§ 25.164 Milestones.
(a) Licensees of geostationary orbit satellite systems other than DBS and DARS satellite systems, including GSO MSS satellite systems, licensed on or after August 27, 2003 will be required to comply with the schedule set forth in paragraphs (a)(1) through (a)(4) of this section in implementing their satellite systems, unless a different schedule is established by Title 47, Chapter I, or by Commission Order, or by Order adopted pursuant to delegated authority. These dates are to be measured from the date the license is issued.
(1) One year: Enter into a binding non-contingent contract to construct the licensed satellite system.
(2) Two years: Complete the critical design review of the licensed satellite system.
(3) Three years: Begin the construction of the satellite.
(4) Five years: Launch and operate the satellite.
(b) Licensees of non-geostationary orbit satellite systems other than DBS and DARS satellite systems licensed on or after September 11, 2003, will be required to comply with the schedule set forth in paragraphs (b)(1) through (b)(5) of this section in implementing their satellite systems, unless a different schedule is established by Title 47, Chapter I, or by Commission Order, or by Order adopted pursuant to delegated authority. These dates are to be measured from the date the license is issued.
(1) One year: Enter into a binding non-contingent contract to construct the licensed satellite system.
(2) Two years: Complete the critical design review of the licensed satellite system.
(3) Two years, six months: Begin the construction of the first satellite in the licensed satellite system.
(4) Three years, six months: Launch and operate the first satellite in the licensed satellite system.
(5) Six years: Bring all the satellites in the licensed satellite system into operation.
(c) Licensees of all satellite systems, other than DBS and DARS satellite systems, licensed on or after September 11, 2003, will be required to submit a copy of their binding non-contingent contract with the Commission on or before the date scheduled for entering into such a contract.
(d) Licensees of all satellite systems, other than DBS and DARS satellite systems, licensed on or after September 11, 2003, will be required to submit information to the Commission sufficient to demonstrate that the licensee has completed the critical design review of the licensed satellite system on or before the date scheduled for entering into such completion.
(e) Licensees of all satellite systems, other than DBS and DARS satellite systems, licensed on or after September 11, 2003, will be required to submit information to the Commission sufficient to demonstrate that the licensee has commenced physical construction of its licensed spacecraft on or before the date scheduled for such commencement.
(f) In cases where the Commission grants a satellite authorization in different stages, such as a license for a satellite system using feeder links or intersatellite links, the earliest of the milestone schedules shall be applied to the entire satellite system.
(g) Licensees of satellite systems that include both non-geostationary orbit satellites and geostationary orbit satellites, other than DBS and DARS satellite systems, and licensed on or after September 20, 2004 will be required to comply with the schedule set forth in paragraph (a) of this section with respect to the geostationary orbit satellites, and with the schedule set forth in paragraph (b) of this section with respect to the non-geostationary orbit satellites.
[68 FR 51507, Aug. 27, 2003, as amended at 69 FR 51587, Aug. 20, 2004]

Title 47 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 47.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-31; vol. 79 # 147 - Thursday, July 31, 2014
    1. 79 FR 44312 - Comprehensive Review of Licensing and Operating Rules for Satellite Services.
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule; correction.
      The final rule published February 12, 2014, at 79 FR 8308, contains information collection requirements that have not been approved by the Office of Management and Budget (OMB). The Commission will publish a document in the Federal Register announcing the effective date of the rule, this correction, and all other rules adopted by FCC 13-111 after receiving approval from the OMB for the information collection requirements contained in the rulemaking.
      47 CFR Part 25

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 47 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR 25 after this date.

  • 2014-07-31; vol. 79 # 147 - Thursday, July 31, 2014
    1. 79 FR 44312 - Comprehensive Review of Licensing and Operating Rules for Satellite Services.
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule; correction.
      The final rule published February 12, 2014, at 79 FR 8308, contains information collection requirements that have not been approved by the Office of Management and Budget (OMB). The Commission will publish a document in the Federal Register announcing the effective date of the rule, this correction, and all other rules adopted by FCC 13-111 after receiving approval from the OMB for the information collection requirements contained in the rulemaking.
      47 CFR Part 25