40 CFR Part 63, Subpart NNNNN, Table 7 to Subpart NNNNN of Part 63 - Applicability of General Provisions to Subpart NNNNN

Status message

There are 6 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
prev | next
View PDF at GPO Pt. 63, Subpt. NNNNN, Table 7
Table 7 to Subpart NNNNN of Part 63—Applicability of General Provisions to Subpart NNNNN
As stated in § 63.9065, you must comply with the applicable General Provisions requirements according to the following:
Citation Requirement Applies to subpart NNNNN Explanation
§ 63.1 Initial applicability determination; applicability after standard established; permit requirements; extensions; notifications Yes.
§ 63.2 Definitions Yes Additional definitions are found in § 63.9075.
§ 63.3 Units and abbreviations Yes.
§ 63.4 Prohibited activities; compliance date; circumvention, severability Yes.
§ 63.5 Construction/reconstruction applicability; applications; approvals Yes.
§ 63.6(a) Compliance with standards and maintenance requirements-applicability Yes.
§ 63.6(b)(1)-(4) Compliance dates for new or reconstructed sources Yes § 63.8995 specifies compliance dates.
§ 63.6(b)(5) Notification if commenced construction or reconstruction after proposal Yes.
§ 63.6(b)(6) [Reserved] Yes.
§ 63.6(b)(7) Compliance dates for new or reconstructed area sources that become major Yes § 63.8995 specifies compliance dates.
§ 63.6(c)(1)-(2) Compliance dates for existing sources Yes § 63.8995 specifies compliance dates.
§ 63.6(c)(3)-(4) [Reserved] Yes.
§ 63.6(c)(5) Compliance dates for existing area sources that become major Yes § 63.8995 specifies compliance dates.
§ 63.6(d) [Reserved] Yes.
§ 63.6(e)(1)-(2) Operation and maintenance requirements Yes.
§ 63.6(e)(3) SSM plans Yes.
§ 63.6(f)(1) Compliance except during SSM Yes.
§ 63.6(f)(2)-(3) Methods for determining compliance Yes.
§ 63.6(g) Use of an alternative non-opacity emission standard Yes.
§ 63.6(h) Compliance with opacity/visible emission standards No Subpart NNNNN does not specify opacity or visible emission standards.
§ 63.6(i) Extension of compliance with emission standards Yes.
§ 63.6(j) Presidential compliance exemption Yes.
§ 63.7(a)(1)-(2) Performance test dates Yes Except for existing affected sources as specified in § 63.9010(b).
§ 63.7(a)(3) Administrator's Clean Air Act section 114 authority to require a performance test Yes.
§ 63.7(b) Notification of performance test and rescheduling Yes.
§ 63.7(c) Quality assurance program and site-specific test plans Yes.
§ 63.7(d) Performance testing facilities Yes.
§ 63.7(e)(1) Conditions for conducting performance tests Yes.
§ 63.7(f) Use of an alternative test method Yes.
§ 63.7(g) Performance test data analysis, recordkeeping, and reporting Yes.
§ 63.7(h) Waiver of performance tests Yes.
§ 63.8(a)(1)-(3) Applicability of monitoring requirements Yes Additional monitoring requirements are found in § 63.9005(d) and 63.9035.
63.8(a)(4) Monitoring with flares No Subpart NNNNN does not refer directly or indirectly to § 63.11.
§ 63.8(b) Conduct of monitoring and procedures when there are multiple effluents and multiple monitoring systems Yes.
§ 63.8(c)(1)-(3) Continuous monitoring system O&M Yes Applies as modified by § 63.9005(d).
§ 63.8(c)(4) Continuous monitoring system requirements during breakdown, out-of-control, repair, maintenance, and high-level calibration drifts Yes Applies as modified by § 63.9005(d).
§ 63.8(c)(5) Continuous opacity monitoring system (COMS) minimum procedures No Subpart NNNNN does not have opacity or visible emission standards.
§ 63.8(c)(6) Zero and high level calibration checks Yes Applies as modified by § 63.9005(d).
§ 63.8(c)(7)-(8) Out-of-control periods, including reporting Yes.
§ 63.8(d)-(e) Quality control program and CMS performance evaluation No Applies as modified by § 63.9005(d).
§ 63.8(f)(1)-(5) Use of an alternative monitoring method Yes.
§ 63.8(f)(6) Alternative to relative accuracy test No Only applies to sources that use continuous emissions monitoring systems (CEMS).
§ 63.8(g) Data reduction Yes Applies as modified by § 63.9005(d).
§ 63.9(a) Notification requirements—applicability Yes.
§ 63.9(b) Initial notifications Yes Except § 63.9045(c) requires new or reconstructed affected sources to submit the application for construction or reconstruction required by § 63.9(b)(1)(iii) in lieu of the initial notification.
§ 63.9(c) Request for compliance extension Yes.
§ 63.9(d) Notification that a new source is subject to special compliance requirements Yes.
§ 63.9(e) Notification of performance test Yes.
§ 63.9(f) Notification of visible emissions/opacity test No Subpart NNNNN does not have opacity or visible emission standards.
§ 63.9(g)(1) Additional CMS notifications—date of CMS performance evaluation Yes.
§ 63.9(g)(2) Use of COMS data No Subpart NNNNN does not require the use of COMS.
§ 63.9(g)(3) Alternative to relative accuracy testing No Applies only to sources with CEMS.
§ 63.9(h) Notification of compliance status Yes Except the submission date specified in § 63.9(h)(2)(ii) is superseded by the date specified in § 63.9045(f).
§ 63.9(i) Adjustment of submittal deadlines Yes.
§ 63.9(j) Change in previous information Yes.
§ 63.10(a) Recordkeeping/reporting applicability Yes.
§ 63.10(b)(1) General recordkeeping requirements Yes §§ 63.9055 and 63.9060 specify additional recordkeeping requirements.
§ 63.10(b)(2)(i)-(xi) Records related to SSM periods and CMS Yes.
§ 63.10(b)(2)(xii) Records when under waiver Yes.
§ 63.10(b)(2)(xiii) Records when using alternative to relative accuracy test No Applies only to sources with CEMS.
§ 63.10(b)(2)(xiv) All documentation supporting initial notification and notification of compliance status Yes.
§ 63.10(b)(3) Recordkeeping requirements for applicability determinations Yes.
§ 63.10(c) Additional recordkeeping requirements for sources with CMS Yes Applies as modified by § 63.9005 (d).
§ 63.10(d)(1) General reporting requirements Yes § 63.9050 specifies additional reporting requirements.
§ 63.10(d)(2) Performance test results Yes § 63.9045(f) specifies submission date.
§ 63.10(d)(3) Opacity or visible emissions observations No Subpart NNNNN does not specify opacity or visible emission standards.
§ 63.10(d)(4) Progress reports for sources with compliance extensions Yes.
§ 63.10(d)(5) SSM reports Yes.
§ 63.10(e)(1) Additional CMS reports—general Yes Applies as modified by § 63.9005(d).
§ 63.10(e)(2)(i) Results of CMS performance evaluations Yes Applies as modified by § 63.9005(d).
§ 63.10(e)(2) Results of COMS performance evaluations No Subpart NNNNN does not require the use of COMS.
§ 63.10(e)(3) Excess emissions/CMS performance reports Yes.
§ 63.10(e)(4) Continuous opacity monitoring system data reports No Subpart NNNNN does not require the use of COMS.
§ 63.10(f) Recordkeeping/reporting waiver Yes.
§ 63.11 Control device requirements—applicability No Facilities subject to subpart NNNNN do not use flares as control devices.
§ 63.12 State authority and delegations Yes § 63.9070 lists those sections of subparts NNNNN and A that are not delegated.
§ 63.13 Addresses Yes.
§ 63.14 Incorporation by reference Yes Subpart NNNNN does not incorporate any material by reference.
§ 63.15 Availability of information/confidentiality Yes.
[68 FR 19090, Apr. 17, 2003, as amended at 71 FR 17748, Apr. 7, 2006]

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-03-27; vol. 79 # 59 - Thursday, March 27, 2014
    1. 79 FR 17340 - National Emission Standards for Hazardous Air Pollutant Emissions: Group IV Polymers and Resins; Pesticide Active Ingredient Production; and Polyether Polyols Production
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final action is effective on March 27, 2014. The incorporation by reference of certain publications listed in this final rule was approved by the Director of the Federal Register as of March 27, 2014.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-07-02; vol. 79 # 127 - Wednesday, July 2, 2014
    1. 79 FR 37850 - National Emission Standards for Hazardous Air Pollutants: Off-Site Waste and Recovery Operations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Proposed rule.
      Comments. Comments must be received on or before August 18, 2014. A copy of comments on the information collection provisions should be submitted to the Office of Management and Budget (OMB) on or before August 1, 2014. Public Hearing. We do not plan to conduct a public hearing unless requested. If requested, we will hold a public hearing on July 17, 2014. To request a hearing, please contact the person listed in the following FOR FURTHER INFORMATION CONTACT section by July 14, 2014.
      40 CFR Part 63