40 CFR Part 63, Subpart VVVV, Table 1 to Subpart VVVV of Part 63 - Compliance Dates for New and Existing Boat Manufacturing Facilities

Status message

There are 5 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
prev | next
View PDF at GPO Pt. 63, Subpt. VVVV, Table 1
Table 1 to Subpart VVVV of Part 63—Compliance Dates for New and Existing Boat Manufacturing Facilities
As specified in § 63.5695, you must comply by the dates in the following table:
If your facility is— And— Then you must comply by this date—
1Your facility is a major source if it is a stationary source or group of stationary sources located within a contiguous area and under common control that emits or can potentially emit, considering controls, in the aggregate, 9.1 megagrams or more per year of a single hazardous air pollutant or 22.7 megagrams or more per year of a combination of hazardous air pollutants.
1. An existing source Is a major source on or before August 22, 20011 August 23, 2004.
2. An existing or new area source Becomes a major source after August 22, 20011 1 year after becoming a major source or August 22, 2002, whichever is later.
3. A new source Is a major source at startup 1 Upon startup or August 22, 2001, whichever is later.

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63