40 CFR Appendix Table 4 to Subpart DD of Part 63 - Table 4 to Subpart DD of Part 63—Tank Control Levels for Tanks at Existing Affected Sources as Required by 40 CFR 63.685(b)(1)(ii)
Table 4 to Subpart DD of Part 63—Tank Control Levels for Tanks at Existing Affected Sources as Required by 40 CFR 63.685(b)(1)(ii)
Tank design capacity (cubic meters) | Maximum HAP vapor pressure of off-site
material managed in tank (kilopascals) |
Tank control level |
---|---|---|
Design capacity less than 75 m 3 | Maximum HAP vapor pressure less than 76.6 kPa | Level 1. |
Design capacity less than 75 m 3 | Maximum HAP vapor pressure equal to or greater than 76.6 kPa | Level 2, except that fixed roof tanks equipped with an internal floating roof and tanks equipped with an external floating roof as provided for in § 63.685(d)(1) and (2) shall not be used. |
Design capacity equal to or greater than 75 m 3 and less than 151 m 3 | Maximum HAP vapor pressure less than 13.1 kPa | Level 1. |
Maximum HAP vapor pressure equal to or greater than 13.1 kPa | Level 2. | |
Design capacity equal to or greater than 151 m 3 | Maximum HAP vapor pressure less than 5.2 kPa | Level 1. |
Maximum HAP vapor pressure equal to or greater than 5.2 kPa | Level 2. |
[80 FR 14283, Mar. 18, 2015]