§ 98.264 Monitoring and QA/QC requirements.
(a) You must obtain a monthly grab sample of phosphate rock directly from the rock being fed to the process line before it enters the mill using one of the following methods. You may conduct the representative bulk sampling using a method published by a consensus standards organization, or you may use industry consensus standard practice methods, including but not limited to the Phosphate Mining States Methods Used and Adopted by the Association of Fertilizer and Phosphate Chemists (AFPC) (P.O. Box 1645, Bartow, Florida 33831, (863) 534-9755, http://afpc.net, paul.mcafee@mosaicco.com ). If phosphate rock is obtained from more than one origin in a month, you must obtain a sample from each origin of rock or obtain a composite representative sample.
(b) You must determine the carbon dioxide or inorganic carbon content of each monthly grab sample of phosphate rock (consumed in the production of phosphoric acid). You may use a method published by a consensus standards organization, or you may use industry consensus standard practice methods, including but not limited to the Phosphate Mining States Methods Used and Adopted by AFPC (P.O. Box 1645, Bartow, Florida 33831, (863) 534-9755, http://afpc.net, paul.mcafee@mosaicco.com ).
(c) You must determine the mass of phosphate rock consumed each month (by origin) in each wet-process phosphoric acid process line. You can use existing plant procedures that are used for accounting purposes (such as sales records) or you can use data from existing monitoring equipment that is used to measure total mass flow of phosphorous-bearing feed under 40 CFR part 60 or part 63.
[74 FR 56374, Oct. 30, 2009, as amended at 75 FR 66468, Oct. 28, 2010]

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-11; vol. 79 # 238 - Thursday, December 11, 2014
    1. 79 FR 73750 - Greenhouse Gas Reporting Program: Addition of Global Warming Potentials to the General Provisions and Amendments and Confidentiality Determinations for Fluorinated Gas Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on January 1, 2015.
      40 CFR Part 98

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 98 after this date.

  • 2014-12-11; vol. 79 # 238 - Thursday, December 11, 2014
    1. 79 FR 73750 - Greenhouse Gas Reporting Program: Addition of Global Warming Potentials to the General Provisions and Amendments and Confidentiality Determinations for Fluorinated Gas Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on January 1, 2015.
      40 CFR Part 98