§ 178.813 Leakproofness test.
(a) General. The leakproofness test must be conducted for the qualification of all IBC design types and on all production units intended to contain solids that are loaded or discharged under pressure or intended to contain liquids.
(b) Special preparation for the leakproofness test. Vented closures must either be replaced by similar non-vented closures or the vent must be sealed. For metal IBC design types, the initial test must be carried out before the fitting of any thermal insulation equipment. The inner receptacle of a composite IBC may be tested without the outer packaging provided the test results are not affected.
(c) Test method and pressure applied. The leakproofness test must be carried out for a suitable length of time using air at a gauge pressure of not less than 20 kPa (2.9 psig). Leakproofness of IBC design types must be determined by coating the seams and joints with a heavy oil, a soap solution and water, or other methods suitable for the purpose of detecting leaks. Other methods, if at least equally effective, may be used in accordance with appendix B of this part, or if approved by the Associate Administrator, as provided in § 178.801(i)).
(d) Criterion for passing the test. For all IBC design types intended to contain solids that are loaded or discharged under pressure or intended to contain liquids, there may be no leakage of air from the IBC.
[Amdt. 178-103, 59 FR 38074, July 26, 1994, as amended at 64 FR 10782, Mar. 5, 1999; 66 FR 45185, 45386, Aug. 28, 2001]

Title 49 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 49.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-11; vol. 79 # 133 - Friday, July 11, 2014
    1. 79 FR 40590 - Hazardous Materials: Compatibility With the Regulations of the International Atomic Energy Agency (RRR)
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Final rule.
      Effective date: October 1, 2014. Voluntary compliance date: PHMSA is authorizing voluntary compliance beginning July 11, 2014. Delayed compliance date: Unless otherwise specified, compliance with the amendments adopted in this final rule is required beginning July 13, 2015. Incorporation by reference date: The incorporation by reference of certain publications listed in this rule is approved by the Director of the Federal Register as of October 1, 2014.
      49 CFR Parts 171, 172, 173, 174, 175, 176, 177 and 178

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 49 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 49 CFR 178 after this date.

  • 2014-08-25; vol. 79 # 164 - Monday, August 25, 2014
    1. 79 FR 50742 - Hazardous Materials: Harmonization With International Standards (RRR)
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Notice of proposed rulemaking (NPRM).
      Comments must be received by October 24, 2014.
      49 CFR Parts 171, 172, 173, 175, 176, 178, and 180