48 CFR 48.001 - Definitions.

Status message

There is 1 rule appearing in the Federal Register for 48 CFR 48. View below or at eCFR (GPOAccess)
prev | next
48.001 Definitions.
As used in this subpart—
Acquisition savings means savings resulting from the application of a value engineering change proposal (VECP) to contracts awarded by the same contracting office of its successor for essentially the same unit. Acquisition savings include—
(1) Instant contract savings, that are the net cost reductions on the contract under which the VECP is submitted and accepted, and that are equal to the instant unit cost reduction multiplied by the number of instant contract units affected by the VECP, less the contractor's allowable development and implementation costs;
(2) Concurrent contract savings, that are net reductions in the prices of other contracts that are definitized and ongoing at the time the VECP is accepted; and
(3) Future contract savings, that are the product of the future unit cost reduction multiplied by the number of future contract units in the sharing base. On an instant contract, future contract savings include savings on increases in quantities after VECP acceptance that are due to contract modifications, exercise of options, additional orders, and funding of subsequent year requirements on a multiyear contract.
Collateral costs means agency costs of operation, maintenance logistic support, or Government-furnished property.
Collateral savings means those measurable net reductions resulting from a VECP in the agency's overall projected collateral costs, exclusive of acquisition savings, whether or not the acquisition cost changes.
Contracting office includes any contracting office that the acquisition is transferred to, such as another branch of the agency or another agency's office that is performing a joint acquisition action.
Contractor's development and implementation costs means those costs the contractor incurs on a VECP specifically in developing, testing, preparing, and submitting the VECP, as well as those costs the contractor incurs to make the contractual changes required by Government acceptance of a VECP.
Future unit cost reduction means the instant unit cost reduction adjusted as the contracting officer considers necessary for projected learning or changes in quantity during the sharing period. It is calculated at the time the VECP is accepted and applies either (1) throughout the sharing period, unless the contracting officer decides that recalculation is necessary because conditions are significantly different from those previously anticipated or (2) to the calculation of a lump-sum payment, that cannot later be revised.
Government costs means those agency costs that result directly from developing and implementing the VECP, such as any net increases in the cost of testing, operations, maintenance, and logistics support. The term does not include the normal administrative costs of processing the VECP or any increase in instant contract cost or price resulting from negative instant contract savings, except that for use in 52.248-3, see the definition at 52.248-3(b).
Instant contract means the contract under which the VECP is submitted. It does not include increases in quantities after acceptance of the VECP that are due to contract modifications, exercise of options, or additional orders. If the contract is a multiyear contract, the term does not include quantities funded after VECP acceptance. In a fixed-price contract with prospective price redetermination, the term refers to the period for which firm prices have been established.
Instant unit cost reduction means the amount of the decrease in unit cost of performance (without deducting any contractor's development or implementation costs) resulting from using the VECP on the instant contract. In service contracts, the instant unit cost reduction is normally equal to the number of hours per line-item task saved by using the VECP on the instant contract, multiplied by the appropriate contract labor rate.
Negative instant contract savings means the increase in the instant contract cost or price when the acceptance of a VECP results in an excess of the contractor's allowable development and implementation costs over the product of the instant unit cost reduction multiplied by the number of instant contract units affected.
Net acquisition savings means total acquisition savings, including instant, concurrent, and future contract savings, less Government costs.
Sharing base means the number of affected end items on contracts of the contracting office accepting the VECP.
Sharing period means the period beginning with acceptance of the first unit incorporating the VECP and ending at a calendar date or event determined by the contracting officer for each VECP.
Unit means the item or task to which the contracting officer and the contractor agree the VECP applies.
Value engineering proposal means, in connection with an A-E contract, a change proposal developed by employees of the Federal Government or contractor value engineering personnel under contract to an agency to provide value engineering services for the contract or program.
[48 FR 42443, Sept. 19, 1983, as amended at 54 FR 5057, Jan. 31, 1989; 55 FR 3887, Feb. 5, 1990; 61 FR 39220, July 26, 1996; 64 FR 51847, Sept. 24, 1999; 66 FR 2134, Jan. 10, 2001]

Title 48 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 48.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-04-29; vol. 79 # 82 - Tuesday, April 29, 2014
    1. 79 FR 24192 - Federal Acquisition Regulation; Positive Law Codification of Title 41
      GPO FDSys XML | Text
      DEPARTMENT OF DEFENSE, GENERAL SERVICES ADMINISTRATION, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
      Final rule.
      Effective: May 29, 2014.
      48 CFR Parts 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 19, 22, 23, 24, 25, 26, 27, 28, 30, 31, 32, 33, 36, 37, 38, 39, 41, 42, 43, 44, 46, 47, 48, 50, 51, 52, and 53

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 10 - ARMED FORCES

§ 2301 - Repealed.

§ 2302 - Definitions

§ 2302a - Simplified acquisition threshold

§ 2302b - Implementation of simplified acquisition procedures

§ 2302c - Implementation of electronic commerce capability

§ 2302d - Major system: definitional threshold amounts

§ 2303 - Applicability of chapter

§ 2303a - Repealed.

§ 2304 - Contracts: competition requirements

§ 2304a - Task and delivery order contracts: general authority

§ 2304b - Task order contracts: advisory and assistance services

§ 2304c - Task and delivery order contracts: orders

§ 2304d - Task and delivery order contracts: definitions

§ 2304e - Contracts: prohibition on competition between Department of Defense and small businesses and certain other entities

§ 2305 - Contracts: planning, solicitation, evaluation, and award procedures

§ 2305a - Design-build selection procedures

§ 2306 - Kinds of contracts

§ 2306a - Cost or pricing data: truth in negotiations

§ 2306b - Multiyear contracts: acquisition of property

§ 2306c - Multiyear contracts: acquisition of services

§ 2307 - Contract financing

§ 2308 - Buy-to-budget acquisition: end items

§ 2309 - Allocation of appropriations

§ 2310 - Determinations and decisions

§ 2311 - Assignment and delegation of procurement functions and responsibilities

§ 2312 - Remission of liquidated damages

§ 2313 - Examination of records of contractor

§ 2313a - Defense Contract Audit Agency: annual report

§ 2314 - Laws inapplicable to agencies named in

§ 2315 - Law inapplicable to the procurement of automatic data processing equipment and services for certain defense purposes

§ 2316 - Disclosure of identity of contractor

§ 2317 - Repealed.

§ 2318 - Advocates for competition

§ 2319 - Encouragement of new competitors

§ 2320 - Rights in technical data

§ 2321 - Validation of proprietary data restrictions

§ 2322 - Repealed.

§ 2323 - Contract goal for small disadvantaged businesses and certain institutions of higher education

§ 2323a - Credit for Indian contracting in meeting certain subcontracting goals for small disadvantaged businesses and certain institutions of higher education

§ 2324 - Allowable costs under defense contracts

§ 2325 - Restructuring costs

§ 2326 - Undefinitized contractual actions: restrictions

§ 2327 - Contracts: consideration of national security objectives

§ 2328 - Release of technical data under Freedom of Information Act: recovery of costs

§ 2329 - Repealed.

§ 2330 - Procurement of contract services: management structure

§ 2330a - Procurement of services: tracking of purchases

§ 2331 - Procurement of services: contracts for professional and technical services

§ 2332 - Share-in-savings contracts

§ 2333 - Joint policies on requirements definition, contingency program management, and contingency contracting

§ 2334 - Independent cost estimation and cost analysis

§ 2335 - Prohibition on collection of political information

§ 2336 - Intergovernmental support agreements with State and local governments

§ 2337 - Life-cycle management and product support

U.S. Code: Title 40 - PUBLIC BUILDINGS, PROPERTY, AND WORKS
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

Title 48 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 48 CFR 48 after this date.

  • 2014-04-29; vol. 79 # 82 - Tuesday, April 29, 2014
    1. 79 FR 24192 - Federal Acquisition Regulation; Positive Law Codification of Title 41
      GPO FDSys XML | Text
      DEPARTMENT OF DEFENSE, GENERAL SERVICES ADMINISTRATION, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
      Final rule.
      Effective: May 29, 2014.
      48 CFR Parts 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 19, 22, 23, 24, 25, 26, 27, 28, 30, 31, 32, 33, 36, 37, 38, 39, 41, 42, 43, 44, 46, 47, 48, 50, 51, 52, and 53