46 CFR 160.156-11 - Fabrication of prototype rescue boats and fast rescue boats for approval.

Status message

There is 1 rule appearing in the Federal Register for 46 CFR 160. View below or at eCFR (GPOAccess)
§ 160.156-11 Fabrication of prototype rescue boats and fast rescue boats for approval.
(a) If the manufacturer is notified that the information submitted in accordance with § 160.156-9 of this subpart is satisfactory to the Commandant, the manufacturer may proceed with fabrication of the prototype rescue boat as set forth in this section.
(b) Unless the Commandant directs otherwise, an independent laboratory must perform or witness, as appropriate, inspections, tests, and oversight required by this section. Prototype inspections and tests of a rescue boat must be carried out in accordance with the procedures for independent laboratory inspection in 46 CFR part 159, subpart 159.007 and in this section, unless the Commandant authorizes alternative tests and inspections. The Commandant may prescribe additional prototype tests and inspections necessary to maintain quality control and to monitor compliance with the requirements of this subpart.
(c) Fabrication of a rescue boat must proceed in the following sequence:
(1) The manufacturer must arrange for an independent laboratory (or Coast Guard inspector if required under paragraph (b) of this section) to inspect, test, and oversee the rescue boat during its fabrication and prepare an inspection and test report meeting the requirements of 46 CFR 159.005-11.
(2) The independent laboratory must make such inspections as are necessary to determine that the prototype is constructed by the methods and with the materials specified in the plans reviewed under § 160.156-9 of this subpart. By conducting at least one inspection during its construction, the independent laboratory must determine the prototype rescue boat conforms with those plans by inspecting—
(i) Fiber Reinforced Plastic (FRP) Construction.
(A) FRP components of each prototype rescue boat outer hull and any FRP inner hull or liner components that are bonded or bolted to the outer hull must have a layup made of unpigmented clear resins so that details of construction are visible for inspection. Test panels representative of each prototype layup must be tested in accordance with MIL-P-17549D(SH) (incorporated by reference, see § 160.156-5 of this subpart). If an accepted MIL-R-21607E(SH) Grade B resin is used for the prototype rescue boat, additives for fire retardancy must not be used so that the laminate is translucent for inspection purposes. A prototype test rescue boat with Grade B resins will not be marked in accordance with § 160.156-17 of this subpart for use as a production rescue boat regardless of the outcome of the performance tests. Whichever accepted resin the manufacturer decides to use for the prototype rescue boat, the same resin must be used in the production rescue boats.
(B) The hull, canopy, and major structural laminates of each prototype FRP rescue boat must be tested for resin content, ultimate flexural strength, and tensile strength. The test samples must be cut out from the prototype rescue boat, or be laid up at the same time, using the same procedures and by the same operators as the laminate used in the rescue boat. The number of samples used for each test, and the conditions and test methods used, must be as per the applicable test specified in this paragraph. The resin content must be determined as per ASTM D 2584 or ISO 1172 (incorporated by reference, see § 160.156-5 of this subpart). The flexural ultimate strength must be determined by ASTM D 790 method I (test condition “A”, flatwise, dry) or the corresponding ISO 14125 test method (incorporated by reference, see § 160.156-5 of this subpart). The tensile strength, lengthwise, must be determined as per ASTM D 638 or ISO 527 (incorporated by reference, see § 160.156-5 of this subpart).
(C) Each major FRP component, such as the hull, canopy, and inner liner(s) of each prototype FRP rescue boat, must be examined and weighed after it is completed but before it is assembled. If the rescue boat is constructed by the spray lay-up technique, the hull and canopy thicknesses must be measured using ultrasonic or equivalent techniques;
(ii) Steel construction. Steel sheet and plate used for the hull, floors, and other structural components of a prototype steel rescue boat must meet the bend tests requirement specified under ASTM A 653 (incorporated by reference, see § 160.156-5 of this subpart) after galvanizing or other anti-corrosion treatment has been applied. This may be demonstrated through supplier's certification papers or through witnessing actual tests;
(iii) Welding. Structural components of each prototype rescue boat joined by welding must be joined by the welding procedures and materials per the plans reviewed under § 160.156-9 of this subpart and by welders appropriately qualified;
(iv) Buoyancy material. If block foam buoyancy material is used, each piece must be weighed after it is cut and shaped to make sure that the correct amount of foam is installed. If foamed-in-place buoyancy material is used, a separate sample of the foam must be poured, and used to make a density determination after it has set. The density must be 32 ±8 kg/m3 (2 ±0.5 lb/ft3). Each major subassembly such as the hull-with-liner and canopy-with-liner must be weighed after the buoyancy foam is installed and before it is further assembled;
(v) Coated fabric. Coated fabric for inflatable collars used in the construction of each rescue boat must meet the requirements specified under § 160.156-7(b)(3) of this subpart. This may be demonstrated through a supplier's certification papers or through witnessing actual tests;
(vi) Installation of the propulsion system; and
(vii) Installation of the steering system.
(3) The independent laboratory must submit the inspection report to the Commandant.

Title 46 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 46.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-30; vol. 79 # 146 - Wednesday, July 30, 2014
    1. 79 FR 44129 - Lifesaving Equipment: Production Testing and Harmonization With International Standards
      GPO FDSys XML | Text
      DEPARTMENT OF HOMELAND SECURITY, Coast Guard
      Final rule.
      This final rule is effective August 29, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register on August 29, 2014.
      46 CFR Parts 108, 117, 133, 160, 164, 180, and 199

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
Presidential Documents

Executive Order ... 12234

Title 46 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 46 CFR 160 after this date.

  • 2014-07-30; vol. 79 # 146 - Wednesday, July 30, 2014
    1. 79 FR 44129 - Lifesaving Equipment: Production Testing and Harmonization With International Standards
      GPO FDSys XML | Text
      DEPARTMENT OF HOMELAND SECURITY, Coast Guard
      Final rule.
      This final rule is effective August 29, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register on August 29, 2014.
      46 CFR Parts 108, 117, 133, 160, 164, 180, and 199