§ 79.4 Availability of funding.
(a) Allocation.
(1) For the amount made available for the SRL program, the Administrator will allocate the available funds to States each fiscal year based upon the percentage of the total number of severe repetitive loss properties located within that State. Ten percent of the total funds made available in any fiscal year will be made available to States and Indian tribal applicants that have at least 1 SRL property and that receive little or no allocation.
(2) For the amount made available for the FMA program, the Administrator will allocate the available funds each fiscal year. Funds will be distributed based upon the number of NFIP policies, repetitive loss structures, and any other such criteria as the Administrator may determine are in the best interests of the NFIF.
(i) A maximum of 7.5 percent of the amount made available in any fiscal year may be allocated for FMA planning grants nationally. A planning grant will not be awarded to a State or community more than once every 5 years, and an individual planning grant will not exceed $150,000 to any State agency applicant, or $50,000 to any community subapplicant. The total planning grant made in any fiscal year to any State, including all communities located in the State, will not exceed $300,000.
(ii) The total amount of FMA project grant funds provided during any 5-year period will not exceed $10,000,000 to any State agency(s) or $3,300,000 to any community. The total amount of project grant funds provided to any State, including all communities located in the State will not exceed $20,000,000 during any 5-year period. The Administrator may waive the limits of this subsection for any 5-year period when a major disaster or emergency is declared pursuant to the Robert T. Stafford Disaster Relief and Emergency Assistance Act for flood conditions.
(b) Redistribution. Funds allocated to States who choose not to participate in either the FMA or SRL program in any given year will be reallocated to participating States and Indian tribal applicants. Any funds allocated to a State, and the communities within the State, which have not been obligated within the timeframes established by the Administrator, shall be redistributed by the Administrator to other States and communities to carry out eligible activities in accordance with this part.
(c) Cost Share. All mitigation activities approved under the grant will be subject to the following cost-share provisions:
(1) FEMA may contribute up to 75 percent of the eligible cost of activities for grants approved for funding; or
(2) FEMA may contribute up to 90 percent of the cost of the eligible activities for each severe repetitive loss property for which grant amounts are provided if the applicant has an approved Mitigation Plan meeting the repetitive loss requirements identified in § 201.4(c)(3)(v) or § 201.7(c)(3)(vi) of this chapter, as applicable, at the time the project application is submitted;
(3) For the FMA program only, of the non-Federal contribution, not more than one half will be provided from in-kind contributions.
[72 FR 61738, Oct. 31, 2007, as amended at 74 FR 47481, Sept. 16, 2009]

Title 44 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 44.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, DEPARTMENT OF TRANSPORTATION, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF HEALTH AND HUMAN SERVICES, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF LABOR, ENVIRONMENTAL PROTECTION AGENCY, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, DEPARTMENT OF DEFENSE, NATIONAL ENDOWMENT FOR THE HUMANITIES, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Presidential Documents

Executive Order ... 12127

Executive Order ... 12148

Executive Order ... 13286

Reorganization ... 1978 Plan No. 3

Title 44 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 44 CFR 79 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, DEPARTMENT OF TRANSPORTATION, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF HEALTH AND HUMAN SERVICES, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF LABOR, ENVIRONMENTAL PROTECTION AGENCY, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, DEPARTMENT OF DEFENSE, NATIONAL ENDOWMENT FOR THE HUMANITIES, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200