40 CFR 63.1650 - Applicability and compliance dates.

Status message

There are 6 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
§ 63.1650 Applicability and compliance dates.
(a) This subpart applies to all new and existing ferromanganese and silicomanganese production facilities that manufacture ferromanganese or silicomanganese and are major sources or are co-located at major sources of hazardous air pollutant emissions.
(b) The following sources at a ferromanganese and silicomanganese production facility are subject to this subpart:
(1) Open submerged arc furnaces with a furnace power input of 22 MW or less when producing ferromanganese.
(2) Open submerged arc furnaces with a furnace power input greater than 22 MW when producing ferromanganese.
(3) Open submerged arc furnaces with a furnace power input greater than 25 MW when producing silicomanganese.
(4) Open submerged arc furnaces with a furnace power input of 25 MW or less when producing silicomanganese.
(5) Semi-sealed submerged arc furnaces when producing ferromanganese.
(6) Metal oxygen refining (MOR) process.
(7) Crushing and screening operations.
(8) Fugitive dust sources.
(c) A new affected source is one for which construction or reconstruction commenced after August 4, 1998.
(d) The following table specifies which provisions of subpart A of this part apply to owners and operators of ferromanganese and silicomanganese production facilities subject to this subpart:
General Provisions Applicability to Subpart XXX
Reference, Subpart A General Provisions Applies to Subpart XXX, §§ 63.1620-63.1679 Comment
63.1-63.5 Yes
63.6(a)-(g), (i)-(j) Yes
63.6(h)(1)-(h)(6), (h)(8)-(h)(9) Yes
63.7(h)(7) No § 63.6(h)(7), use of continuous opacity monitoring system, not applicable.
63.7 Yes
63.8 Yes
63.9 Yes Notification of performance test results changed to a 30-day notification period.
63.10 Yes Allow changes in dates by which periodic reports are submitted by mutual agreement between the owner or operator and the State to occur any time after the source's compliance date.
63.11 No Flares will not be used to comply with the emission limits.
63.12-63.15 Yes
(e) Compliance dates.
(1) Each owner or operator of an existing affected source must comply with the requirements of this subpart no later than November 21, 2001.
(2) Each owner or operator of a new or reconstructed affected source that commences construction or reconstruction after August 4, 1998, must comply with the requirements of this subpart by May 20, 1999 or upon startup of operations, whichever is later.
[64 FR 27458, May 20, 1999, as amended at 66 FR 16012, Mar. 22, 2001]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-03-27; vol. 79 # 59 - Thursday, March 27, 2014
    1. 79 FR 17340 - National Emission Standards for Hazardous Air Pollutant Emissions: Group IV Polymers and Resins; Pesticide Active Ingredient Production; and Polyether Polyols Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final action is effective on March 27, 2014. The incorporation by reference of certain publications listed in this final rule was approved by the Director of the Federal Register as of March 27, 2014.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-07-02; vol. 79 # 127 - Wednesday, July 2, 2014
    1. 79 FR 37850 - National Emission Standards for Hazardous Air Pollutants: Off-Site Waste and Recovery Operations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule.
      Comments. Comments must be received on or before August 18, 2014. A copy of comments on the information collection provisions should be submitted to the Office of Management and Budget (OMB) on or before August 1, 2014. Public Hearing. We do not plan to conduct a public hearing unless requested. If requested, we will hold a public hearing on July 17, 2014. To request a hearing, please contact the person listed in the following FOR FURTHER INFORMATION CONTACT section by July 14, 2014.
      40 CFR Part 63