43 CFR 3273.19 - What are the bonding requirements for a site license?

§ 3273.19 What are the bonding requirements for a site license?
(a) For an electrical generation facility, the facility operator must submit a surety or personal bond to BLM for at least $100,000 that meets the requirements of subpart 3214.BLM may increase the required bond amount. See subparts 3214 and 3215 for additional details on bonding procedures.
(b) For a direct use facility, the facility operator must submit a surety or personal bond to BLM that meets the requirements of subpart 3214 in an amount BLM will specify.
(c) The bond's terms must cover compliance with the requirements of § 3200.4.
(d) Until BLM approves your bond, do not start construction, testing, or any other activity that would disturb the surface.

Title 43 published on 2013-10-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Public Laws