Table 13 to Subpart WWWW of Part 63—Applicability and Timing of Notifications
As required in § 63.5905(a), you must determine the applicable notifications and submit them by the dates shown in the following table:
If your facility . . . You must submit . . . By this date . . .
1. Is an existing source subject to this subpart An Initial Notification containing the information specified in § 63.9(b)(2) No later than the dates specified in § 63.9(b)(2).
2. Is a new source subject to this subpart The notifications specified in § 63.9(b)(4) and (5) No later than the dates specified § 63.9(b)(4) and (5).
3. Qualifies for a compliance extension as specified in § 63.9(c) A request for a compliance extension as specified in § 63.9(c) No later than the dates specified in § 63.6(i).
4. Is complying with organic HAP emissions limit averaging provisions A Notification of Compliance Status as specified in § 63.9(h) No later than 1 year plus 30 days after your facility's compliance date.
5. Is complying with organic HAP content limits, application equipment requirements, or organic HAP emissions limit other than organic HAP emissions limit averaging A Notification of Compliance Status as specified in § 63.9(h) No later than 30 calendar days after your facility's compliance date.
6. Is complying by using an add-on control device a. A notification of intent to conduct a performance test as specified in § 63.9(e) No later than the date specified in § 63.9(e).
b. A notification of the date for the CMS performance evaluation as specified in § 63.9(g) The date of submission of notification of intent to conduct a performance test.
c. A Notification of Compliance Status as specified in § 63.9(h) No later than 60 calendar days after the completion of the add-on control device performance test and CMS performance evaluation.

Title 40 published on 2013-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.
      40 CFR Parts 51, 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2013-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-02-27; vol. 79 # 39 - Thursday, February 27, 2014
    1. 79 FR 11228 - Revisions to Test Methods and Testing Regulations
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule.
      This final rule is effective on February 27, 2014. The incorporation by reference materials listed in the rule are approved by the Director of the Federal Register as of February 27, 2014.