§ 63.7822 What test methods and other procedures must I use to demonstrate initial compliance with the emission limits for particulate matter?
(a) You must conduct each performance test that applies to your affected source according to the requirements in § 63.7(e)(1) and the conditions detailed in paragraphs (b) through (i) of this section.
(b) To determine compliance with the applicable emission limit for particulate matter in Table 1 to this subpart, follow the test methods and procedures in paragraphs (b)(1) and (2) of this section.
(1) Determine the concentration of particulate matter according to the following test methods in appendix A to part 60 of this chapter:
(i) Method 1 to select sampling port locations and the number of traverse points. Sampling ports must be located at the outlet of the control device and prior to any releases to the atmosphere.
(ii) Method 2, 2F, or 2G to determine the volumetric flow rate of the stack gas.
(iii) Method 3, 3A, or 3B to determine the dry molecular weight of the stack gas.
(iv) Method 4 to determine the moisture content of the stack gas.
(v) Method 5, 5D, or 17, as applicable, to determine the concentration of particulate matter (front half filterable catch only).
(2) Collect a minimum sample volume of 60 dry standard cubic feet (dscf) of gas during each particulate matter test run. Three valid test runs are needed to comprise a performance test.
(c) For each sinter plant windbox exhaust stream, you must complete the requirements of paragraphs (c)(1) and (2) of this section:
(1) Follow the procedures in your operation and maintenance plan for measuring and recording the sinter production rate for each test run in tons per hour; and
(2) Compute the process-weighted mass emissions (Ep) for each test run using Equation 1 of this section as follows:
Where:
Ep = Process-weighted mass emissions of particulate matter, lb/ton;
C = Concentration of particulate matter, grains per dry standard cubic foot (gr/dscf);
Q = Volumetric flow rate of stack gas, dry standard cubic foot per hour (dscf/hr);
P = Production rate of sinter during the test run, tons/hr; and
K = Conversion factor, 7,000 grains per pound (gr/lb).
(d) If you apply two or more control devices in parallel to emissions from a sinter plant discharge end or a BOPF, compute the average flow-weighted concentration for each test run using Equation 2 of this section as follows:
Where:
Cw = Flow-weighted concentration, gr/dscf;
Ci = Concentration of particulate matter from exhaust stream “i”, gr/dscf; and
Qi = Volumetric flow rate of effluent gas from exhaust stream “i”, dry standard cubic foot per minute (dscfm).
(e) For a control device applied to emissions from a blast furnace casthouse, sample for an integral number of furnace tapping operations sufficient to obtain at least 1 hour of sampling for each test run.
(f) For a primary emission control device applied to emissions from a BOPF with a closed hood system, sample only during the primary oxygen blow and do not sample during any subsequent reblows. Continue sampling for each run for an integral number of primary oxygen blows.
(g) For a primary emission control system applied to emissions from a BOPF with an open hood system and for a control device applied solely to secondary emissions from a BOPF, you must complete the requirements of paragraphs (g)(1) and (2) of this section:
(1) Sample only during the steel production cycle. Conduct sampling under conditions that are representative of normal operation. Record the start and end time of each steel production cycle and each period of abnormal operation; and
(2) Sample for an integral number of steel production cycles. The steel production cycle begins when the scrap is charged to the furnace and ends 3 minutes after the slag is emptied from the vessel into the slag pot.
(h) For a control device applied to emissions from BOPF shop ancillary operations (hot metal transfer, skimming, desulfurization, or ladle metallurgy), sample only when the operation(s) is being conducted.
(i) Subject to approval by the permitting authority, you may conduct representative sampling of stacks when there are more than three stacks associated with a process.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-08-15; vol. 79 # 158 - Friday, August 15, 2014
    1. 79 FR 48072 - NESHAP for Reciprocating Internal Combustion Engines; NSPS for Stationary Internal Combustion Engines
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of final decision on reconsideration.
      Effective August 15, 2014. Any petitions for review of the letters announcing the EPA's decision not to propose changes to the regulations in response to the public comments received on the three issues under reconsideration described in this Notice must be filed in the U.S. Court of Appeals for the District of Columbia Circuit by October 14, 2014.
      40 CFR Parts 60 and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-08-15; vol. 79 # 158 - Friday, August 15, 2014
    1. 79 FR 48072 - NESHAP for Reciprocating Internal Combustion Engines; NSPS for Stationary Internal Combustion Engines
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of final decision on reconsideration.
      Effective August 15, 2014. Any petitions for review of the letters announcing the EPA's decision not to propose changes to the regulations in response to the public comments received on the three issues under reconsideration described in this Notice must be filed in the U.S. Court of Appeals for the District of Columbia Circuit by October 14, 2014.
      40 CFR Parts 60 and 63