40 CFR 63.1408 - Aggregate batch vent stream provisions.

Status message

There are 6 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
§ 63.1408 Aggregate batch vent stream provisions.
(a) Emission standards. Owners or operators of aggregate batch vent streams at a new or existing affected source shall comply with either paragraph (a)(1) or (2) of this section, as appropriate. As an alternative to complying with paragraph (a)(1) or (2) of this section, an owner or operator may comply with paragraph (b) of this section.
(1) The owner or operator of an aggregate batch vent stream located at a new affected source shall:
(i) Vent all emissions of organic HAP to a flare; or
(ii) Reduce organic HAP emissions by 95 weight percent or to a concentration of 20 ppmv when using a combustion control device or to a concentration of 50 ppmv when using a non-combustion control device, whichever is less stringent, on a continuous basis.
(2) The owner or operator of an aggregate batch vent stream located at an existing affected source shall:
(i) Vent all emissions of organic HAP to a flare; or
(ii) Reduce organic HAP emissions by 83 weight percent or to a concentration of 20 ppmv when using a combustion control device or to a concentration of 50 ppmv when using a non-combustion control device, whichever is less stringent, on a continuous basis.
(b) Alternative standard. Comply with either paragraph (b)(1) or (2) of this section.
(1) Control device outlet concentration. Vent all organic HAP emissions from an aggregate batch vent stream to a combustion control device achieving an outlet organic HAP concentration of 20 ppmv or less or to a non-combustion control device achieving an outlet organic HAP concentration of 50 ppmv or less. Any aggregate batch vent streams that are not vented to a control device meeting these conditions shall be controlled in accordance with the provisions of paragraphs (a)(1) or (a)(2) of this section.
(2) Mass emission limit. Include the emissions from all aggregate batch vent streams in the compliance demonstration required for reactor batch process vents complying with the mass emission limits specified in § 63.1406(a)(1)(iii) and (a)(2)(iii), as appropriate. This compliance option may only be used when the owner or operator has elected to comply with the mass emission limit for reactor batch process vents.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-19; vol. 79 # 223 - Wednesday, November 19, 2014
    1. 79 FR 68777 - Reconsideration of Certain Startup/Shutdown Issues: National Emission Standards for Hazardous Air Pollutants From Coal- and Oil-Fired Electric Utility Steam Generating Units and Standards of Performance for Fossil-Fuel-Fired Electric Utility, Industrial-Commercial-Institutional, and Small Industrial-Commercial-Institutional Steam Generating Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; notice of final action on reconsideration.
      The effective date of the rule is November 19, 2014.
      40 CFR Parts 60 and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-11-19; vol. 79 # 223 - Wednesday, November 19, 2014
    1. 79 FR 68777 - Reconsideration of Certain Startup/Shutdown Issues: National Emission Standards for Hazardous Air Pollutants From Coal- and Oil-Fired Electric Utility Steam Generating Units and Standards of Performance for Fossil-Fuel-Fired Electric Utility, Industrial-Commercial-Institutional, and Small Industrial-Commercial-Institutional Steam Generating Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; notice of final action on reconsideration.
      The effective date of the rule is November 19, 2014.
      40 CFR Parts 60 and 63