§ 63.2987 What must my operation, maintenance, and monitoring (OMM) plan include?
(a) You must prescribe the monitoring that will be performed to ensure compliance with these emission limitations. Minimum monitoring requirements are listed in table 1 of this subpart. Your plan must specify the items listed in paragraphs (a)(1) through (3) of this section:
(1) Each process and control device to be monitored, the type of monitoring device that will be used, and the operating parameters that will be monitored.
(2) A monitoring schedule that specifies the frequency that the parameter values will be determined and recorded.
(3) The operating limits or ranges for each parameter that represent continuous compliance with the emission limits in § 63.2983. Operating limits and ranges must be based on values of the monitored parameters recorded during performance tests.
(b) You must establish routine and long-term maintenance and inspection schedules for each control device. You must incorporate in the schedules the control device manufacturer's recommendations for maintenance and inspections or equivalent procedures. If you use a thermal oxidizer, the maintenance schedule must include procedures for annual or more frequent inspection of the thermal oxidizer to ensure that the structural and design integrity of the combustion chamber is maintained. At a minimum, you must meet the requirements of paragraphs (b)(1) through (10) of this section:
(1) Inspect all burners, pilot assemblies, and pilot sensing devices for proper operation. Clean pilot sensor if necessary.
(2) Ensure proper adjustment of combustion air and adjust if necessary.
(3) Inspect, when possible, all internal structures (such as baffles) to ensure structural integrity per the design specifications.
(4) Inspect dampers, fans, and blowers for proper operation.
(5) Inspect motors for proper operation.
(6) Inspect, when possible, combustion chamber refractory lining. Clean and repair or replace lining if necessary.
(7) Inspect the thermal oxidizer shell for proper sealing, corrosion, and hot spots.
(8) For the burn cycle that follows the inspection, document that the thermal oxidizer is operating properly and make any necessary adjustments.
(9) Generally observe whether the equipment is maintained in good operating condition.
(10) Complete all necessary repairs as soon as practicable.
(c) You must establish procedures for responding to operating parameter deviations. At a minimum, the procedures must include the information in paragraphs (c)(1) through (3) of this section.
(1) Procedures for determining the cause of the operating parameter deviation.
(2) Actions for correcting the deviation and returning the operating parameters to the allowable ranges or limits.
(3) Procedures for recording the date and time that the deviation began and ended, and the times corrective actions were initiated and completed.
(d) Your plan must specify the recordkeeping procedures to document compliance with the emissions and operating limits. Table 1 of this subpart establishes the minimum recordkeeping requirements.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-10-08; vol. 79 # 195 - Wednesday, October 8, 2014
    1. 79 FR 60898 - National Emission Standards for Hazardous Air Pollutants: Generic Maximum Achievable Control Technology Standards; and Manufacture of Amino/Phenolic Resins
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final action is effective on October 8, 2014.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-10-15; vol. 79 # 199 - Wednesday, October 15, 2014
    1. 79 FR 61843 - National Emission Standards for Hazardous Air Pollutants: Ferroalloys Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Supplemental notice of proposed rulemaking; correction.
      This correction is made on October 15, 2014. Public Hearing. If anyone contacts the EPA requesting a public hearing by October 20, 2014, the EPA will hold a public hearing on October 30, 2014 from 1:00 p.m. [Eastern Standard Time] to 5:00 p.m. [Eastern Standard Time] at the U.S. Environmental Protection Agency building located at 109 T.W. Alexander Drive, Research Triangle Park, NC 27711. If the EPA holds a public hearing, the EPA will keep the record of the hearing open for 30 days after completion of the hearing to provide an opportunity for submission of rebuttal and supplementary information.
      40 CFR Part 63