§ 63.7918 How do I demonstrate continuous compliance with the emissions limitations and work practice standards for transfer systems?
(a) You must demonstrate continuous compliance with the emissions limitations and work practice standards in § 63.7915 applicable to your affected transfer system by meeting the requirements in paragraphs (b) through (e) of this section as applicable to your transfer systems.
(b) You must demonstrate continuous compliance for each individual drain system using controls according to § 63.7915(b) by meeting the requirements in paragraphs (b)(1) through (5) of this section.
(1) Operating and maintaining the air emission controls for individual drain systems according to the requirements in § 63.962.
(2) Visually inspecting each individual drain system at least annually according to the requirements in § 63.964(a).
(3) Repairing defects according to the requirements in § 63.964(b).
(4) Recording the information specified in § 63.965(a).
(5) Keeping records to document compliance with the requirements of this subpart according to the requirements in § 63.7952.
(c) You must demonstrate continuous compliance for each transfer system using covers according to § 63.7915(c)(1) by meeting the requirements in paragraphs (c)(1) through (4) of this section.
(1) Operating and maintaining each cover and its closure devices according to the requirements in § 63.689(d)(1) through (5).
(2) Performing inspections of each cover and its closure devices for defects at least annually according to the requirements in § 63.695(d)(1) through (5).
(3) Repairing defects according to the requirements in § 63.695(5)
(4) Keeping records to document compliance with the requirements of this subpart according to the requirements in § 63.7952.
(d) You must demonstrate continuous compliance for each transfer system that consists of hard piping according to § 63.7915(c)(2) by meeting the requirements in paragraphs (d)(1) through (4) of this section.
(1) Operating and maintaining the pipeline to ensure that all joints or seams between the pipe sections remain permanently or semi-permanently sealed (e.g., a welded joint between two sections of metal pipe or a bolted and gasketed flange).
(2) Inspecting the pipeline for defects at least annually according to the requirements in § 63.7917(c).
(3) Repairing defects according to the requirements in § 63.7917(e).
(4) Keeping records to document compliance with the requirements of this subpart according to the requirements in § 63.7952.
(e) You must demonstrate continuous compliance for each transfer system that is enclosed and vented to a control device according to § 63.7915(c)(3) by meeting the requirements in paragraphs (e)(1) through (5) of this section.
(1) Operating and maintaining the enclosure to ensure that the internal pressure in the vapor headspace in the enclosure is maintained continuously at a level less than atmospheric pressure when the control device is operating.
(2) Inspecting the enclosure and its closure devices for defects at least annually according to the requirements in § 63.7918(d).
(3) Repairing defects according to the requirements in § 63.7918(e).
(4) Meeting each applicable requirement for demonstrating continuous compliance with the emission limitations and work practice standards for a closed vent system and control device in § 63.7928.
(5) Keeping records to document compliance with the requirements according to the requirements in § 63.7952.
[68 FR 58190, Oct. 8, 2003, as amended at 71 FR 69018, Nov. 29, 2006]

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70102 - National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Texas
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on January 26, 2015 without further notice, unless EPA receives relevant adverse comment by December 26, 2014. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that this rule will not take effect.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-12-12; vol. 79 # 239 - Friday, December 12, 2014
    1. 79 FR 73872 - Phosphoric Acid Manufacturing and Phosphate Fertilizer Production RTR and Standards of Performance for Phosphate Processing; Extension of Comment Period
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of proposed rulemaking; extension of public comment period.
      Comments. The public comment period for the proposed rule published in the Federal Register on November 7, 2014, (79 FR 66512) is being extended for 30 days to January 21, 2015.
      40 CFR Parts 60 and 63