§ 178.348-1 General requirements.
(a) Each specification DOT 412 cargo tank motor vehicle must conform to the general design and construction requirements in § 178.345 in addition to the specific requirements of this section.
(b) The MAWP of each cargo tank must be at least 5 psig.
(c) The MAWP for each cargo tank designed to be loaded by vacuum must be at least 25 psig internal and 15 psig external.
(d) Each cargo tank having a MAWP greater than 15 psig must be of circular cross-section.
(e) Each cargo tank having a—
(1) MAWP greater than 15 psig must be “constructed and certified in conformance with Section VIII of the ASME Code” (IBR, see § 171.7 of this subchapter); or
(2) MAWP of 15 psig or less must be “constructed in accordance with Section VIII of the ASME Code,” except as modified herein:
(i) The recordkeeping requirements contained in Section VIII of the ASME Code do not apply. Parts UG-90 through 94 in Section VIII do not apply. Inspection and certification must be made by an inspector registered in accordance with subpart F of part 107.
(ii) Loadings must be as prescribed in § 178.345-3.
(iii) The knuckle radius of flanged heads must be at least three times the material thickness, and in no case less than 0.5 inch. Stuffed (inserted) heads may be attached to the shell by a fillet weld. The knuckle radius and dish radius versus diameter limitations of UG-32 do not apply for cargo tank motor vehicles with a MAWP of 15 psig or less. Shell sections of cargo tanks designed with a non-circular cross section need not be given a preliminary curvature, as prescribed in UG-79(b).
(iv) Marking, certification, data reports, and nameplates must be as prescribed in §§ 178.345-14 and 178.345-15.
(v) Manhole closure assemblies must conform to §§ 178.345-5.
(vi) Pressure relief devices must be as prescribed in § 178.348-4.
(vii) The hydrostatic or pneumatic test must be as prescribed in § 178.348-5.
(viii) The following paragraphs in parts UG and UW in Section VIII of the ASME Code do not apply: UG-11, UG-12, UG-22(g), UG-32(e), UG-34, UG-35, UG-44, UG-76, UG-77, UG-80, UG-81, UG-96, UG-97, UW-13(b)(2), UW-13.1(f), and the dimensional requirements found in Figure UW-13.1.
[Amdt. 178-89, 54 FR 25031, June 12, 1989, as amended at 55 FR 37065, Sept. 7, 1990; Amdt. 178-89, 56 FR 27877, June 17, 1991; 65 FR 58632, Sept. 29, 2000; 68 FR 19285, Apr. 18, 2003; 68 fR 75756, Dec. 31, 2003]

Title 49 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 49.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-11; vol. 79 # 133 - Friday, July 11, 2014
    1. 79 FR 40590 - Hazardous Materials: Compatibility With the Regulations of the International Atomic Energy Agency (RRR)
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Final rule.
      Effective date: October 1, 2014. Voluntary compliance date: PHMSA is authorizing voluntary compliance beginning July 11, 2014. Delayed compliance date: Unless otherwise specified, compliance with the amendments adopted in this final rule is required beginning July 13, 2015. Incorporation by reference date: The incorporation by reference of certain publications listed in this rule is approved by the Director of the Federal Register as of October 1, 2014.
      49 CFR Parts 171, 172, 173, 174, 175, 176, 177 and 178

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 49 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 49 CFR 178 after this date.

  • 2014-07-11; vol. 79 # 133 - Friday, July 11, 2014
    1. 79 FR 40590 - Hazardous Materials: Compatibility With the Regulations of the International Atomic Energy Agency (RRR)
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Final rule.
      Effective date: October 1, 2014. Voluntary compliance date: PHMSA is authorizing voluntary compliance beginning July 11, 2014. Delayed compliance date: Unless otherwise specified, compliance with the amendments adopted in this final rule is required beginning July 13, 2015. Incorporation by reference date: The incorporation by reference of certain publications listed in this rule is approved by the Director of the Federal Register as of October 1, 2014.
      49 CFR Parts 171, 172, 173, 174, 175, 176, 177 and 178