49 CFR 173.121 - Class 3

Status message

There are 10 Updates appearing in the Federal Register for 49 CFR 173. View below or at eCFR (GPOAccess)
§ 173.121 Class 3—Assignment of packing group.
(a)
(1) The packing group of a Class 3 material is as assigned in column 5 of the § 172.101 Table. When the § 172.101 Table provides more than one packing group for a hazardous material, the packing group must be determined by applying the following criteria:
Packing group Flash point (closed-cup) Initial boiling point
I ≤35 °C(95 °F)
II <23 °C (73 °F) >35 °C(95 °F)
III ≥23 °C, ≤60 °C(≥73 °F, ≤140 °F) >35 °C(95 °F)
(2) The initial boiling point of a Class 3 material may be determined by using one of the following test methods:
(i) Standard Test Method for Distillation of Petroleum Products at Atmospheric Pressure (ASTM D 86) (IBR; see§ 171.7 of this subchapter);
(ii) Standard Test Method for Distillation Range of Volatile Organic Liquids (ASTM D 1078) (IBR; see§ 171.7 of this subchapter);
(iii) Petroleum Products—Determination of Distillation Characteristics at Atmospheric Pressure (ISO 3405) (IBR; see§ 171.7 of this subchapter);
(iv) Petroleum Products—Determination of Boiling Range Distribution—Gas Chromatography Method (ISO 3924) (IBR; see§ 171.7 of this subchapter); or
(v) Volatile Organic Liquids—Determination of Boiling Range of Organic Solvents Used as Raw Materials (ISO 4626) (IBR; see§ 171.7 of this subchapter).
(b) Criteria for inclusion of viscous Class 3 materials in Packing Group III.
(1) Viscous Class 3 materials in Packing Group II with a flash point of less than 23 °C (73 °F) may be grouped in Packing Group III provided that—
(i) Less than 3 percent of the clear solvent layer separates in the solvent separation test;
(ii) The mixture does not contain any substances with a primary or a subsidiary risk of Division 6.1 or Class 8;
(iii) The capacity of the packaging is not more than 30 L (7.9 gallons); and
(iv) The viscosity and flash point are in accordance with the following table:
Flow time t in seconds Jet diameter in mm Flash point c.c.
20<t≤60 4 above 17 °C (62.6 °F).
60<t≤100 4 above 10 °C (50 °F).
20<t≤32 6 above 5 °C (41 °F).
32<t≤44 6 above −1 °C (31.2 °F).
44<t≤100 6 above −5 °C (23 °F).
100<t 6 −5 °C (23 °F) and below.
(2) The methods by which the tests referred to in paragraph (b)(1) of this section shall be performed are as follows:
(i) Viscosity test. The flow time in seconds is determined at 23 °C (73.4 °F) using the ISO standard cup with a 4 mm (0.16 inch) jet as set forth in ISO 2431 (IBR, see § 171.7 of this subchapter). Where the flow time exceeds 100 seconds, a further test is carried out using the ISO standard cup with a 6 mm (0.24 inch) jet.
(ii) Solvent Separation Test. This test is carried out at 23 °C (73 °F) using a 100.0 mL(3 ounces) measuring cylinder of the stoppered type of approximately 25.0 cm (9.8 inches) total height and of a uniform internal diameter of approximately 30 mm (1.2 inches) over the calibrated section. The sample should be stirred to obtain a uniform consistency, and poured in up to the 100 mL (3 ounces) mark. The stopper should be inserted and the cylinder left standing undisturbed for 24 hours. After 24 hours, the height of the upper separated layer should be measured and the percentage of this layer as compared with the total height of the sample calculated.
(c) Transitional provisions. The criteria for packing group assignments in effect on December 31, 2006, may continue to be used until January 1, 2012.
[Amdt. 173-224, 55 FR 52634, Dec. 21, 1990, as amended at 56 FR 66268, Dec. 20, 1991; Amdt. 173-241, 59 FR 67507, Dec. 29, 1994 Amdt. 173-255, 61 FR 50625, Sept. 26, 1996; 64 FR 10777, Mar. 5, 1999; 64 FR 51918, Sept. 27, 1999; 66 FR 45381, Aug. 28, 2001; 68 FR 75744, Dec. 31, 2003; 71 FR 78631, Dec. 29, 2006; 76 FR 3372, Jan. 19, 2011; 76 FR 43529, July 20, 2011.]

Title 49 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 49.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-09-24; vol. 79 # 185 - Wednesday, September 24, 2014
    1. 79 FR 56988 - Clarification on Fireworks Policy Regarding Display Aerial Shells With Attachments
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Clarification.
      September 24, 2014.
      49 CFR Part 173

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 49 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 49 CFR 173 after this date.

  • 2014-09-25; vol. 79 # 186 - Thursday, September 25, 2014
    1. 79 FR 57494 - Hazardous Materials: Reverse Logistics (RRR).
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Notice of proposed rulemaking. Extension of comment period.
      The comment period for the NPRM published August 11, 2014, at 79 FR 46748, is extended from October 10, 2014, until November 10, 2014. To the extent possible, PHMSA will consider late-filed comments.
      49 CFR Parts 171 and 173