§ 63.7495 When do I have to comply with this subpart?
(a) If you have a new or reconstructed boiler or process heater, you must comply with this subpart by November 12, 2004 or upon startup of your boiler or process heater, whichever is later.
(b) If you have an existing boiler or process heater, you must comply with this subpart no later than September 13, 2007.
(c) If you have an area source that increases its emissions or its potential to emit such that it becomes a major source of HAP, paragraphs (c)(1) and (2) of this section apply to you.
(1) Any new or reconstructed boiler or process heater at the existing facility must be in compliance with this subpart upon startup.
(2) Any existing boiler or process heater at the existing facility must be in compliance with this subpart within 3 years after the facility becomes a major source.
(d) You must meet the notification requirements in § 63.7545 according to the schedule in § 63.7545 and in subpart A of this part. Some of the notifications must be submitted before you are required to comply with the emission limits and work practice standards in this subpart.

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63