§ 86.1238-96 Hot soak test.
(a)
(1) Gasoline- and methanol-fueled vehicles. For gasoline- and methanol-fueled vehicles, the hot soak test shall be conducted immediately following the running loss test. However, sampling of emissions from the running loss test is not required as preparation for the hot soak test.
(2) Gaseous-fueled vehicles. Since gaseous-fueled vehicles are not required to perform a running loss test, the hot soak test shall be conducted within seven minutes after completion of the hot start exhaust test.
(b) The hot soak test may be conducted in the running loss enclosure as a continuation of that test or in a separate enclosure.
(1) If the hot soak test is conducted in the running loss enclosure, the driver may exit the enclosure after the running loss test. If exiting, the driver should use the personnel door described in § 86.1207-96(a)(2), exiting as quickly as possible with a minimum disturbance to the system. The final hydrocarbon and methanol concentration for the running loss test, measured in § 86.1234-96(g)(1)(xx), shall be the initial hydrocarbon and methanol concentration (time=0 minutes) CHCi and CCH [=E T=0362]3 OHi, for the hot soak test.
(2) If the vehicle must be moved to a different enclosure, the following steps must be taken:
(i) The enclosure for the hot soak test shall be purged for several minutes prior to completion of the running loss test. Warning: If at any time the concentration of hydrocarbons, of methanol, or of methanol and hydrocarbons exceeds 15,000 ppm C the enclosure should be immediately purged. This concentration provides at least a 4:1 safety factor against the lean flammability limit.
(ii) The FID hydrocarbon analyzer shall be zeroed and spanned immediately prior to the test.
(iii) Fresh impingers shall be installed in the methanol sample collection system immediately prior to the start of the test, if applicable.
(iv) If not already on, the mixing fan(s) shall be turned on at this time. Throughout the hot soak test, the mixing fan(s) shall circulate the air at a rate of 0.8±0.2 cfm per cubic foot of the nominal enclosure volume.
(v) Begin sampling as follows:
(A) Analyze the enclosure atmosphere for hydrocarbons and record. This is the initial (time = 0 minutes) hydrocarbon concentration, CHCi, required in § 86.1243. Hydrocarbon emissions may be sampled continuously during the test period.
(B) Analyze the enclosure atmosphere for methanol, if applicable, and record. The methanol sampling must start simultaneously with the initiation of the hydrocarbon analysis and continue for 4.0±0.5 minutes. This is the initial (time=0 minutes) methanol concentration, CCH [=E T=0362]3 OHi, required in § 86.1243. Record the time elapsed during this analysis. If the 4-minute sample period is inadequate to collect a sample of sufficient concentration to allow accurate GC analysis, rapidly collect the methanol sample in a bag and then bubble the bag sample through the impingers at the specified flow rate. The time elapsed between collection of the bag sample and flow through the impingers should be minimized to prevent any losses.
(vi) The vehicle engine compartment cover shall be closed (if not already closed), the cooling fan shall be moved, the vehicle shall be disconnected from the dynamometer and any sampling system, and then driven at minimum throttle to the enclosure for the hot soak test. These steps should be done as quickly as possible to minimize the time needed to start the hot soak test.
(vii) The vehicle's engine must be stopped before any part of the vehicle enters the enclosure.
(viii) The vehicle shall enter the enclosure; the enclosure doors shall be closed and sealed within 2 minutes of engine shutdown and within seven minutes after the end of the running loss test.
(ix) The test vehicle windows and any luggage compartments shall be opened (if not already open). The vehicle engine compartment cover shall be closed (if not already closed).
(c) [Reserved]
(d) The temperature recording system shall be started and the time of engine shutoff shall be noted on the evaporative emission hydrocarbon data recording system.
(e) For the first 5 minutes of the hot soak test, the ambient temperature shall be maintained at 95±10 °F. For the remainder of the hot soak test, the ambient temperature shall be maintained at 95±5 °F (95±2 °F on average).
(f) The 60±0.5 minute hot soak begins when the enclosure doors are sealed (or when the running loss test ends, if the hot soak test is conducted in the running loss enclosure).
(g) The FID (or HFID) hydrocarbon analyzer shall be zeroed and spanned immediately prior to the end of the test.
(h) Fresh impingers shall be installed in the methanol collection system immediately prior to the end of the test, if applicable.
(i) [Reserved]
(j) At the end of the 60±0.5 minute test period:
(1) Analyze the enclosure atmosphere for hydrocarbons and record. This is the final (time=60 minutes) hydrocarbon concentration, CHCf, required in § 86.1243.
(2) Analyze the enclosure atmosphere for methanol and record, if applicable. The methanol sampling must start simultaneously with the initiation of the hydrocarbon analysis and continue for 4.0±0.5 minutes. This is the final (time=60 minutes) methanol concentration, CCH [=E T=0362]3 OHf, required in § 86.1243. Record the time elapsed during this analysis. If the 4-minute sample period is inadequate to collect a sample of sufficient concentration to allow accurate GC analysis, rapidly collect the methanol sample in a bag and then bubble the bag sample through the impingers at the specified flow rate. The time elapsed between collection of the bag sample and flow through the impingers should be minimized to prevent any losses.
(k) For the supplemental two-diurnal test sequence (see § 86.1230-96), the hot soak test described in § 86.1238-90 shall be conducted immediately following the dynamometer run. This test requires ambient temperatures between 68° and 86 °F at all times. The equipment and calibration specifications of §§ 86.1207-90 and 86.1207-90 may apply for this testing. Enclosures meeting the requirements of §§ 86.1207-96 and 86.1217-96 may also be used. This hot soak test is followed by two consecutive diurnal heat builds, described in § 86.1233-96(p).
(l) If the vehicle is to be tested for diurnal emissions, follow the procedure outlined in § 86.1233-96.
[58 FR 16061, Mar. 24, 1993, as amended at 59 FR 48524, Sept. 21, 1994; 60 FR 43906, Aug. 23, 1995]

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-08-08; vol. 79 # 153 - Friday, August 8, 2014
    1. 79 FR 46356 - Emergency Vehicle Rule—SCR Maintenance and Regulatory Flexibility for Nonroad Equipment
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This rule is effective on September 8, 2014.
      40 CFR Parts 86 and 1039

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

§ 7401 - Congressional findings and declaration of purpose

§ 7402 - Cooperative activities

§ 7403 - Research, investigation, training, and other activities

§ 7404 - Research relating to fuels and vehicles

§ 7405 - Grants for support of air pollution planning and control programs

§ 7406 - Interstate air quality agencies; program cost limitations

§ 7407 - Air quality control regions

§ 7408 - Air quality criteria and control techniques

§ 7409 - National primary and secondary ambient air quality standards

§ 7410 - State implementation plans for national primary and secondary ambient air quality standards

§ 7411 - Standards of performance for new stationary sources

§ 7412 - Hazardous air pollutants

§ 7413 - Federal enforcement

§ 7414 - Recordkeeping, inspections, monitoring, and entry

§ 7415 - International air pollution

§ 7416 - Retention of State authority

§ 7417 - Advisory committees

§ 7418 - Control of pollution from Federal facilities

§ 7419 - Primary nonferrous smelter orders

§ 7420 - Noncompliance penalty

§ 7421 - Consultation

§ 7422 - Listing of certain unregulated pollutants

§ 7423 - Stack heights

§ 7424 - Assurance of adequacy of State plans

§ 7425 - Measures to prevent economic disruption or unemployment

§ 7426 - Interstate pollution abatement

§ 7427 - Public notification

§ 7428 - State boards

§ 7429 - Solid waste combustion

§ 7430 - Emission factors

§ 7431 - Land use authority

§ 7450 to 7459 - Repealed.

§ 7470 - Congressional declaration of purpose

§ 7471 - Plan requirements

§ 7472 - Initial classifications

§ 7473 - Increments and ceilings

§ 7474 - Area redesignation

§ 7475 - Preconstruction requirements

§ 7476 - Other pollutants

§ 7477 - Enforcement

§ 7478 - Period before plan approval

§ 7479 - Definitions

§ 7491 - Visibility protection for Federal class I areas

§ 7492 - Visibility

§ 7501 - Definitions

§ 7502 - Nonattainment plan provisions in general

§ 7503 - Permit requirements

§ 7504 - Planning procedures

§ 7505 - Environmental Protection Agency grants

§ 7505a - Maintenance plans

§ 7506 - Limitations on certain Federal assistance

§ 7506a - Interstate transport commissions

§ 7507 - New motor vehicle emission standards in nonattainment areas

§ 7508 - Guidance documents

§ 7509 - Sanctions and consequences of failure to attain

§ 7509a - International border areas

§ 7511 - Classifications and attainment dates

§ 7511a - Plan submissions and requirements

§ 7511b - Federal ozone measures

§ 7511c - Control of interstate ozone air pollution

§ 7511d - Enforcement for Severe and Extreme ozone nonattainment areas for failure to attain

§ 7511e - Transitional areas

§ 7511f - NO

§ 7512 - Classification and attainment dates

§ 7512a - Plan submissions and requirements

§ 7513 - Classifications and attainment dates

§ 7513a - Plan provisions and schedules for plan submissions

§ 7513b - Issuance of RACM and BACM guidance

§ 7514 - Plan submission deadlines

§ 7514a - Attainment dates

§ 7515 - General savings clause

§ 7521 - Emission standards for new motor vehicles or new motor vehicle engines

§ 7522 - Prohibited acts

§ 7523 - Actions to restrain violations

§ 7524 - Civil penalties

§ 7525 - Motor vehicle and motor vehicle engine compliance testing and certification

§ 7541 - Compliance by vehicles and engines in actual use

§ 7542 - Information collection

§ 7543 - State standards

§ 7544 - State grants

§ 7545 - Regulation of fuels

§ 7546 - Renewable fuel

§ 7547 - Nonroad engines and vehicles

§ 7548 - Study of particulate emissions from motor vehicles

§ 7549 - High altitude performance adjustments

§ 7550 - Definitions

§ 7551 - Omitted

§ 7552 - Motor vehicle compliance program fees

§ 7553 - Prohibition on production of engines requiring leaded gasoline

§ 7554 - Urban bus standards

§ 7571 - Establishment of standards

§ 7572 - Enforcement of standards

§ 7573 - State standards and controls

§ 7574 - Definitions

§ 7581 - Definitions

§ 7582 - Requirements applicable to clean-fuel vehicles

§ 7583 - Standards for light-duty clean-fuel vehicles

§ 7584 - Administration and enforcement as per California standards

§ 7585 - Standards for heavy-duty clean-fuel vehicles (GVWR above 8,500 up to 26,000 lbs.)

§ 7586 - Centrally fueled fleets

§ 7587 - Vehicle conversions

§ 7588 - Federal agency fleets

§ 7589 - California pilot test program

§ 7590 - General provisions

§ 7601 - Administration

§ 7602 - Definitions

§ 7603 - Emergency powers

§ 7604 - Citizen suits

§ 7605 - Representation in litigation

§ 7606 - Federal procurement

§ 7607 - Administrative proceedings and judicial review

§ 7608 - Mandatory licensing

§ 7609 - Policy review

§ 7610 - Other authority

§ 7611 - Records and audit

§ 7612 - Economic impact analyses

§ 7613 - Repealed.

§ 7614 - Labor standards

§ 7615 - Separability

§ 7616 - Sewage treatment grants

§ 7617 - Economic impact assessment

§ 7618 - Repealed.

§ 7619 - Air quality monitoring

§ 7620 - Standardized air quality modeling

§ 7621 - Employment effects

§ 7622 - Employee protection

§ 7623 - Repealed.

§ 7624 - Cost of vapor recovery equipment

§ 7625 - Vapor recovery for small business marketers of petroleum products

42 U.S. Code § 7450 to 7459 - Repealed.

§ 7625a - Statutory construction

§ 7626 - Authorization of appropriations

§ 7627 - Air pollution from Outer Continental Shelf activities

§ 7628 - Demonstration grant program for local governments

§ 7641 - Noise abatement

§ 7642 - Authorization of appropriations

§ 7651 - Findings and purposes

§ 7651a - Definitions

§ 7651b - Sulfur dioxide allowance program for existing and new units

§ 7651c - Phase I sulfur dioxide requirements

§ 7651d - Phase II sulfur dioxide requirements

§ 7651e - Allowances for States with emissions rates at or below 0.80 lbs/mmBtu

§ 7651f - Nitrogen oxides emission reduction program

§ 7651g - Permits and compliance plans

§ 7651h - Repowered sources

§ 7651i - Election for additional sources

§ 7651j - Excess emissions penalty

§ 7651k - Monitoring, reporting, and recordkeeping requirements

42 U.S. Code § -

§ 7651m - Enforcement

§ 7651n - Clean coal technology regulatory incentives

42 U.S. Code § -

§ 7661 - Definitions

§ 7661a - Permit programs

§ 7661b - Permit applications

§ 7661c - Permit requirements and conditions

§ 7661d - Notification to Administrator and contiguous States

§ 7661e - Other authorities

§ 7661f - Small business stationary source technical and environmental compliance assistance program

§ 7671 - Definitions

§ 7671a - Listing of class I and class II substances

§ 7671b - Monitoring and reporting requirements

§ 7671c - Phase-out of production and consumption of class I substances

§ 7671d - Phase-out of production and consumption of class II substances

§ 7671e - Accelerated schedule

§ 7671f - Exchange authority

§ 7671g - National recycling and emission reduction program

§ 7671h - Servicing of motor vehicle air conditioners

§ 7671i - Nonessential products containing chlorofluorocarbons

§ 7671j - Labeling

§ 7671k - Safe alternatives policy

42 U.S. Code § -

§ 7671m - Relationship to other laws

§ 7671n - Authority of Administrator

42 U.S. Code § -

§ 7671p - International cooperation

§ 7671q - Miscellaneous provisions

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 86 after this date.

  • 2014-08-08; vol. 79 # 153 - Friday, August 8, 2014
    1. 79 FR 46356 - Emergency Vehicle Rule—SCR Maintenance and Regulatory Flexibility for Nonroad Equipment
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This rule is effective on September 8, 2014.
      40 CFR Parts 86 and 1039