the affected facility is located in Connecticut).
(2) The requirement specified in this paragraph does not apply to chief facility operators, shift supervisors, and control room operators who have obtained full certification from the American Society of Mechanical Engineers on or before the effective date of this subpart. The owner or operator of an affected facility may request that the EPA Administrator waive the requirement specified in this paragraph for chief facility operators, shift supervisors, and control room operators who have obtained provisional certification from the American Society of Mechanical Engineers on or before the effective date of this subpart.
(e) The owner or operator of an affected facility must develop and update on a yearly basis a site-specific operating manual that must, at a minimum, address the elements of municipal waste combustor unit operation specified in paragraphs (e)(1) through (e)(11) of this section.
(1) A summary of the applicable standards under this subpart;
(2) A description of basic combustion theory applicable to a municipal waste combustor unit;
(3) Procedures for receiving, handling, and feeding municipal solid waste;
(4) Procedures for municipal waste combustor unit startup, shutdown, and malfunction;
(5) Procedures for maintaining proper combustion air supply levels;
(6) Procedures for operating the municipal waste combustor unit within the standards established under this subpart;
(7) Procedures for responding to periodic upset or off-specification conditions;
(8) Procedures for minimizing particulate matter carryover;
(9) Procedures for handling ash;
(10) Procedures for monitoring municipal waste combustor unit emissions; and
(11) Reporting and recordkeeping procedures.
(f) The owner or operator of an affected facility must establish a training program to review the operating manual according to the schedule specified in paragraphs (f)(1) and (f)(2) of this section with each person who has responsibilities affecting the operation of an affected facility including, but not limited to, chief facility operators, shift supervisors, control room operators, ash handlers, maintenance personnel, and crane/load handlers.
(1) Each person specified in paragraph (f) of this section must undergo initial training no later than the date specified in paragraph (f)(1)(i) or (f)(1)(ii) of this section, whichever is later.
(i) The date prior to the day the person assumes responsibilities affecting municipal waste combustor unit operation; or
(ii) The date 12 months after the effective date of this subpart.
(2) Annually, following the initial review required by paragraph (f)(1) of this section.
(g) The operating manual required by paragraph (e) of this section must be kept in a location readily accessible to each person required to undergo training under paragraph (f) of this section. The operating manual and records of training must be available for inspection by the EPA or its delegated enforcement agency upon request.
[63 FR 63202, Nov. 12, 1998, as amended at 69 FR 18803, Apr. 9, 2004]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-10; vol. 79 # 132 - Thursday, July 10, 2014
    1. 79 FR 39334 - Approval and Promulgation of State Air Quality Plans for Designated Facilities and Pollutants; Delaware, District of Columbia, and West Virginia; Control of Emissions From Existing Sewage Sludge Incinerator Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule.
      This rule is effective on September 8, 2014 without further notice, unless EPA receives adverse written comment by August 11, 2014. If EPA receives such comments, it will publish a timely withdrawal of the direct final rule in the Federal Register and inform the public that the rule will not take effect.
      40 CFR Part 62

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7450 to 7459 - Repealed.

§ 7470 - Congressional declaration of purpose

§ 7471 - Plan requirements

§ 7472 - Initial classifications

§ 7473 - Increments and ceilings

§ 7474 - Area redesignation

§ 7475 - Preconstruction requirements

§ 7476 - Other pollutants

§ 7477 - Enforcement

§ 7478 - Period before plan approval

§ 7479 - Definitions

§ 7491 - Visibility protection for Federal class I areas

§ 7492 - Visibility

§ 7501 - Definitions

§ 7502 - Nonattainment plan provisions in general

§ 7503 - Permit requirements

§ 7504 - Planning procedures

§ 7505 - Environmental Protection Agency grants

§ 7505a - Maintenance plans

§ 7506 - Limitations on certain Federal assistance

§ 7506a - Interstate transport commissions

§ 7507 - New motor vehicle emission standards in nonattainment areas

§ 7508 - Guidance documents

§ 7509 - Sanctions and consequences of failure to attain

§ 7509a - International border areas

§ 7511 - Classifications and attainment dates

§ 7511a - Plan submissions and requirements

§ 7511b - Federal ozone measures

§ 7511c - Control of interstate ozone air pollution

§ 7511d - Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

§ 7511e - Transitional areas

§ 7511f - NO

§ 7512 - Classification and attainment dates

§ 7512a - Plan submissions and requirements

§ 7513 - Classifications and attainment dates

§ 7513a - Plan provisions and schedules for plan submissions

§ 7513b - Issuance of RACM and BACM guidance

§ 7514 - Plan submission deadlines

§ 7514a - Attainment dates

§ 7515 - General savings clause

§ 7521 - Emission standards for new motor vehicles or new motor vehicle engines

§ 7522 - Prohibited acts

§ 7523 - Actions to restrain violations

§ 7524 - Civil penalties

§ 7525 - Motor vehicle and motor vehicle engine compliance testing and certification

§ 7541 - Compliance by vehicles and engines in actual use

§ 7542 - Information collection

§ 7543 - State standards

§ 7544 - State grants

§ 7545 - Regulation of fuels

§ 7546 - Renewable fuel

§ 7547 - Nonroad engines and vehicles

§ 7548 - Study of particulate emissions from motor vehicles

§ 7549 - High altitude performance adjustments

§ 7550 - Definitions

§ 7551 - Omitted

§ 7552 - Motor vehicle compliance program fees

§ 7553 - Prohibition on production of engines requiring leaded gasoline

§ 7554 - Urban bus standards

§ 7571 - Establishment of standards

§ 7572 - Enforcement of standards

§ 7573 - State standards and controls

§ 7574 - Definitions

§ 7581 - Definitions

§ 7582 - Requirements applicable to clean-fuel vehicles

§ 7583 - Standards for light-duty clean-fuel vehicles

§ 7584 - Administration and enforcement as per California standards

§ 7585 - Standards for heavy-duty clean-fuel vehicles (GVWR above 8,500 up to 26,000 lbs.)

§ 7586 - Centrally fueled fleets

§ 7587 - Vehicle conversions

§ 7588 - Federal agency fleets

§ 7589 - California pilot test program

§ 7590 - General provisions

§ 7601 - Administration

§ 7602 - Definitions

§ 7603 - Emergency powers

§ 7604 - Citizen suits

§ 7605 - Representation in litigation

§ 7606 - Federal procurement

§ 7607 - Administrative proceedings and judicial review

§ 7608 - Mandatory licensing

§ 7609 - Policy review

§ 7610 - Other authority

§ 7611 - Records and audit

§ 7612 - Economic impact analyses

§ 7613 - Repealed.

§ 7614 - Labor standards

§ 7615 - Separability

§ 7616 - Sewage treatment grants

§ 7617 - Economic impact assessment

§ 7618 - Repealed.

§ 7619 - Air quality monitoring

§ 7620 - Standardized air quality modeling

§ 7621 - Employment effects

§ 7622 - Employee protection

§ 7623 - Repealed.

§ 7624 - Cost of vapor recovery equipment

§ 7625 - Vapor recovery for small business marketers of petroleum products

42 U.S. Code § 7450 to 7459 - Repealed.

§ 7625a - Statutory construction

§ 7626 - Authorization of appropriations

§ 7627 - Air pollution from Outer Continental Shelf activities

§ 7628 - Demonstration grant program for local governments

§ 7641 - Noise abatement

§ 7642 - Authorization of appropriations

§ 7651 - Findings and purposes

§ 7651a - Definitions

§ 7651b - Sulfur dioxide allowance program for existing and new units

§ 7651c - Phase I sulfur dioxide requirements

§ 7651d - Phase II sulfur dioxide requirements

§ 7651e - Allowances for States with emissions rates at or below 0.80 lbs/mmBtu

§ 7651f - Nitrogen oxides emission reduction program

§ 7651g - Permits and compliance plans

§ 7651h - Repowered sources

§ 7651i - Election for additional sources

§ 7651j - Excess emissions penalty

§ 7651k - Monitoring, reporting, and recordkeeping requirements

42 U.S. Code § -

§ 7651m - Enforcement

§ 7651n - Clean coal technology regulatory incentives

42 U.S. Code § -

§ 7661 - Definitions

§ 7661a - Permit programs

§ 7661b - Permit applications

§ 7661c - Permit requirements and conditions

§ 7661d - Notification to Administrator and contiguous States

§ 7661e - Other authorities

§ 7661f - Small business stationary source technical and environmental compliance assistance program

§ 7671 - Definitions

§ 7671a - Listing of class I and class II substances

§ 7671b - Monitoring and reporting requirements

§ 7671c - Phase-out of production and consumption of class I substances

§ 7671d - Phase-out of production and consumption of class II substances

§ 7671e - Accelerated schedule

§ 7671f - Exchange authority

§ 7671g - National recycling and emission reduction program

§ 7671h - Servicing of motor vehicle air conditioners

§ 7671i - Nonessential products containing chlorofluorocarbons

§ 7671j - Labeling

§ 7671k - Safe alternatives policy

42 U.S. Code § -

§ 7671m - Relationship to other laws

§ 7671n - Authority of Administrator

42 U.S. Code § -

§ 7671p - International cooperation

§ 7671q - Miscellaneous provisions

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 62 after this date.

  • 2014-07-10; vol. 79 # 132 - Thursday, July 10, 2014
    1. 79 FR 39334 - Approval and Promulgation of State Air Quality Plans for Designated Facilities and Pollutants; Delaware, District of Columbia, and West Virginia; Control of Emissions From Existing Sewage Sludge Incinerator Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule.
      This rule is effective on September 8, 2014 without further notice, unless EPA receives adverse written comment by August 11, 2014. If EPA receives such comments, it will publish a timely withdrawal of the direct final rule in the Federal Register and inform the public that the rule will not take effect.
      40 CFR Part 62