§ 25.149 Application requirements for ancillary terrestrial components in the mobile-satellite service networks operating in the 1.5./1.6 GHz, 1.6/2.4 GHz and 2 GHz mobile-satellite service.
(a) Applicants for ancillary terrestrial component authority shall demonstrate that the applicant does or will comply with the following through certification or explanatory technical exhibit, as appropriate:
(1) ATC shall be deployed in the forward-band mode of operation whereby the ATC mobile terminals transmit in the MSS uplink bands and the ATC base stations transmit in the MSS downlink bands in portions of the 2000-2020 MHz/2180-2200 MHz bands (2 GHz band), the 1626.5-1660.5 MHz/1525-1559 MHz bands (L-band), and the 1610-1626.5 MHz/2483.5-2500 MHz bands (Big LEO band).
Note to paragraph (a)(1):
An L-band MSS licensee is permitted to apply for ATC authorization based on a non-forward-band mode of operation provided it is able to demonstrate that the use of a non-forward-band mode of operation would produce no greater potential interference than that produced as a result of implementing the rules of this section.
(2) ATC operations shall be limited to certain frequencies:
(i) In the 2000-2020 MHz/2180-2200 MHz bands (2 GHz MSS band), ATC operations are limited to the selected assignment of the 2 GHz MSS licensee that seeks ATC authority.
(ii) In the 1626.5-1660.5 MHz/1525-1559 MHz bands (L-band), ATC operations are limited to the frequency assignments authorized and internationally coordinated for the MSS system of the MSS licensee that seeks ATC authority.
(iii) In the 1610-1626.5 MHz/2483.5-2500 MHz bands (Big LEO bands), ATC operations are limited to the 1610-1617.775 MHz, 1621.35-1626.5 MHz, and 2483.5-2495 MHz bands and to the specific frequencies authorized for use by the MSS licensee that seeks ATC authority.
(3) ATC operations shall not exceed the geographical coverage area of the mobile satellite service network of the applicant for ATC authority.
(4) ATC base stations shall comply with all applicable antenna and structural clearance requirements established in part 17 of this chapter.
(5) ATC base stations and mobile terminals shall comply with part 1 of this chapter, Subpart I—Procedures Implementing the National Environmental Policy Act of 1969, including the guidelines for human exposure to radio frequency electromagnetic fields as defined in §§ 1.1307(b) and 1.1310 of this chapter for PCS networks.
(6) ATC base station operations shall use less than all available MSS frequencies when using all available frequencies for ATC base station operations would exclude otherwise available signals from MSS space-stations.
(b) Applicants for an ancillary terrestrial component shall demonstrate that the applicant does or will comply with the following criteria through certification:
(1) Geographic and temporal coverage.
(i) For the 2 GHz MSS band, an applicant must demonstrate that it can provide space-segment service covering all 50 states, Puerto Rico, and the U.S. Virgin Islands one-hundred percent of the time, unless it is not technically possible, consistent with the coverage requirements for 2 GHz MSS GSO operators.
(ii) For the L-band, an applicant must demonstrate that it can provide space-segment service covering all 50 states, Puerto Rico, and the U.S. Virgin Islands one-hundred percent of the time, unless it is not technically possible for the MSS operator to meet the coverage criteria from its orbital position.
(iii) For the Big LEO band, an applicant must demonstrate that it can provide space-segment service to all locations as far north as 70° North latitude and as far south as 55° South latitude for at least seventy-five percent of every 24-hour period, i.e., that at least one satellite will be visible above the horizon at an elevation angle of at least 5° for at least 18 hours each day, and on a continuous basis throughout the fifty states, Puerto Rico and the U.S. Virgin Islands, i.e., that at least one satellite will be visible above the horizon at an elevation angle of at least 5° at all times.
(2) Replacement satellites.
(i) Operational NGSO MSS ATC systems shall maintain an in-orbit spare satellite.
(ii) Operational GSO MSS ATC systems shall maintain a spare satellite on the ground within one year of commencing operations and launch it into orbit during the next commercially reasonable launch window following a satellite failure.
(iii) All MSS ATC licensees must report any satellite failures, malfunctions or outages that may require satellite replacement within ten days of their occurrence.
(3) Commercial availability. Mobile-satellite service must be commercially available (viz., offering services for a fee) in accordance with the coverage requirements that pertain to each band as a prerequisite to an MSS licensee's offering ATC service.
(4) Integrated services. MSS ATC licensees shall offer an integrated service of MSS and MSS ATC. Applicants for MSS ATC may establish an integrated service offering by affirmatively demonstrating that:
(i) The MSS ATC operator will use a dual-mode handset that can communicate with both the MSS network and the MSS ATC component to provide the proposed ATC service; or
(ii) Other evidence establishing that the MSS ATC operator will provide an integrated service offering to the public.
(5) In-band operation.
(i) In the 2 GHz MSS band, MSS ATC is limited to an MSS licensee's selected assignment. MSS ATC operations on frequencies beyond the MSS licensee's selected assignment are prohibited.
(ii) In the Big LEO bands, MSS ATC is limited to no more than 7.775 MHz of spectrum in the L-band and 11.5 MHz of spectrum in the S-band. Licensees in these bands may implement ATC only on those channels on which MSS is authorized, consistent with the Big LEO band-sharing arrangement.
(iii) In the L-band, MSS ATC is limited to those frequency assignments available for MSS use in accordance with the Mexico City Memorandum of Understanding, its successor agreements or the result of other organized efforts of international coordination.
(c) Equipment certification.
(1) Each ATC MET utilized for operation under this part and each transmitter marketed, as set forth in § 2.803 of this chapter, must be of a type that has been authorized by the Commission under its certification procedure for use under this part.
(2) Any manufacturer of radio transmitting equipment to be used in these services may request equipment authorization following the procedures set forth in subpart J of part 2 of this chapter. Equipment authorization for an individual transmitter may be requested by an applicant for a station authorization by following the procedures set forth in part 2 of this chapter.
(3) Licensees and manufacturers are subject to the radiofrequency radiation exposure requirements specified in §§ 1.1307(b), 2.1091 and 2.1093 of this chapter, as appropriate. MSS ATC base stations must comply with the requirements specified in § 1.1307(b) of this chapter for PCS base stations. MSS ATC mobile terminals must comply with the requirements specified for mobile and portable PCS transmitting devices in § 1.1307(b) of this chapter. MSS ATC mobile terminals must also comply with the requirements in §§ 2.1091 and 2.1093 of this chapter for Satellite Communications Services devices. Applications for equipment authorization of mobile or portable devices operating under this section must contain a statement confirming compliance with these requirements for both fundamental emissions and unwanted emissions. Technical information showing the basis for this statement must be submitted to the Commission upon request.
(d) Applicants for an ancillary terrestrial component authority shall demonstrate that the applicant does or will comply with the provisions of §§ 1.924 and 25.203(e) through 25.203(g) and with § 25.252, § 25.253, or § 25.254, as appropriate, through certification or explanatory technical exhibit.
(e) Except as provided for in paragraph (f) of this section, no application for an ancillary terrestrial component shall be granted until the applicant has demonstrated actual compliance with the provisions of paragraph (b) of this section. Upon receipt of ATC authority, all ATC licensees must ensure continued compliance with this section and § 25.252, § 25.253, or § 25.254, as appropriate.
(f) Special provision for operational MSS systems. Applicants for MSS ATC authority with operational MSS systems that are in actual compliance with the requirements prescribed in paragraphs (b)(1), (b)(2), and (b)(3) of this section at the time of application may elect to satisfy the requirements of paragraphs (b)(4) and (b)(5) of this section prospectively by providing a substantial showing in its certification regarding how the applicant will comply with the requirements of paragraphs (b)(4) and (b)(5) of this section. Notwithstanding § 25.117(f) and paragraph (e) of this section, the Commission may grant an application for ATC authority based on such a prospective substantial showing if the Commission finds that operations consistent with the substantial showing will result in actual compliance with the requirements prescribed in paragraphs (b)(4) and (b)(5) of this section. An MSS ATC applicant that receives a grant of ATC authority pursuant to this paragraph (f) shall notify the Commission within 30 days once it begins providing ATC service. This notification must take the form of a letter formally filed with the Commission in the appropriate MSS license docket and shall contain a certification that the MSS ATC service is consistent with its ATC authority.
(g) Spectrum leasing. Leasing of spectrum rights by MSS licensees or system operators to spectrum lessees for ATC use is subject to the rules for spectrum manager leasing arrangements (see§ 1.9020) as set forth in part 1, subpart X of the rules (see§ 1.9001 et seq.). In addition, at the time of the filing of the requisite notification of a spectrum manager leasing arrangement using Form 608 (see§§ 1.9020(e) and 1.913(a)(5)), both parties to the proposed arrangement must have a complete and accurate Form 602 (see§ 1.913(a)(2)) on file with the Commission.
[68 FR 47859, Aug. 12, 2003, as amended at 69 FR 48162, Aug. 9, 2004; 70 FR 19318, Apr. 13, 2005, 73 FR 25592, May 7, 2008; 76 FR 31260, May 31, 2011]

Title 47 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 47.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-02-12; vol. 79 # 29 - Wednesday, February 12, 2014
    1. 79 FR 8308 - Comprehensive Review of Licensing and Operating Rules for Satellite Services
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule.
      The rules in this document contain information collection requirements that have not been approved by Office of Management and Budget. The Commission will publish a document in the Federal Register announcing such OMB approval, the effective date of all of the rule amendments adopted in the Report and Order, and the approval date of the incorporation by reference of a certain publication listed in the rule.
      47 CFR Part 25

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 47 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR 25 after this date.

  • 2014-02-19; vol. 79 # 33 - Wednesday, February 19, 2014
    1. 79 FR 9445 - Proposal To Enable Operation of a Terrestrial Broadband Network in Certain Mobile Satellite Service Spectrum
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Proposed rule.
      Comments are due on or before May 5, 2014 and reply comments are due on or before June 4, 2014. Written comments on the proposed information collection requirements, subject to the Paperwork Reduction Act (PRA) of 1995, Public Law 104-13, should be submitted on or before April 21, 2014.
      47 CFR Part 25