§ 63.1102 Compliance schedule.
(a) General requirements. Affected sources, as defined in § 63.1103(a)(1)(i) for acetyl resins production, § 63.1103(b)(1)(i) for acrylic and modacrylic fiber production, § 63.1103(c)(1)(i) for hydrogen fluoride production, § 63.1103(d)(1)(i) for polycarbonate production, § 63.1103(e)(1)(i) for ethylene production, § 63.1103(f)(1)(i) for carbon black production, § 63.1103(g)(1)(i) for cyanide chemicals manufacturing, or § 63.1103(h)(1)(i) for spandex production shall comply with the appropriate provisions of this subpart and the subparts referenced by this subpart according to the schedule in paragraph (a)(1) or (2) of this section, as appropriate. Proposal and effective dates are specified in Table 1 to this section.
(1) Compliance dates for new and reconstructed sources.
(i) The owner or operator of a new or reconstructed affected source that commences construction or reconstruction after the proposal date, and that has an initial startup before the effective date of standards for an affected source, shall comply with this subpart no later than the applicable effective date in Table 1 to § 63.1102 of this section.
(ii) The owner or operator of a new or reconstructed affected source that has an initial startup after the applicable effective date in Table 1 to § 63.1102 of this section shall comply with this subpart upon startup of the source.
(iii) The owner or operator of an affected source that commences construction or reconstruction after the proposal date, but before the effective date in Table 1 to this section, shall comply with this subpart no later than the date 3 years after the effective date if the conditions in paragraphs (a)(1)(iii) (A) and (B) of this section are met.
(A) The promulgated standards are more stringent than the proposed standards.
(B) The owner or operator complies with this subpart as proposed during the 3-year period immediately after the effective date of standards for the affected source.
(2) Compliance dates for existing sources.
(i) The owner or operator of an existing affected source shall comply with the requirements of this subpart within 3 years after the effective date of standards for the affected source.
(ii) The owner or operator of an area source that increases its emissions of (or its potential to emit) HAP such that the source becomes a major source shall be subject to the relevant standards for existing sources under this subpart. Such sources shall comply with the relevant standards within 3 years of becoming a major source.
(b) [Reserved].
Table 1 to § 63.1102 —Source Category Proposal and Effective Dates
Source category Proposal date Effective date
(a) Acetal Resins Production October 14, 1998 June 29, 1999.
(b) Acrylic and Modacrylic Fibers Production October 14, 1998 June 29, 1999.
(c) Hydrogen Fluoride Production October 14, 1998 June 29, 1999.
(d) Polycarbonate Production October 14, 1998 June 29, 1999.
(e) Ethylene Production December 6, 2000 July 12, 2002.
(f) Carbon Black Production December 6, 2000 July 12, 2002.
(g) Cyanide Chemicals Manufacturing December 6, 2000 July 12, 2002.
(h) Spandex Production December 6, 2000 July 12, 2002.
[67 FR 46280, July 12, 2002]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-03-27; vol. 79 # 59 - Thursday, March 27, 2014
    1. 79 FR 17340 - National Emission Standards for Hazardous Air Pollutant Emissions: Group IV Polymers and Resins; Pesticide Active Ingredient Production; and Polyether Polyols Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final action is effective on March 27, 2014. The incorporation by reference of certain publications listed in this final rule was approved by the Director of the Federal Register as of March 27, 2014.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-07-02; vol. 79 # 127 - Wednesday, July 2, 2014
    1. 79 FR 37850 - National Emission Standards for Hazardous Air Pollutants: Off-Site Waste and Recovery Operations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule.
      Comments. Comments must be received on or before August 18, 2014. A copy of comments on the information collection provisions should be submitted to the Office of Management and Budget (OMB) on or before August 1, 2014. Public Hearing. We do not plan to conduct a public hearing unless requested. If requested, we will hold a public hearing on July 17, 2014. To request a hearing, please contact the person listed in the following FOR FURTHER INFORMATION CONTACT section by July 14, 2014.
      40 CFR Part 63