§ 80.1155 What are the additional requirements for a producer of cellulosic biomass ethanol or waste derived ethanol?
(a) A producer of cellulosic biomass ethanol or waste derived ethanol (hereinafter referred to as “ethanol producer” under this section) is required to arrange for an independent third party to review the records required in § 80.1151(c) and provide the ethanol producer with a written verification that the records support a claim that:
(1) The ethanol producer's facility is a facility that has the capability of producing cellulosic biomass ethanol as defined in § 80.1101(a) or waste derived ethanol as defined in § 80.1101(b); and
(2) The ethanol producer produces cellulosic biomass ethanol as defined in § 80.1101(a) or waste derived ethanol as defined in § 80.1101(b).
(b) The verifications required under paragraph (a) of this section must be conducted by a Professional Chemical Engineer who is based in the United States and is licensed by the appropriate state agency, unless the ethanol producer is a foreign producer subject to § 80.1166.
(c) To be considered an independent third party under paragraph (a) of this section:
(1) The third party shall not be operated by the ethanol producer or any subsidiary of employee of the ethanol producer.
(2) The third party shall be free from any interest in the ethanol producer's business.
(3) The ethanol producer shall be free from any interest in the third party's business.
(4) Use of a third party that is debarred, suspended, or proposed for debarment pursuant to the Government-wide Debarment and Suspension regulations, 40 CFR part 32, or the Debarment, Suspension and Ineligibility provisions of the Federal Acquisition Regulations, 48 CFR, part 9, subpart 9.4, shall be deemed noncompliance with the requirements of this section.
(d) The ethanol producer must obtain the written verification required under paragraph (a)(1) of this section by February 28 of the year following the first year in which the ethanol producer claims to be producing cellulosic biomass ethanol or waste derived ethanol.
(e) The verification in paragraph (a)(2) of this section is required for each calendar year that the ethanol producer claims to be producing cellulosic biomass ethanol or waste derived ethanol. The ethanol producer must obtain the written verification required under paragraph (a)(2) of this section by February 28 for the previous calendar year.
(f) The ethanol producer must retain records of the verifications required under paragraph (a) of this section, as required in § 80.1151(c)(5).
(g) The independent third party shall retain all records pertaining to the verification required under this section for a period of five years from the date of creation and shall deliver such records to the Administrator upon request.
[72 FR 24000, May 1, 2007]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-05-22; vol. 79 # 99 - Thursday, May 22, 2014
    1. 79 FR 29362 - Approval of States' Requests To Relax the Federal Reid Vapor Pressure Volatility Standard in Florida, and the Raleigh-Durham-Chapel Hill and Greensboro/Winston-Salem/High Point Areas in North Carolina
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Withdrawal of direct final rule.
      The direct final rule published at 79 FR 17889 on March 31, 2014, is withdrawn as of May 22, 2014.
      40 CFR Part 80

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 80 after this date.

  • 2014-05-22; vol. 79 # 99 - Thursday, May 22, 2014
    1. 79 FR 29362 - Approval of States' Requests To Relax the Federal Reid Vapor Pressure Volatility Standard in Florida, and the Raleigh-Durham-Chapel Hill and Greensboro/Winston-Salem/High Point Areas in North Carolina
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Withdrawal of direct final rule.
      The direct final rule published at 79 FR 17889 on March 31, 2014, is withdrawn as of May 22, 2014.
      40 CFR Part 80