43 CFR 3261.15 - Must I give BLM my drilling permit application, drilling program, and operations plan at the same time?

§ 3261.15 Must I give BLM my drilling permit application, drilling program, and operations plan at the same time?
You may submit your completed and signed drilling permit application and complete drilling program and operations plan either together or separately.
(a) If you submit them together and we approve your drilling permit, the approved drilling permit will authorize both the pad construction and the drilling and testing of the well.
(b) If you submit the operations plan separately from the drilling permit application and program, you must:
(1) Submit the operations plan before the drilling permit application and drilling program to allow BLM time to comply with National Environmental Policy Act (NEPA); and
(2) Submit a completed and signed Sundry Notice for well pad and access road construction. Do not begin construction until we approve your Sundry Notice.

Title 43 published on 2014-10-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Public Laws