43 CFR 46.240 - Establishing time limits for the NEPA process.

prev | next
§ 46.240 Establishing time limits for the NEPA process.
(a) For each proposed action, on a case-by-case basis, bureaus shall:
(1) Set time limits from the start to the finish of the NEPA analysis and documentation, consistent with the requirements of 40 CFR 1501.8 and other legal obligations, including statutory and regulatory timeframes;
(2) Consult with cooperating agencies in setting time limits; and
(3) Encourage cooperating agencies to meet established time frames.
(b) Time limits should reflect the availability of Department and bureau personnel and funds. Efficiency of the NEPA process is dependent on the management capabilities of the lead bureau, which must assemble an interdisciplinary team and/or qualified staff appropriate to the type of project to be analyzed to ensure timely completion of NEPA documents.

Title 43 published on 2013-10-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE
Presidential Documents

Executive Order ... 11514

Executive Order ... 11991