§ 63.5130 When must I comply?
(a) For an existing affected source, the compliance date is 3 years after June 10, 2002.
(b) If you own or operate a new affected source subject to the provisions of this subpart, you must comply immediately upon start-up of the affected source, or by June 10, 2002, whichever is later.
(c) Affected sources which have undergone reconstruction are subject to the requirements for new affected sources.
(d) The initial compliance period begins on the applicable compliance date specified in paragraph (a) or (b) of this section and ends on the last day of the 12th month following the compliance date. If the compliance date falls on any day other than the first day of a month, then the initial compliance period extends through that month plus the next 12 months.
(e) For the purpose of demonstrating continuous compliance, a compliance period consists of 12 months. Each month after the end of the initial compliance period described in paragraph (d) of this section is the end of a compliance period consisting of that month and the preceding 11 months.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70102 - National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Texas
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on January 26, 2015 without further notice, unless EPA receives relevant adverse comment by December 26, 2014. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that this rule will not take effect.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-12-12; vol. 79 # 239 - Friday, December 12, 2014
    1. 79 FR 73872 - Phosphoric Acid Manufacturing and Phosphate Fertilizer Production RTR and Standards of Performance for Phosphate Processing; Extension of Comment Period
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of proposed rulemaking; extension of public comment period.
      Comments. The public comment period for the proposed rule published in the Federal Register on November 7, 2014, (79 FR 66512) is being extended for 30 days to January 21, 2015.
      40 CFR Parts 60 and 63