Skip to main content
 

48 CFR 50.103-3 - Contract adjustment.

50.103-3
Contract adjustment.
(a) Contractor requests. A contractor seeking a contract adjustment shall submit a request in duplicate to the contracting officer or an authorized representative. The request, normally a letter, shall state as a minimum—
(1) The precise adjustment requested;
(2) The essential facts, summarized chronologically in narrative form;
(3) The contractor's conclusions based on these facts, showing, in terms of the considerations set forth in 50.103-1 and 50.103-2, when the contractor considers itself entitled to the adjustment; and
(4) Whether or not—
(i) All obligations under the contracts involved have been discharged;
(ii) Final payment under the contracts involved has been made;
(iii) Any proceeds from the request will be subject to assignment or other transfer, and to whom; and
(iv) The contractor has sought the same, or a similar or related, adjustment from the Government Accountability Office or any other part of the Government, or anticipates doing so.
(b) Contractor certification. A contractor seeking a contract adjustment that exceeds the simplified acquisition threshold shall, at the time the request is submitted, submit a certification by a person authorized to certify the request on behalf of the contractor that—
(1) The request is made in good faith; and
(2) The supporting data are accurate and complete to the best of that person's knowledge and belief.

Title 48 published on 2012-10-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.