40 CFR Part 63, Subpart NNN, Table 1 to Subpart NNN of Part 63 - Applicability of General Provisions (40 CFR Part 63, Subpart A) to Subpart NNN

Status message

There are 5 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
prev | next
View PDF at GPO Pt. 63, Subpt. NNN, Table 1
Table 1 to Subpart NNN of Part 63—Applicability of General Provisions (40 CFR Part 63, Subpart A) to Subpart NNN
General provisions citation Requirement Applies tosubpart NNN Explanation
63.1(a)(1)-(a)(4) Applicability Yes.
63.1(a)(5) No [Reserved].
63.1(a)(6)-(a)(8) Yes.
63.1(a)(9) No [Reserved].
63.1(a)(10)-(a)(14) Yes.
63.1(b)(1)-(b)(3) Initial Applicability Determination Yes.
63.1(c)(1)-(c)(2) Applicability After Standard Established Yes.
63.1(c)(3) No [Reserved].
63.1(c)(4)-(c)(5) Yes.
63.1(d) No [Reserved].
63.1(e) Applicability of Permit Program Yes.
63.2 Definitions Yes Additional definitions in § 63.1381.
63.3(a)-(c) Units and Abbreviations Yes.
63.4(a)(1)-(a)(3) Prohibited Activities Yes.
63.4(a)(4) No [Reserved].
63.4(a)(5) Yes.
63.4(b)-(c) Yes.
63.5(a)(1)-(a)(2) Construction/Reconstruction Yes.
63.5(b)(1) Existing, New, Reconstructed Yes.
63.5(b)(2) No [Reserved].
63.5(b)(3)-(b)(6) Yes.
63.5(c) No [Reserved].
63.5(d) Approval of Construction/Reconstruction Yes.
63.5(e) Yes.
63.5(f) Yes.
63.6(a) Compliance with Standards and Maintenance Requirements Yes.
63.6(b)(1)-(b)(5) Yes.
63.6(b)(6) No [Reserved].
63.6(b)(7) Yes.
63.6(c)(1) Compliance Date for Existing Sources Yes § 63.1387 specifies compliance dates.
63.6(c)(2) Yes.
63.6(c)(3)-(c)(4) No [Reserved].
63.6(c)(5) Yes.
63.6(d) No [Reserved].
63.6(e)(1)-(e)(2) Operation & Maintenance Yes § 63.1383 specifies operations/maintenance plan.
63.6(e)(3) Startup, Shutdown Malfunction Plan Yes.
63.6(f)(1)-(f)(3) Compliance with Nonopacity Emission Standards Yes.
63.6(g)(1)-(g)(3) Alternative Nonopacity Standard Yes.
63.6(h) Opacity/VE Standards No Subpart NNN-no COMS, VE or opacity standards.
63.6(i)(1)-(i)(14) Extension of Compliance Yes.
63.6(i)(15) No [Reserved].
63.6(i)(16) Yes.
63.6(j) Exemption from Compliance Yes.
63.7(a) Performance Testing Requirements Yes § 63.1384 has specific requirements.
63.7(b) Notification Yes.
63.7(c) Quality Assurance Program/Test Plan Yes.
63.7(d) Performance Testing Facilities Yes.
63.7(e)(1)-(e)(4) Conduct of Performance Tests Yes.
63.7(f) Alternative Test Method Yes.
63.7(g) Data Analysis Yes.
63.7(h) Waiver of Performance Tests Yes.
63.8(a)(1)-(a)(2) Monitoring Requirements Yes.
63.8(a)(3) No [Reserved].
63.8(a)(4) Yes.
63.8(b) Conduct of Monitoring Yes.
63.8(c) CMS Operation/Maintenance Yes.
63.8(d) Quality Control Program Yes.
63.8(e) Performance Evaluation for CMS Yes.
63.8(f) Alternative Monitoring Method Yes.
63.8(g) Reduction of Monitoring Data Yes.
63.9(a) Notification Requirements Yes.
63.9(b) Initial Notifications Yes.
63.9(c) Request for Compliance Extension Yes.
63.9(d) New Source Notification for Special Compliance Requirements Yes.
63.9(e) Notification of Performance Test Yes.
63.9(f) Notification of VE/Opacity Test No Opacity/VE tests not required.
63.9(g) Additional CMS Notifications Yes.
63.9(h)(1)-(h)(3) Notification of Compliance Status Yes.
63.9(h)(4) No [Reserved].
63.9(h)(5)-(h)(6) Yes.
63.9(i) Adjustment of Deadlines Yes.
63.9(j) Change in Previous Information Yes.
63.10(a) Recordkeeping/Reporting Yes.
63.10(b) General Requirements Yes.
63.10(c)(1) Additional CMS Recordkeeping Yes.
63.10(c)(2)-(c)(4) No [Reserved].
63.10(c)(5)-(c)(8) Yes.
63.10(c)(9) No [Reserved].
63.10(c)(10)-(15) Yes.
63.10(d)(1) General Reporting Requirements Yes.
63.10(d)(2) Performance Test Results Yes.
63.10(d)(3) Opacity or VE Observations No No limits for VE/opacity.
63.10(d)(4) Progress Reports Yes.
63.10(d)(5) Startup, Shutdown, Malfunction Reports Yes.
63.10(e)(1)-(e)(3) Additional CMS Reports Yes.
63.10(e)(4) Reporting COM Data No COM not required.
63.10(f) Waiver of Recordkeeping/Reporting Yes.
63.11(a) Control Device Requirements Yes.
63.11(b) Flares No Flares not applicable.
63.12 State Authority and Delegations Yes.
63.13 State/Regional Addresses Yes.
63.14 Incorporation by Reference No
63.15 Availability of Information Yes.

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63