32.1004 Procedures.
Performance-based payments may be made either on a whole contract or on a deliverable item basis, unless otherwise prescribed by agency regulations. Financing payments to be made on a whole contract basis are applicable to the entire contract, and not to specific deliverable items. Financing payments to be made on a deliverable item basis are applicable to a specific individual deliverable item. (A deliverable item for these purposes is a separate item with a distinct unit price. Thus, a contract line item for 10 airplanes, with a unit price of $1,000,000 each, has 10 deliverable items-the separate planes. A contract line item for 1 lot of 10 airplanes, with a lot price of $10,000,000, has only one deliverable item-the lot.)
(a) Establishing performance bases.
(1) The basis for performance-based payments may be either specifically described events (e.g., milestones) or some measurable criterion of performance. Each event or performance criterion that will trigger a finance payment shall be an integral and necessary part of contract performance and shall be identified in the contract, along with a description of what constitutes successful performance of the event or attainment of the performance criterion. The signing of contracts or modifications, the exercise of options, the passage of time, or other such occurrences do not represent meaningful efforts or actions and shall not be identified as events or criteria for performance-based payments. An event need not be a critical event in order to trigger a payment, but the Government must be able to readily verify successful performance of each such event or performance criterion.
(2) Events or criteria may be either severable or cumulative. The successful completion of a severable event or criterion is independent of the accomplishment of any other event or criterion. Conversely, the successful accomplishment of a cumulative event or criterion is dependent upon the previous accomplishment of another event. A contract may provide for more than one series of severable and/or cumulative performance events or criteria performed in parallel. The contracting officer shall include the following in the contract:
(i) The contract shall not permit payment for a cumulative event or criterion until the dependent event or criterion has been successfully completed.
(ii) The contract shall specifically identify severable events or criteria.
(iii) The contract shall specifically identify cumulative events or criteria and identify which events or criteria are preconditions for the successful achievement of each event or criterion.
(iv) Because performance-based payments are contract financing, events or criteria shall not serve as a vehicle to reward the contractor for completion of performance levels over and above what is required for successful completion of the contract.
(v) If payment of performance-based finance amounts is on a deliverable item basis, each event or performance criterion shall be part of the performance necessary for that deliverable item and shall be identified to a specific contract line item or subline item.
(b) Establishing performance-based finance payment amounts.
(1) The contracting officer shall establish a complete, fully defined schedule of events or performance criteria and payment amounts when negotiating contract terms. If a contract action significantly affects the price, or event or performance criterion, the contracting officer responsible for pricing the contract modification shall adjust the performance-based payment schedule appropriately.
(2) Total performance-based payments shall—
(i) Reflect prudent contract financing provided only to the extent needed for contract performance (see 32.104(a)); and
(ii) Not exceed 90 percent of the contract price if on a whole contract basis, or 90 percent of the delivery item price if on a delivery item basis.
(3) The contract shall specifically state the amount of each performance-based payment either as a dollar amount or as a percentage of a specifically identified price (e.g., contract price or unit price of the deliverable item). The payment of contract financing has a cost to the Government in terms of interest paid by the Treasury to borrow funds to make the payment. Because the contracting officer has wide discretion as to the timing and amount of the performance-based payments, the contracting officer shall ensure that—
(i) The total contract price is fair and reasonable, all factors considered; and
(ii) Performance-based payment amounts are commensurate with the value of the performance event or performance criterion and are not expected to result in an unreasonably low or negative level of contractor investment in the contract. To confirm sufficient investment, the contracting officer may request expenditure profile information from offerors, but only if other information in the proposal, or information otherwise available to the contracting officer, is expected to be insufficient.
(4) Unless agency procedures prescribe the bases for establishing performance-based payment amounts, contracting officers may establish them on any rational basis, including (but not limited to)—
(i) Engineering estimates of stages of completion;
(ii) Engineering estimates of hours or other measures of effort to be expended in performance of an event or achievement of a performance criterion; or
(iii) The estimated projected cost of performance of particular events.
(5) When subsequent contract modifications are issued, the contracting officer shall adjust the performance-based payment schedule as necessary to reflect the actions required by those contract modifications.
(c) Instructions for multiple appropriations. If there is more than one appropriation account (or subaccount) funding payments on the contract, the contracting officer shall provide instructions to the Government payment office for distribution of financing payments to the respective funds accounts. Distribution instructions shall be consistent with the contract's liquidation provisions.
(d) Liquidating performance-based finance payments. Performance-based amounts shall be liquidated by deducting a percentage or a designated dollar amount from the delivery payments. The contracting officer shall specify the liquidation rate or designated dollar amount in the contract. The method of liquidation shall ensure complete liquidation no later than final payment.
(1) If the contracting officer establishes the performance-based payments on a delivery item basis, the liquidation amount for each line item is the percent of that delivery item price that was previously paid under performance-based finance payments or the designated dollar amount.
(2) If the performance-based finance payments are on a whole contract basis, liquidation is by predesignated liquidation amounts or liquidation percentages.
(e) Competitive negotiated solicitations.
(1) If a solicitation requests offerors to propose performance-based payments, the solicitation shall specify—
(i) What, if any, terms shall be included in all offers; and
(ii) The extent to which and how offeror-proposed performance-based payment terms will be evaluated. Unless agencies prescribe other evaluation procedures, if the contracting officer anticipates that the cost of providing performance-based payments would have a significant impact on determining the best value offer, the solicitation should state that the evaluation of the offeror's proposed prices will include an adjustment to reflect the estimated cost to the Government of providing each offeror's proposed performance-based payments (see Alternate I to the provision at 52.232-28).
(2) The contracting officer shall—
(i) Review the proposed terms to ensure they comply with this section; and
(ii) Use the adjustment method at 32.205(c) if the price is to be adjusted for evaluation purposes in accordance with paragraph (e)(1)(ii) of this section.
[72 FR 73220, Dec. 26, 2007]

Title 48 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 48.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-25; vol. 79 # 143 - Friday, July 25, 2014
    1. 79 FR 43590 - Federal Acquisition Regulation; Technical Amendments
      GPO FDSys XML | Text
      DEPARTMENT OF DEFENSE, GENERAL SERVICES ADMINISTRATION, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
      Final rule.
      Effective: July 25, 2014.
      48 CFR Parts 4 and 32

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 10 - ARMED FORCES

§ 2301 - Repealed.

§ 2302 - Definitions

§ 2302a - Simplified acquisition threshold

§ 2302b - Implementation of simplified acquisition procedures

§ 2302c - Implementation of electronic commerce capability

§ 2302d - Major system: definitional threshold amounts

§ 2303 - Applicability of chapter

§ 2303a - Repealed.

§ 2304 - Contracts: competition requirements

§ 2304a - Task and delivery order contracts: general authority

§ 2304b - Task order contracts: advisory and assistance services

§ 2304c - Task and delivery order contracts: orders

§ 2304d - Task and delivery order contracts: definitions

§ 2304e - Contracts: prohibition on competition between Department of Defense and small businesses and certain other entities

§ 2305 - Contracts: planning, solicitation, evaluation, and award procedures

§ 2305a - Design-build selection procedures

§ 2306 - Kinds of contracts

§ 2306a - Cost or pricing data: truth in negotiations

§ 2306b - Multiyear contracts: acquisition of property

§ 2306c - Multiyear contracts: acquisition of services

§ 2307 - Contract financing

§ 2308 - Buy-to-budget acquisition: end items

§ 2309 - Allocation of appropriations

§ 2310 - Determinations and decisions

§ 2311 - Assignment and delegation of procurement functions and responsibilities

§ 2312 - Remission of liquidated damages

§ 2313 - Examination of records of contractor

§ 2313a - Defense Contract Audit Agency: annual report

§ 2314 - Laws inapplicable to agencies named in

§ 2315 - Law inapplicable to the procurement of automatic data processing equipment and services for certain defense purposes

§ 2316 - Disclosure of identity of contractor

§ 2317 - Repealed.

§ 2318 - Advocates for competition

§ 2319 - Encouragement of new competitors

§ 2320 - Rights in technical data

§ 2321 - Validation of proprietary data restrictions

§ 2322 - Repealed.

§ 2323 - Contract goal for small disadvantaged businesses and certain institutions of higher education

§ 2323a - Credit for Indian contracting in meeting certain subcontracting goals for small disadvantaged businesses and certain institutions of higher education

§ 2324 - Allowable costs under defense contracts

§ 2325 - Restructuring costs

§ 2326 - Undefinitized contractual actions: restrictions

§ 2327 - Contracts: consideration of national security objectives

§ 2328 - Release of technical data under Freedom of Information Act: recovery of costs

§ 2329 - Repealed.

§ 2330 - Procurement of contract services: management structure

§ 2330a - Procurement of services: tracking of purchases

§ 2331 - Procurement of services: contracts for professional and technical services

§ 2332 - Share-in-savings contracts

§ 2333 - Joint policies on requirements definition, contingency program management, and contingency contracting

§ 2334 - Independent cost estimation and cost analysis

§ 2335 - Prohibition on collection of political information

§ 2336 - Intergovernmental support agreements with State and local governments

§ 2337 - Life-cycle management and product support

U.S. Code: Title 40 - PUBLIC BUILDINGS, PROPERTY, AND WORKS
U.S. Code: Title 51 - NATIONAL AND COMMERCIAL SPACE PROGRAMS

Title 48 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 48 CFR 32 after this date.

  • 2014-07-25; vol. 79 # 143 - Friday, July 25, 2014
    1. 79 FR 43590 - Federal Acquisition Regulation; Technical Amendments
      GPO FDSys XML | Text
      DEPARTMENT OF DEFENSE, GENERAL SERVICES ADMINISTRATION, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
      Final rule.
      Effective: July 25, 2014.
      48 CFR Parts 4 and 32