§ 173.462 Preparation of specimens for testing.
(a) Each specimen (i.e., sample, prototype or scale model) must be examined before testing to identify and record faults or damage, including:
(1) Divergence from the specifications or drawings;
(2) Defects in construction;
(3) Corrosion or other deterioration; and
(4) Distortion of features.
(b) Any deviation found under paragraph (a) of this section from the specified design must be corrected or appropriately taken into account in the subsequent evaluation.
(c) The containment system of the packaging must be clearly specified.
(d) The external features of the specimen must be clearly identified so that reference may be made to any part of it.

Title 49 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 49.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-09-24; vol. 79 # 185 - Wednesday, September 24, 2014
    1. 79 FR 56988 - Clarification on Fireworks Policy Regarding Display Aerial Shells With Attachments
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Clarification.
      September 24, 2014.
      49 CFR Part 173

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 49 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 49 CFR 173 after this date.

  • 2014-09-25; vol. 79 # 186 - Thursday, September 25, 2014
    1. 79 FR 57494 - Hazardous Materials: Reverse Logistics (RRR).
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Notice of proposed rulemaking. Extension of comment period.
      The comment period for the NPRM published August 11, 2014, at 79 FR 46748, is extended from October 10, 2014, until November 10, 2014. To the extent possible, PHMSA will consider late-filed comments.
      49 CFR Parts 171 and 173