§ 25.114 Applications for space station authorizations.
(a) A comprehensive proposal shall be submitted for each proposed space station on FCC Form 312, Main Form and Schedule S, together with attached exhibits as described in paragraph (d) of this section.
(b) Each application for a new or modified space station authorization must constitute a concrete proposal for Commission evaluation. Each application must also contain the formal waiver required by section 304 of the Communications Act, 47 U.S.C. 304. The technical information for a proposed satellite system specified in paragraph (c) of this section must be filed on FCC Form 312, Main Form and Schedule S. The technical information for a proposed satellite system specified in paragraph (d) of this section need not be filed on any prescribed form but should be complete in all pertinent details. Applications for all new space station authorizations must be filed electronically through the International Bureau Filing System (IBFS) in accordance with the applicable provisions of part 1, subpart Y of this chapter.
(c) The following information shall be filed on FCC Form 312, Main Form and Schedule S:
(1) Name, address, and telephone number of the applicant;
(2) Name, address, and telephone number of the person(s), including counsel, to whom inquiries or correspondence should be directed;
(3) Type of authorization requested (e.g., launch authority, station license, modification of authorization);
(4)
(i) Radio frequencies and polarization plan (including beacon, telemetry, and telecommand functions), center frequency and polarization of transponders (both receiving and transmitting frequencies),
(ii) Emission designators and allocated bandwidth of emission, final amplifier output power (identify any net losses between output of final amplifier and input of antenna and specify the maximum EIRP for each antenna beam),
(iii) Identification of which antenna beams are connected or switchable to each transponder and TT&C function,
(iv) Receiving system noise temperature,
(v) The relationship between satellite receive antenna gain pattern and gain-to-temperature ratio and saturation flux density for each antenna beam (may be indicated on antenna gain plot),
(vi) The gain of each transponder channel (between output of receiving antenna and input of transmitting antenna) including any adjustable gain step capabilities, and
(vii) Predicted receiver and transmitter channel filter response characteristics.
(5) For satellites in geostationary-satellite orbit,
(i) Orbital location, or locations if alternatives are proposed, requested for the satellite,
(ii) The factors that support the orbital assignment or assignments proposed in paragraph (c)(5)(i) of this section,
(iii) Longitudinal tolerance or east-west station-keeping capability;
(iv) Inclination incursion or north-south station-keeping capability.
(6) For satellites in non-geostationary-satellite orbits,
(i) The number of space stations and applicable information relating to the number of orbital planes,
(ii) The inclination of the orbital plane(s),
(iii) The orbital period,
(iv) The apogee,
(v) The perigee,
(vi) The argument(s) of perigee,
(vii) Active service arc(s), and
(viii) Right ascension of the ascending node(s).
(7) For satellites in geostationary-satellite orbit, accuracy with which the orbital inclination, the antenna axis attitude, and longitudinal drift will be maintained;
(8) Calculation of power flux density levels within each coverage area and of the energy dispersal, if any, needed for compliance with § 25.208, for angles of arrival of 5°, 10°, 15°, 20°, and 25° above the horizontal;
(9) Arrangement for tracking, telemetry, and control;
(10) Physical characteristics of the space station including weight and dimensions of spacecraft, detailed mass (on ground and in-orbit) and power (beginning and end of life) budgets, and estimated operational lifetime and reliability of the space station and the basis for that estimate;
(11) A clear and detailed statement of whether the space station is to be operated on a common carrier basis, or whether non-common carrier transactions are proposed. If non-common carrier transactions are proposed, describe the nature of the transactions and specify the number of transponders to be offered on a non-common carrier basis;
(12) Dates by which construction will be commenced and completed, launch date, and estimated date of placement into service.
(13) The polarization information specified in §§ 25.210(a)(1), (a)(3), and (i), to the extent applicable.
(d) The following information in narrative form shall be contained in each application:
(1) General description of overall system facilities, operations and services;
(2) If applicable, the feeder link and inter-satellite service frequencies requested for the satellite, together with any demonstration otherwise required by this chapter for use of those frequencies (see, e.g., §§ 25.203(j) and (k));
(3) Predicted space station antenna gain contour(s) for each transmit and each receive antenna beam and nominal orbital location requested. These contour(s) should be plotted on an area map at 2 dB intervals down to 10 dB below the peak value of the parameter and at 5 dB intervals between 10 dB and 20 dB below the peak values, with the peak value and sense of polarization clearly specified on each plotted contour. For applications for geostationary orbit satellites, this information must be provided in the .gxt format.
(4) A description of the types of services to be provided, and the areas to be served, including a description of the transmission characteristics and performance objectives for each type of proposed service, details of the link noise budget, typical or baseline earth station parameters, modulation parameters, and overall link performance analysis (including an analysis of the effects of each contributing noise and interference source);
(5) Calculation of power flux density levels within each coverage area and of the energy dispersal, if any, needed for compliance with § 25.208; Calculation of power flux density levels within each coverage area and of the energy dispersal, if any, needed for compliance with § 25.208, for angles of arrival other than 5°, 10°, 15°, 20°, and 25° above the horizontal.
(6) Public interest considerations in support of grant;
(7) Applicants for authorizations for space stations in the fixed-satellite service must also include the information specified in §§ 25.140(b)(1) and (2) of this part. Applicants for authorizations for space stations in the 17/24 GHz broadcasting-satellite service must also include the information specified in § 25.140(b)(1) and §§ 25.140(b)(3), (b)(4), (b)(5), or (b)(6) of this part.
(8) Applications for authorizations in the Mobile-Satellite Service in the 1545-1559/1646.5-1660.5 MHz frequency bands shall also provide all information necessary to comply with the policies and procedures set forth in Rules and Policies Pertaining to the Use of Radio Frequencies in a Land Mobile Satellite Service, 2 FCC Rcd 485 (1987) (Available at address in § 0.445 of this chapter.);
(9) Applications to license multiple space station systems in the non-voice, non-geostationary mobile-satellite service under blanket operating authority shall also provide all information specified in § 25.142; and
(10) Applications for authorizations in the 1.6/2.4 GHz Mobile-Satellite Service shall also provide all information specified in § 25.143.
(11) In addition to a statement of whether the space station is to be operated on a common carrier basis, or whether non-common carrier transactions are proposed, as specified in paragraph (c)(11) of this section, satellite applications in the Direct Broadcast Satellite service must provide a clear and detailed statement of whether the space station is to be operated on a broadcast or non-broadcast basis.
(12) Applications for authorizations in the non-geostationary satellite orbit fixed-satellite service (NGSO FSS) in the bands 10.7 GHz to 14.5 GHz shall also provide all information specified in § 25.146.
(13) For satellite applications in the Direct Broadcast Satellite service, if the proposed system's technical characteristics differ from those specified in the Appendix 30 BSS Plans, the Appendix 30A feeder link Plans, Annex 5 to Appendix 30 or Annex 3 to Appendix 30A, each applicant shall provide:
(i) The information requested in Appendix 4 of the ITU's Radio Regulations. Further, applicants shall provide sufficient technical showing that the proposed system could operate satisfactorily if all assignments in the BSS and feeder link Plans were implemented.
(ii) Analyses of the proposed system with respect to the limits in Annex 1 to Appendices 30 and 30A.
(14) A description of the design and operational strategies that will be used to mitigate orbital debris, including the following information:
(i) A statement that the space station operator has assessed and limited the amount of debris released in a planned manner during normal operations, and has assessed and limited the probability of the space station becoming a source of debris by collisions with small debris or meteoroids that could cause loss of control and prevent post-mission disposal;
(ii) A statement that the space station operator has assessed and limited the probability of accidental explosions during and after completion of mission operations. This statement must include a demonstration that debris generation will not result from the conversion of energy sources on board the spacecraft into energy that fragments the spacecraft. Energy sources include chemical, pressure, and kinetic energy. This demonstration should address whether stored energy will be removed at the spacecraft's end of life, by depleting residual fuel and leaving all fuel line valves open, venting any pressurized system, leaving all batteries in a permanent discharge state, and removing any remaining source of stored energy, or through other equivalent procedures specifically disclosed in the application;
(iii) A statement that the space station operator has assessed and limited the probability of the space station becoming a source of debris by collisions with large debris or other operational space stations. Where a space station will be launched into a low-Earth orbit that is identical, or very similar, to an orbit used by other space stations, the statement must include an analysis of the potential risk of collision and a description of what measures the space station operator plans to take to avoid in-orbit collisions. If the space station operator is relying on coordination with another system, the statement must indicate what steps have been taken to contact, and ascertain the likelihood of successful coordination of physical operations with, the other system. The statement must disclose the accuracy—if any—with which orbital parameters of non-geostationary satellite orbit space stations will be maintained, including apogee, perigee, inclination, and the right ascension of the ascending node(s). In the event that a system is not able to maintain orbital tolerances, i.e., it lacks a propulsion system for orbital maintenance, that fact should be included in the debris mitigation disclosure. Such systems must also indicate the anticipated evolution over time of the orbit of the proposed satellite or satellites. Where a space station requests the assignment of a geostationary-Earth orbit location, it must assess whether there are any known satellites located at, or reasonably expected to be located at, the requested orbital location, or assigned in the vicinity of that location, such that the station keeping volumes of the respective satellites might overlap. If so, the statement must include a statement as to the identities of those parties and the measures that will be taken to prevent collisions;
(iv) A statement detailing the post-mission disposal plans for the space station at end of life, including the quantity of fuel—if any—that will be reserved for post-mission disposal maneuvers. For geostationary-Earth orbit space stations, the statement must disclose the altitude selected for a post-mission disposal orbit and the calculations that are used in deriving the disposal altitude. The statement must also include a casualty risk assessment if planned post-mission disposal involves atmospheric re-entry of the space station. In general, an assessment should include an estimate as to whether portions of the spacecraft will survive re-entry and reach the surface of the Earth, as well as an estimate of the resulting probability of human casualty.
(15) Each applicant for a space station license in the 17/24 GHz broadcasting-satellite service shall include the following information as an attachment to its application:
(i) Except as set forth in paragraph (d)(15)(ii) of this section, an applicant proposing to operate in the 17.3-17.7 GHz frequency band, must provide a demonstration that the proposed space station will comply with the power flux density limits set forth in § 25.208(w) of this part.
(ii) In cases where the proposed space station will not comply with the power flux density limits set forth in § 25.208(w) of this part, the applicant will be required to provide a certification that all potentially affected parties acknowledge and do not object to the use of the applicant's higher power flux densities. The affected parties with whom the applicant must coordinate are those GSO 17/24 GHz BSS satellite networks located up to ±6° away for excesses of up to 3 dB above the power flux-density levels specified in § 25.208(w) of this part, and up to ±10° away greater for excesses greater than 3 dB above those levels.
(iii) An applicant proposing to provide international service in the 17.7-17.8 GHz band must demonstrate that it will meet the power flux density limits set forth in § 25.208(c) of this part.
(iv) The information required in § 25.264(a) and (b).
(16) In addition to the requirements of paragraph (d)(15) of this section, each applicant for a license to operate a 17/24 GHz BSS space station that will be used to provide video programming directly to consumers in the United States, that will not meet the requirements of § 25.225 of this part, must include as an attachment to its application a technical analysis demonstrating that providing video programming service to consumers in Alaska and Hawaii that is comparable to the video programming service provided to consumers in the 48 contiguous United States (CONUS) is not feasible as a technical matter or that, while technically feasible, such service would require so many compromises in satellite design and operation as to make it economically unreasonable.
(17) An applicant seeking to operate a space station in the 17/24 GHz broadcasting-satellite service pursuant to the provisions of § 25.262(b) of this part, at an offset location no greater than one degree offset from an orbital location specified in Appendix F of the Report and Order adopted May 2, 2007, IB Docket No. 06-123, FCC 07-76, must submit a written request to that effect as part of the narrative portion of its application.
(18) For space stations in the Direct Broadcast Satellite service or the 17/24 GHz broadcasting-satellite service, maximum orbital eccentricity.
(e) Applicants requesting authority to launch and operate a system comprised of technically identical, non-geostationary satellite orbit space stations may file a single “blanket” application containing the information specified in paragraphs (c) and (d) of this section for each representative space station.
[68 FR 63997, Nov. 12, 2003, as amended at 69 FR 29901, May 26, 2004; 69 FR 47794, Aug. 6, 2004; 69 FR 54587, Sept. 9, 2004; 72 FR 50027, Aug. 29, 2007; 72 FR 60278, Oct. 24, 2007; 76 FR 50431, Aug. 15, 2011]

Title 47 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 47.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-09-03; vol. 79 # 170 - Wednesday, September 3, 2014
    1. 79 FR 52224 - Rules Governing the Licensing of, and Spectrum Usage by, Commercial Earth Stations and Space Stations
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule; announcement of effective date.
      47 CFR 25.170, 25.171, 25.172, 25.173, 25.285, 25.286, and 25.287, and the amendments to 47 CFR 25.103, 25.111, 25.112, 25.113, 25.114, 25.115, 25.118, 25.121, 25.129, 25.130, 25.131, 25.132, 25.133, 25.134, 25.135, 25.136, 25.138, 25.140, 25.142, 25.143, 25.144, 25.145, 25.146, 25.153, 25.154, 25.161, 25.164, 25.201, 25.202, 25.203, 25.204, 25.206, 25.208, 25.209, 25.210, 25.211, 25.212, 25.214, 25.215, 25.217, 25.218, 25.220, 25.221, 25.222, 25.223, 25.226, 25.227, 25.259, 25.260, 25.271, 25.272, 25.276, and 25.281 published February 12, 2014 (79 FR 8308) are effective September 3, 2014. The incorporation by reference of certain publications listed in 47 CFR 25.281 is approved by the Director of the Federal Register as of September 3, 2014.
      47 CFR Part 25

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 47 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR 25 after this date.

  • 2014-12-03; vol. 79 # 232 - Wednesday, December 3, 2014
    1. 79 FR 71714 - Comprehensive Review of Licensing and Operating Rules for Satellite Services
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Proposed rule; extension of comment and reply comment period.
      Comments must be received on or before January 29, 2015. Reply comments must be received on or before March 2, 2015.
      47 CFR Part 25