Skip to main content
 

47 CFR 24.249 - Payment issues.

There are 2 Updates appearing in the Federal Register for 47 CFR 24. Select the tab below to view, or View eCFR (GPOAccess)
§ 24.249
Payment issues.
(a) Timing. On the day that a PCS entity files its prior coordination notice (PCN) in accordance with § 101.103(d) of this chapter, it must file a copy of the PCN with the clearinghouse. The clearinghouse will determine if any reimbursement obligation exists and notify the PCS entity in writing of its repayment obligation, if any. When the PCS entity receives a written copy of such obligation, it must pay directly to the PCS relocator or the voluntarily relocating microwave incumbent the amount owed within thirty days, with the exception of those businesses that qualify for installment payments. A business that qualifies for an installment payment plan must make its first installment payment within thirty days of notice from the clearinghouse. UTAM's first payment will be due thirty days after its reimbursement obligation is triggered, as described in § 24.247(b).
(b) Eligibility for Installment Payments. PCS licensees that are allowed to pay for their licenses in installments under our designated entity rules will have identical payment options available to them with respect to payments under the cost-sharing plan. The specific terms of the installment payment mechanism, including the treatment of principal and interest, are the same as those applicable to the licensee's installment auction payments. If, for any reason, the entity eligible for installment payments is no longer eligible for such installment payments on its license, that entity is no longer eligible for installment payments under the cost-sharing plan. UTAM may make quarterly payments over a five-year period with an interest rate of prime plus 2.5 percent. UTAM may also negotiate separate repayment arrangements with other parties.
[61 FR 29693, June 12, 1996, as amended at 62 FR 12757, Mar. 18, 1997]

Title 47 published on 2012-10-01

The following are only the Rules published in the Federal Register after the published date of Title 47.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2013-04-11; vol. 78 # 70 - Thursday, April 11, 2013
    1. 78 FR 21555 - Signal Booster Rules
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule.
      Effective May 13, 2013, except for amendments to §§ 1.1307(b)(1), 20.3, 20.21(a)(2), 20.21(a)(5), 20.21(e)(2), 20.21(e)(8)(i)(G), 20.21(e)(9)(i)(H), 20.21(f), 20.21(h), 22.9, 24.9, 27.9, 90.203(q), 90.219(b)(1)(i), 90.219(d)(5), and 90.219(e)(5), which contain information collection requirements that are not effective until approved by the Office of Management and Budget (“OMB”). The FCC will publish a document in the Federal Register announcing the effective date for those sections.
      47 CFR Parts 1, 2, 20, 22, 24, 27, and 90

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
USC : Title 47 - TELEGRAPHS, TELEPHONES, AND RADIOTELEGRAPHS

§ 301 - License for radio communication or transmission of energy

§ 302 - Repealed. June 5, 1936, ch. 511,

§ 309 - Application for license

§ 332 - Mobile services

Title 47 published on 2012-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR 24 after this date.

  • 2013-04-11; vol. 78 # 70 - Thursday, April 11, 2013
    1. 78 FR 21555 - Signal Booster Rules
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule.
      Effective May 13, 2013, except for amendments to §§ 1.1307(b)(1), 20.3, 20.21(a)(2), 20.21(a)(5), 20.21(e)(2), 20.21(e)(8)(i)(G), 20.21(e)(9)(i)(H), 20.21(f), 20.21(h), 22.9, 24.9, 27.9, 90.203(q), 90.219(b)(1)(i), 90.219(d)(5), and 90.219(e)(5), which contain information collection requirements that are not effective until approved by the Office of Management and Budget (“OMB”). The FCC will publish a document in the Federal Register announcing the effective date for those sections.
      47 CFR Parts 1, 2, 20, 22, 24, 27, and 90