§ 69.124 Interconnection charge.
(a) Until December 31, 2001, local exchange carriers not subject to price cap regulation shall assess an interconnection charge expressed in dollars and cents per access minute upon all interexchange carriers and upon all other persons using the telephone company switched access network.
(b) If the use made of the local exchange carrier's switched access network includes the local switch, but not local transport, the interconnection charge assessed pursuant to paragraph (a) of this section shall be computed by subtracting entrance facilities, tandem-switched transport, direct-trunked transport, and dedicated signalling transport revenues, as well as any interconnection charge revenues that the local exchange carrier anticipates will be reassigned to other, facilities-based rate elements in the future, from the part 69 transport revenue requirement, and dividing by the total interstate local switching minutes.
(c) If the use made of the local exchange carrier's switched access network includes local transport, the interconnection charge to be assessed pursuant to paragraph (a) of this section shall be computed by dividing any interconnection charge revenues that the local exchange carrier anticipates will be reassigned to other, facilities-based rate elements in the future by the total interstate local transport minutes, and adding thereto the per minute amount calculated pursuant to paragraph (b) of this section.
[62 FR 66030, Dec. 17, 1997, as amended at 66 FR 59732, Nov. 30, 2001]

Title 47 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 47.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-09-26; vol. 79 # 187 - Friday, September 26, 2014
    1. 79 FR 57810 - Special Access Proceeding; Effective Date for Data Collection
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule; announcement of effective date.
      On December 11, 2012, the Commission adopted a Report and Order and Further Notice of Proposed Rulemaking ( Report and Order ) regarding the special access data collection and stated that the information collection would not go into effect until OMB approved the collection and the Commission published a notice in the Federal Register announcing the effective date of the collection. FCC 12-153, 78 FR 2572 (Jan. 11, 2013). On August 15, 2014, OMB approved the data collection requirement and assigned this new information collection OMB Control Number 3060-1197, as required by PRA. Accordingly, the information collection requirement contained in the Report and Order is effective September 26, 2014. The Commission's Wireline Competition Bureau (Bureau) will separately announce a deadline for responding to the collection.
      47 CFR Part 69

Title 47 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR 69 after this date.

  • 2014-09-26; vol. 79 # 187 - Friday, September 26, 2014
    1. 79 FR 57810 - Special Access Proceeding; Effective Date for Data Collection
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule; announcement of effective date.
      On December 11, 2012, the Commission adopted a Report and Order and Further Notice of Proposed Rulemaking ( Report and Order ) regarding the special access data collection and stated that the information collection would not go into effect until OMB approved the collection and the Commission published a notice in the Federal Register announcing the effective date of the collection. FCC 12-153, 78 FR 2572 (Jan. 11, 2013). On August 15, 2014, OMB approved the data collection requirement and assigned this new information collection OMB Control Number 3060-1197, as required by PRA. Accordingly, the information collection requirement contained in the Report and Order is effective September 26, 2014. The Commission's Wireline Competition Bureau (Bureau) will separately announce a deadline for responding to the collection.
      47 CFR Part 69