40 CFR Part 60, Appendix C to Part 60 - Determination of Emission Rate Change

Status message

There are 6 Updates appearing in the Federal Register for 40 CFR 60. View below or at eCFR (GPOAccess)
View PDF at GPO Pt. 60, App. C
Appendix C to Part 60—Determination of Emission Rate Change
1.Introduction
1.1The following method shall be used to determine whether a physical or operational change to an existing facility resulted in an increase in the emission rate to the atmosphere. The method used is the Student's t test, commonly used to make inferences from small samples.
2.Data
2.1Each emission test shall consist of n runs (usually three) which produce n emission rates. Thus two sets of emission rates are generated, one before and one after the change, the two sets being of equal size.
2.2When using manual emission tests, except as provided in § 60.8(b) of this part, the reference methods of appendix A to this part shall be used in accordance with the procedures specified in the applicable subpart both before and after the change to obtain the data.
2.3When using continuous monitors, the facility shall be operated as if a manual emission test were being performed. Valid data using the averaging time which would be required if a manual emission test were being conducted shall be used.
3.Procedure
3.1Subscripts a and b denote prechange and postchange respectively.
3.2Calculate the arithmetic mean emission rate, E, for each set of data using Equation 1.
Where:
E i=Emission rate for the i th run.
n=number of runs.
3.3Calculate the sample variance, S 2, for each set of data using Equation 2.
3.4 Calculate the pooled estimate, S p, using Equation 3.
3.5 Calculate the test statistic, t, using Equation 4.
4.Results
4.1If E b>,E a and t>t′, where t′ is the critical value of t obtained from Table 1, then with 95% confidence the difference between E b and E a is significant, and an increase in emission rate to the atmosphere has occurred.
Table 1
Degrees of freedom (n a=n b−2) t′ (95 percent confidence level)
2 2.920
3 2.353
4 2.132
5 2.015
6 1.943
7 1.895
8 1.860
For greater than 8 degrees of freedom, see any standard statistical handbook or text.
5.1Assume the two performance tests produced the following set of data:
Test a Test b
Run 1. 100 115
Run 2. 95 120
Run 3. 110 125
5.2Using Equation 1—
E a=100 95 110/3=102
E b=115 120 125/3=120
5.3Using Equation 2—
S a2=(100−102) 2 (95−102) 2 (110−102) 2/3−1=58.5
S b2=(115−120) 2 (120−120) 2 (125−120) 2/3−1=25
5.4Using Equation 3—
S p=[(3−1)(58.5) (3 1)(25)/3 3−2] 1/2=6.46
5.5Using Equation 4—
5.6Since (n 1 n 2−2)=4, t′=2.132 (from Table 1). Thus since t>t′ the difference in the values of E a and E b is significant, and there has been an increase in emission rate to the atmosphere.
6.Continuous Monitoring Data
6.1Hourly averages from continuous monitoring devices, where available, should be used as data points and the above procedure followed.
[40 FR 58420, Dec. 16, 1975]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 60 after this date.

  • 2014-03-06; vol. 79 # 44 - Thursday, March 6, 2014
    1. 79 FR 12681 - Standards of Performance for Greenhouse Gas Emissions From New Stationary Sources: Electric Utility Generating Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of extension of public comment period.
      Comments. The public comment period for the proposed rule published January 8, 2014 (79 FR 1352) and the notice of data availability published on February 26, 2014 (79 FR 10750), is being extended by 60 days to May 9, 2014, in order to provide the public additional time to submit comments and supporting information.
      40 CFR Parts 60, 70, 71 and 98