40 CFR Part 63, Subpart ZZZZ, Table 8 to Subpart ZZZZ of Part 63 - Applicability of General Provisions to Subpart ZZZZ

Status message

There are 6 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
prev | next
View PDF at GPO Pt. 63, Subpt. ZZZZ, Table 8
Table 8 to Subpart ZZZZ of Part 63—Applicability of General Provisions to Subpart ZZZZ.
As stated in § 63.6665, you must comply with the following applicable general provisions.
General provisions citation Subject of citation Applies to subpart Explanation
§ 63.1 General applicability of the General Provisions Yes.
§ 63.2 Definitions Yes Additional terms defined in § 63.6675.
§ 63.3 Units and abbreviations Yes.
§ 63.4 Prohibited activities and circumvention Yes.
§ 63.5 Construction and reconstruction Yes.
§ 63.6(a) Applicability Yes.
§ 63.6(b)(1)-(4) Compliance dates for new and reconstructed sources Yes.
§ 63.6(b)(5) Notification Yes.
§ 63.6(b)(6) [Reserved]
§ 63.6(b)(7) Compliance dates for new and reconstructed area sources that become major sources Yes.
§ 63.6(c)(1)-(2) Compliance dates for existing sources Yes.
§ 63.6(c)(3)-(4) [Reserved]
§ 63.6(c)(5) Compliance dates for existing area sources that become major sources Yes.
§ 63.6(d) [Reserved]
§ 63.6(e) Operation and maintenance No.
§ 63.6(f)(1) Applicability of standards No.
§ 63.6(f)(2) Methods for determining compliance Yes.
§ 63.6(f)(3) Finding of compliance Yes.
§ 63.6(g)(1)-(3) Use of alternate standard Yes.
§ 63.6(h) Opacity and visible emission standards No Subpart ZZZZ does not contain opacity or visible emission standards.
§ 63.6(i) Compliance extension procedures and criteria Yes.
§ 63.6(j) Presidential compliance exemption Yes.
§ 63.7(a)(1)-(2) Performance test dates Yes Subpart ZZZZ contains performance test dates at §§ 63.6610, 63.6611, and 63.6612.
§ 63.7(a)(3) CAA section 114 authority Yes.
§ 63.7(b)(1) Notification of performance test Yes Except that § 63.7(b)(1) only applies as specified in § 63.6645.
§ 63.7(b)(2) Notification of rescheduling Yes Except that § 63.7(b)(2) only applies as specified in § 63.6645.
§ 63.7(c) Quality assurance/test plan Yes Except that § 63.7(c) only applies as specified in § 63.6645.
§ 63.7(d) Testing facilities Yes.
§ 63.7(e)(1) Conditions for conducting performance tests No. Subpart ZZZZ specifies conditions for conducting performance tests at § 63.6620.
§ 63.7(e)(2) Conduct of performance tests and reduction of data Yes Subpart ZZZZ specifies test methods at § 63.6620.
§ 63.7(e)(3) Test run duration Yes.
§ 63.7(e)(4) Administrator may require other testing under section 114 of the CAA Yes.
§ 63.7(f) Alternative test method provisions Yes.
§ 63.7(g) Performance test data analysis, recordkeeping, and reporting Yes.
§ 63.7(h) Waiver of tests Yes.
§ 63.8(a)(1) Applicability of monitoring requirements Yes Subpart ZZZZ contains specific requirements for monitoring at § 63.6625.
§ 63.8(a)(2) Performance specifications Yes.
§ 63.8(a)(3) [Reserved]
§ 63.8(a)(4) Monitoring for control devices No.
§ 63.8(b)(1) Monitoring Yes.
§ 63.8(b)(2)-(3) Multiple effluents and multiple monitoring systems Yes.
§ 63.8(c)(1) Monitoring system operation and maintenance Yes.
§ 63.8(c)(1)(i) Routine and predictable SSM Yes.
§ 63.8(c)(1)(ii) SSM not in Startup Shutdown Malfunction Plan Yes.
§ 63.8(c)(1)(iii) Compliance with operation and maintenance requirements Yes.
§ 63.8(c)(2)-(3) Monitoring system installation Yes.
§ 63.8(c)(4) Continuous monitoring system (CMS) requirements Yes Except that subpart ZZZZ does not require Continuous Opacity Monitoring System (COMS).
§ 63.8(c)(5) COMS minimum procedures No Subpart ZZZZ does not require COMS.
§ 63.8(c)(6)-(8) CMS requirements Yes Except that subpart ZZZZ does not require COMS.
§ 63.8(d) CMS quality control Yes.
§ 63.8(e) CMS performance evaluation Yes Except for § 63.8(e)(5)(ii), which applies to COMS.
Except that § 63.8(e) only applies as specified in § 63.6645.
§ 63.8(f)(1)-(5) Alternative monitoring method Yes Except that § 63.8(f)(4) only applies as specified in § 63.6645.
§ 63.8(f)(6) Alternative to relative accuracy test Yes Except that § 63.8(f)(6) only applies as specified in § 63.6645.
§ 63.8(g) Data reduction Yes Except that provisions for COMS are not applicable. Averaging periods for demonstrating compliance are specified at §§ 63.6635 and 63.6640.
§ 63.9(a) Applicability and State delegation of notification requirements Yes.
§ 63.9(b)(1)-(5) Initial notifications Yes Except that § 63.9(b)(3) is reserved.
Except that § 63.9(b) only applies as specified in § 63.6645.
§ 63.9(c) Request for compliance extension Yes Except that § 63.9(c) only applies as specified in § 63.6645.
§ 63.9(d) Notification of special compliance requirements for new sources Yes Except that § 63.9(d) only applies as specified in § 63.6645.
§ 63.9(e) Notification of performance test Yes Except that § 63.9(e) only applies as specified in § 63.6645.
§ 63.9(f) Notification of visible emission (VE)/opacity test No Subpart ZZZZ does not contain opacity or VE standards.
§ 63.9(g)(1) Notification of performance evaluation Yes Except that § 63.9(g) only applies as specified in § 63.6645.
§ 63.9(g)(2) Notification of use of COMS data No Subpart ZZZZ does not contain opacity or VE standards.
§ 63.9(g)(3) Notification that criterion for alternative to RATA is exceeded Yes If alternative is in use.
Except that § 63.9(g) only applies as specified in § 63.6645.
§ 63.9(h)(1)-(6) Notification of compliance status Yes Except that notifications for sources using a CEMS are due 30 days after completion of performance evaluations. § 63.9(h)(4) is reserved.
Except that § 63.9(h) only applies as specified in § 63.6645.
§ 63.9(i) Adjustment of submittal deadlines Yes.
§ 63.9(j) Change in previous information Yes.
§ 63.10(a) Administrative provisions for recordkeeping/reporting Yes.
§ 63.10(b)(1) Record retention Yes.
§ 63.10(b)(2)(i)-(v) Records related to SSM No.
§ 63.10(b)(2)(vi)-(xi) Records Yes.
§ 63.10(b)(2)(xii) Record when under waiver Yes.
§ 63.10(b)(2)(xiii) Records when using alternative to RATA Yes For CO standard if using RATA alternative.
§ 63.10(b)(2)(xiv) Records of supporting documentation Yes.
§ 63.10(b)(3) Records of applicability determination Yes.
§ 63.10(c) Additional records for sources using CEMS Yes Except that § 63.10(c)(2)-(4) and (9) are reserved.
§ 63.10(d)(1) General reporting requirements Yes.
§ 63.10(d)(2) Report of performance test results Yes.
§ 63.10(d)(3) Reporting opacity or VE observations No Subpart ZZZZ does not contain opacity or VE standards.
§ 63.10(d)(4) Progress reports Yes.
§ 63.10(d)(5) Startup, shutdown, and malfunction reports No.
§ 63.10(e)(1) and (2)(i) Additional CMS Reports Yes.
§ 63.10(e)(2)(ii) COMS-related report No Subpart ZZZZ does not require COMS.
§ 63.10(e)(3) Excess emission and parameter exceedances reports Yes. Except that § 63.10(e)(3)(i) (C) is reserved.
§ 63.10(e)(4) Reporting COMS data No Subpart ZZZZ does not require COMS.
§ 63.10(f) Waiver for recordkeeping/reporting Yes.
§ 63.11 Flares No.
§ 63.12 State authority and delegations Yes.
§ 63.13 Addresses Yes.
§ 63.14 Incorporation by reference Yes.
§ 63.15 Availability of information Yes.
[75 FR 9688, Mar. 3, 2010]

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-19; vol. 79 # 223 - Wednesday, November 19, 2014
    1. 79 FR 68777 - Reconsideration of Certain Startup/Shutdown Issues: National Emission Standards for Hazardous Air Pollutants From Coal- and Oil-Fired Electric Utility Steam Generating Units and Standards of Performance for Fossil-Fuel-Fired Electric Utility, Industrial-Commercial-Institutional, and Small Industrial-Commercial-Institutional Steam Generating Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; notice of final action on reconsideration.
      The effective date of the rule is November 19, 2014.
      40 CFR Parts 60 and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2014-11-19; vol. 79 # 223 - Wednesday, November 19, 2014
    1. 79 FR 68777 - Reconsideration of Certain Startup/Shutdown Issues: National Emission Standards for Hazardous Air Pollutants From Coal- and Oil-Fired Electric Utility Steam Generating Units and Standards of Performance for Fossil-Fuel-Fired Electric Utility, Industrial-Commercial-Institutional, and Small Industrial-Commercial-Institutional Steam Generating Units
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; notice of final action on reconsideration.
      The effective date of the rule is November 19, 2014.
      40 CFR Parts 60 and 63