48 CFR 52.215-11 - Price Reduction for Defective Certified Cost or Pricing Data

Status message

There are 6 Updates appearing in the Federal Register for 48 CFR 52. View below or at eCFR (GPOAccess)
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications.
As prescribed in 15.408(c), insert the following clause:
Price Reduction for Defective Certified Cost or Pricing Data—Modifications (AUG 2011)
(a) This clause shall become operative only for any modification to this contract involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data at FAR 15.403-4, except that this clause does not apply to any modification if an exception under FAR 15.403-1 applies.
(b) If any price, including profit or fee, negotiated in connection with any modification under this clause, or any cost reimbursable under this contract, was increased by any significant amount because (1) the Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data, (2) a subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor's Certificate of Current Cost or Pricing Data, or (3) any of these parties furnished data of any description that were not accurate, the price or cost shall be reduced accordingly and the contract shall be modified to reflect the reduction. This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause.
(c) Any reduction in the contract price under paragraph (b) of this clause due to defective data from a prospective subcontractor that was not subsequently awarded the subcontract shall be limited to the amount, plus applicable overhead and profit markup, by which (1) the actual subcontract or (2) the actual cost to the Contractor, if there was no subcontract, was less than the prospective subcontract cost estimate submitted by the Contractor; provided, that the actual subcontract price was not itself affected by defective certified cost or pricing data.
(d)(1) If the Contracting Officer determines under paragraph (b) of this clause that a price or cost reduction should be made, the Contractor agrees not to raise the following matters as a defense:
(i) The Contractor or subcontractor was a sole source supplier or otherwise was in a superior bargaining position and thus the price of the contract would not have been modified even if accurate, complete, and current certified cost or pricing data had been submitted.
(ii) The Contracting Officer should have known that the certified cost or pricing data in issue were defective even though the Contractor or subcontractor took no affirmative action to bring the character of the data to the attention of the Contracting Officer.
(iii) The contract was based on an agreement about the total cost of the contract and there was no agreement about the cost of each item procured under the contract.
(iv) The Contractor or subcontractor did not submit a Certificate of Current Cost or Pricing Data.
(2)(i) Except as prohibited by subdivision (d)(2)(ii) of this clause, an offset in an amount determined appropriate by the Contracting Officer based upon the facts shall be allowed against the amount of a contract price reduction if—
(A) The Contractor certifies to the Contracting Officer that, to the best of the Contractor's knowledge and belief, the Contractor is entitled to the offset in the amount requested; and
(B) The Contractor proves that the certified cost or pricing data were available before the “as of” date specified on its Certificate of Current Cost or Pricing Data, and that the data were not submitted before such date.
(ii) An offset shall not be allowed if—
(A) The understated data were known by the Contractor to be understated before the “as of” date specified on its Certificate of Current Cost or Pricing Data; or
(B) The Government proves that the facts demonstrate that the contract price would not have increased in the amount to be offset even if the available data had been submitted before the “as of” date specified on its Certificate of Current Cost or Pricing Data.
(e) If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid—
(1) Interest compounded daily, as required by 26 U.S.C. 6622, on the amount of such overpayment to be computed from the date(s) of overpayment to the Contractor to the date the Government is repaid by the Contractor at the applicable underpayment rate effective for each quarter prescribed by the Secretary of the Treasury under 26 U.S.C. 6621(a)(2); and
(2) A penalty equal to the amount of the overpayment, if the Contractor or subcontractor knowingly submitted certified cost or pricing data that were incomplete, inaccurate, or noncurrent.
(End of clause)
[62 FR 51262, Sept. 30, 1997, as amended at 75 FR 53151, Aug. 30, 2010; 76 FR 39243, July 5, 2011 ]

Title 48 published on 2014-10-01

The following are only the Rules published in the Federal Register after the published date of Title 48.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-11-25; vol. 79 # 227 - Tuesday, November 25, 2014
    1. 79 FR 70341 - Federal Acquisition Regulation; Incorporating Section K in Contracts
      GPO FDSys XML | Text
      DEPARTMENT OF DEFENSE, GENERAL SERVICES ADMINISTRATION, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
      Final rule.
      Effective: December 26, 2014.
      48 CFR Parts 4, 14, 15, and 52

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 10 - ARMED FORCES

§ 2301 - Repealed.

§ 2302 - Definitions

§ 2302a - Simplified acquisition threshold

§ 2302b - Implementation of simplified acquisition procedures

§ 2302c - Implementation of electronic commerce capability

§ 2302d - Major system: definitional threshold amounts

§ 2303 - Applicability of chapter

§ 2303a - Repealed.

§ 2304 - Contracts: competition requirements

§ 2304a - Task and delivery order contracts: general authority

§ 2304b - Task order contracts: advisory and assistance services

§ 2304c - Task and delivery order contracts: orders

§ 2304d - Task and delivery order contracts: definitions

§ 2304e - Contracts: prohibition on competition between Department of Defense and small businesses and certain other entities

§ 2305 - Contracts: planning, solicitation, evaluation, and award procedures

§ 2305a - Design-build selection procedures

§ 2306 - Kinds of contracts

§ 2306a - Cost or pricing data: truth in negotiations

§ 2306b - Multiyear contracts: acquisition of property

§ 2306c - Multiyear contracts: acquisition of services

§ 2307 - Contract financing

§ 2308 - Buy-to-budget acquisition: end items

§ 2309 - Allocation of appropriations

§ 2310 - Determinations and decisions

§ 2311 - Assignment and delegation of procurement functions and responsibilities

§ 2312 - Remission of liquidated damages

§ 2313 - Examination of records of contractor

§ 2313a - Defense Contract Audit Agency: annual report

§ 2314 - Laws inapplicable to agencies named in

§ 2315 - Law inapplicable to the procurement of automatic data processing equipment and services for certain defense purposes

§ 2316 - Disclosure of identity of contractor

§ 2317 - Repealed.

§ 2318 - Advocates for competition

§ 2319 - Encouragement of new competitors

§ 2320 - Rights in technical data

§ 2321 - Validation of proprietary data restrictions

§ 2322 - Repealed.

§ 2323 - Contract goal for small disadvantaged businesses and certain institutions of higher education

§ 2323a - Credit for Indian contracting in meeting certain subcontracting goals for small disadvantaged businesses and certain institutions of higher education

§ 2324 - Allowable costs under defense contracts

§ 2325 - Restructuring costs

§ 2326 - Undefinitized contractual actions: restrictions

§ 2327 - Contracts: consideration of national security objectives

§ 2328 - Release of technical data under Freedom of Information Act: recovery of costs

§ 2329 - Repealed.

§ 2330 - Procurement of contract services: management structure

§ 2330a - Procurement of services: tracking of purchases

§ 2331 - Procurement of services: contracts for professional and technical services

§ 2332 - Share-in-savings contracts

§ 2333 - Joint policies on requirements definition, contingency program management, and contingency contracting

§ 2334 - Independent cost estimation and cost analysis

§ 2335 - Prohibition on collection of political information

§ 2336 - Intergovernmental support agreements with State and local governments

§ 2337 - Life-cycle management and product support

U.S. Code: Title 40 - PUBLIC BUILDINGS, PROPERTY, AND WORKS
U.S. Code: Title 51 - NATIONAL AND COMMERCIAL SPACE PROGRAMS

Title 48 published on 2014-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 48 CFR 52 after this date.

  • 2014-12-04; vol. 79 # 233 - Thursday, December 4, 2014
    1. 79 FR 71975 - Federal Acquisition Regulation: Information on Corporate Contractor Performance and Integrity
      GPO FDSys XML | Text
      DEPARTMENT OF DEFENSE, GENERAL SERVICES ADMINISTRATION, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
      Proposed rule.
      Interested parties should submit written comments to the Regulatory Secretariat at one of the addresses shown below on or before February 2, 2015 to be considered in the formation of the final rule.
      48 CFR Parts 1, 4, 9, 22, and 52