43 CFR § 3277.12 - What will BLM do if I do not comply with all BLM requirements pertaining to utilization operations?

prev | next
§ 3277.12 What will BLM do if I do not comply with all BLM requirements pertaining to utilization operations?

(a) We will issue you a written Incident of Noncompliance, directing you to take required corrective action within a specific time period. If the noncompliance continues or is serious in nature, BLM will take one or more of the following actions:

(1) Enter the lease, and correct any deficiencies at your expense;

(2) Collect all or part of your bond;

(3) Order modification or shutdown of your operations; and

(4) Take other enforcement action against a lessee who is ultimately responsible for the noncompliance.

(b) Noncompliance may result in BLM terminating your lease (see §§ 3213.17 through 3213.19).