44 CFR 78.5 - Flood Mitigation Plan development.

§ 78.5 Flood Mitigation Plan development.
A Flood Mitigation Plan will articulate a comprehensive strategy for implementing technically feasible flood mitigation activities for the area affected by the plan. At a minimum, plans will include the following elements:
(a) Description of the planning process and public involvement. Public involvement may include workshops, public meetings, or public hearings.
(b) Description of the existing flood hazard and identification of the flood risk, including estimates of the number and type of structures at risk, repetitive loss properties, and the extent of flood depth and damage potential.
(c) The applicant's floodplain management goals for the area covered by the plan.
(d) Identification and evaluation of cost-effective and technically feasible mitigation actions considered.
(e) Presentation of the strategy for reducing flood risks and continued compliance with the NFIP, and procedures for ensuring implementation, reviewing progress, and recommending revisions to the plan.
(f) Documentation of formal plan adoption by the legal entity submitting the plan (e.g., Governor, Mayor, County Executive).

Title 44 published on 2013-10-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Presidential Documents

Executive Order ... 12127

Executive Order ... 12148

Executive Order ... 13286

Reorganization ... 1978 Plan No. 3