Table 1 to Subpart OOO of Part 63—Applicability of General Provisions to Subpart OOO Affected Sources
Reference Applies to subpart OOO Explanation
a The plan and any records or reports of start-up, shutdown, and malfunction do not apply to emission points that do not require control under this subpart.
63.1(a)(1) Yes § 63.1402 specifies definitions in addition to or that supersede definitions in § 63.2.
63.1(a)(2) Yes
63.1(a)(3) Yes § 63.1401(i) identifies those standards which overlap with the requirements of subpart OOO of this part and specify how compliance shall be achieved.
63.1(a)(4) Yes Subpart OOO (this table) specifies the applicability of each paragraph in subpart A of this part.
63.1(a)(5) No [Reserved].
63.1(a)(6)-63.1(a)(8) Yes.
63.1(a)(9) No [Reserved].
63.1(a)(10) Yes
63.1(a)(11) Yes
63.1(a)(12)-63.1(a)(14) Yes
63.1(b)(1) No
63.1(b)(2) Yes
63.1(b)(3) No § 63.1400(e) provides documentation requirements for APPUs not considered affected sources.
63.1(c)(1) Yes Subpart OOO (this table) specifies the applicability of each paragraph in subpart A of this part.
63.1(c)(2) No Area sources are not subject to this subpart.
63.1(c)(3) No [Reserved].
63.1(c)(4) Yes
63.1(c)(5) Yes Except that affected sources are not required to submit notifications overridden by this table.
63.1(d) No [Reserved].
63.1(e) Yes
63.2 Yes § 63.1402 specifies the definitions from subpart A of this part that apply to this subpart.
63.3 Yes
63.4(a)(1)-63.4(a)(3) Yes
63.4(a)(4) No [Reserved].
63.4(a)(5) Yes
63.4(b) Yes
63.4(c) Yes
63.5(a)(1) Yes Except the terms “source” and “stationary source” should be interpreted as having the same meaning as “affected source.”
63.5(a)(2) Yes
63.5(b)(1) Yes Except § 63.1400(d) specifies when construction or reconstruction is subject to new source standards.
63.5(b)(2) No [Reserved].
63.5(b)(3) Yes
63.5(b)(4) Yes Except that the Initial Notification and § 63.9(b) requirements do not apply.
63.5(b)(5) Yes
63.5(b)(6) Yes Except that § 63.1400(d) specifies when construction or reconstruction is subject to new source standards.
63.5(c) No [Reserved].
63.5(d)(1)(i) Yes Except that the references to the Initial Notification and § 63.9(b)(5) do not apply.
63.5(d)(1)(ii) Yes Except that § 63.5(d)(1)(ii)(H) does not apply.
63.5(d)(1)(iii) No § 63.1417(e) specifies Notification of Compliance Status requirements.
63.5(d)(2) No
63.5(d)(3) Yes Except § 63.5(d)(3)(ii) does not apply, and equipment leaks subject to § 63.1410 are exempt.
63.5(d)(4) Yes
63.5(e) Yes
63.5(f)(1) Yes
63.5(f)(2) Yes Except that where § 63.9(b)(2) is referred to, the owner or operator need not comply.
63.6(a) Yes
63.6(b)(1) Yes
63.6(b)(2) Yes
63.6(b)(3) Yes
63.6(b)(4) Yes
63.6(b)(5) Yes
63.6(b)(6) No [Reserved].
63.6(b)(7) No
63.6(c)(1) Yes Except that § 63.1401 specifies the compliance date.
63.6(c)(2) No
63.6(c)(3) No [Reserved].
63.6(c)(4) No [Reserved].
63.6(c)(5) Yes
63.6(d) No [Reserved].
63.6(e) Yes Except as otherwise specified in this table, § 63.6(e) does not apply to emission points that do not require control under this subpart.a
63.6(e)(1)(i) No This is addressed by § 63.1400(k)(4).
63.6(e)(1)(ii) Yes
63.6(e)(1)(iii) Yes
63.6(e)(2) Yes
63.6(e)(3)(i) Yes For equipment leaks (subject to § 63.1410), the start-up, shutdown, and malfunction plan requirement of § 63.6(e)(3)(i) is limited to control devices and is optional for other equipment. The start-up, shutdown, malfunction plan may include written procedures that identify conditions that justify a delay of repair.
63.6(e)(3)(i)(A) No This is addressed by § 63.1400(k)(4).
63.6(e)(3)(i)(B) Yes
63.6(e)(3)(i)(C) Yes
63.6(e)(3)(ii) Yes
63.6(e)(3)(iii) No Recordkeeping and reporting are specified in §§ 63.1416 and 63.1417.
63.6(e)(3)(iv) No Recordkeeping and reporting are specified in §§ 63.1416 and 63.1417.
63.6(e)(3)(v) Yes
63.6(e)(3)(vi) Yes
63.6(e)(3)(vii) Yes
63.6(e)(3)(vii)(A) Yes
63.6(e)(3)(vii) (B) Yes Except the plan shall provide for operation in compliance with § 63.1400(k)(4).
63.6(e)(3)(vii) (C) Yes
63.6(e)(3)(viii) Yes
63.6(e)(3)(ix) Yes
63.6(f)(1) Yes
63.6(f)(2) Yes Except § 63.7(c), as referred to in § 63.6(f)(2)(iii)(D), does not apply, and except that § 63.6(f)(2)(ii) does not apply to equipment leaks subject to § 63.1410.
63.6(f)(3) Yes
63.6(g) Yes
63.6(h) No This subpart OOO does not require opacity and visible emission standards.
63.6(i)(1) Yes
63.6(i)(2) Yes
63.6(i)(3) Yes
63.6(i)(4)(i)(A) Yes
63.6(i)(4)(i)(B) No Dates are specified in §§ 63.1401(e) and 63.1417(d)(1).
63.6(i)(4)(ii) No
63.6(i)(5)-(14) Yes
63.6(i)(15) No [Reserved].
63.6(i)(16) Yes
63.6(j) Yes
63.7(a)(1) Yes
63.7(a)(2) No § 63.1417(e) specifies the submittal dates of performance test results for all emission points except equipment leaks; for equipment leaks, compliance demonstration results are reported in the Periodic Reports.
63.7(a)(3) Yes
63.7(b) No § 63.1417 specifies notification requirements.
63.7(c) No
63.7(d) Yes
63.7(e)(1) Yes Except that all performance tests shall be conducted at maximum representative operating conditions achievable at the time without disruption of operations or damage to equipment.
63.7(e)(2) Yes
63.7(e)(3) No Subpart OOO specifies requirements.
63.7(e)(4) Yes
63.7(f) Yes Except that if a site specific test plan is not required, the notification deadline in § 63.7(f)(2)(i) shall be 60 days prior to the performance test, and in § 63.7(f)(3), approval or disapproval of the alternative test method shall not be tied to the site specific test plan.
63.7(g) Yes Except that the requirements in § 63.1417(e) shall apply instead of the references to the Notification of Compliance Status report in § 63.9(h). In addition, equipment leaks subject to § 63.1410 are not required to conduct performance tests.
63.7(h) Yes Except § 63.7(h)(4)(ii) may not be applicable, if the site-specific test plan in § 63.7(c)(2) is not required.
63.8(a)(1) Yes
63.8(a)(2) No
63.8(a)(3) No [Reserved].
63.8(a)(4) Yes
63.8(b)(1) Yes
63.8(b)(2) No Subpart OOO specifies locations to conduct monitoring.
63.8(b)(3) Yes
63.8(c)(1) Yes
63.8(c)(1)(i) Yes
63.8(c)(1)(ii) No For all emission points except equipment leaks, comply with § 63.1416(b)(2); for equipment leaks, comply with requirements in 40 CFR part 63, subpart UU.
63.8(c)(1)(iii) Yes
63.8(c)(2) Yes
63.8(c)(3) Yes
63.8(c)(4) No § 63.1415 specifies monitoring frequency; not applicable to equipment leaks because § 63.1410 does not require continuous monitoring systems.
63.8(c)(5)-63.8(c)(8) No
63.8(d) No
63.8(e) No
63.8(f)(1)-63.8(f)(3) Yes
63.8(f)(4)(i) No Timeframe for submitting request is specified in § 63.1417 (j) or (k); not applicable to equipment leaks because § 63.1410 (through reference to 40 CFR part 63, subpart UU) specifies acceptable alternative methods.
63.8(f)(4)(ii) No Contents of request are specified in § 63.1417(j) or (k).
63.8(f)(4)(iii) No
63.8(f)(5)(i) Yes
63.8(f)(5)(ii) No
63.8(f)(5)(iii) Yes
63.8(f)(6) No Subpart OOO does not require continuous emission monitors.
63.8(g) No Data reduction procedures specified in § 63.1416(a) and (h); not applicable to equipment leaks.
63.9(a) Yes
63.9(b) No Subpart OOO does not require an initial notification.
63.9(c) Yes
63.9(d) Yes
63.9(e) No § 63.1417 specifies notification deadlines.
63.9(f) No Subpart OOO does not require opacity and visible emission standards.
63.9(g) No
63.9(h) No § 63.1417(e) specifies Notification of Compliance Status requirements.
63.9(i) Yes
63.9(j) No
63.10(a) Yes
63.10(b)(1) No § 63.1416(a) specifies record retention requirements.
63.10(b)(2) No Subpart OOO specifies recordkeeping requirements.
63.10(b)(3) No § 63.1400(e) requires documentation of sources that are not affected sources.
63.10(c) No § 63.1416 specifies recordkeeping requirements.
63.10(d)(1) Yes
63.10(d)(2) No § 63.1417 specifies performance test reporting requirements; not applicable to equipment leaks.
63.10(d)(3) No Subpart OOO does not require opacity and visible emission standards.
63.10(d)(4) Yes
63.10(d)(5) Yes Except that reports required by § 63.10(d)(5)(i) may be submitted at the same time as Periodic Reports specified in § 63.1417(f). The start-up, shutdown, and malfunction plan, and any records or reports of start-up, shutdown, and malfunction do not apply to emission points that do not require control under this subpart.
63.10(e) No § 63.1417 specifies reporting requirements.
63.10(f) Yes
63.11 Yes Except that instead of § 63.11(b), § 63.1413(g) shall apply.
63.12 Yes
63.13-63.15 Yes
[65 FR 3290, Jan. 20, 2000, as amended at 71 FR 20461, Apr. 20, 2006]

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70102 - National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Texas
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on January 26, 2015 without further notice, unless EPA receives relevant adverse comment by December 26, 2014. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that this rule will not take effect.
      40 CFR Part 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-12-12; vol. 79 # 239 - Friday, December 12, 2014
    1. 79 FR 73872 - Phosphoric Acid Manufacturing and Phosphate Fertilizer Production RTR and Standards of Performance for Phosphate Processing; Extension of Comment Period
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Notice of proposed rulemaking; extension of public comment period.
      Comments. The public comment period for the proposed rule published in the Federal Register on November 7, 2014, (79 FR 66512) is being extended for 30 days to January 21, 2015.
      40 CFR Parts 60 and 63