43 CFR 3212.24 - How will the production incentive apply to a new facility?

§ 3212.24 How will the production incentive apply to a new facility?
(a) If BLM determines that your project qualifies as a new facility, the production incentive will begin on the first day of the month following the commencement of commercial operations at that facility, and will be in effect for 48 consecutive months. The incentive applies to the entire commercial generation of electricity from the new facility.
(b) The amount of the production incentive is established in MMS regulations at 30 CFR 218.307.

Title 43 published on 2014-10-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Public Laws