§ 178.819 Vibration test.
(a) General. The vibration test must be conducted for the qualification of all rigid IBC design types. Flexible IBC design types must be capable of withstanding the vibration test.
(b) Test method.
(1) A sample IBC, selected at random, must be filled and closed as for shipment. IBCs intended for liquids may be tested using water as the filling material for the vibration test.
(2) The sample IBC must be placed on a vibrating platform with a vertical or rotary double-amplitude (peak-to-peak displacement) of one inch. The IBC must be constrained horizontally to prevent it from falling off the platform, but must be left free to move vertically and bounce.
(3) The test must be performed for one hour at a frequency that causes the package to be raised from the vibrating platform to such a degree that a piece of material of approximately 1.6-mm (0.063-inch) thickness (such as steel strapping or paperboard) can be passed between the bottom of the IBC and the platform. Other methods at least equally effective may be used (see § 178.801(i)).
(c) Criteria for passing the test. An IBC passes the vibration test if there is no rupture or leakage.
[Amdt. 178-103, 59 FR 38074, July 26, 1994, as amended by Amdt. 178-108, 60 FR 40038, Aug. 4, 1995; Amdt. 178-110, 60 FR 49111, Sept. 21, 1995; 66 FR 45386, Aug. 28, 2001; 75 FR 5397, Feb. 2, 2010]

Title 49 published on 2013-10-01

The following are only the Rules published in the Federal Register after the published date of Title 49.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-07-11; vol. 79 # 133 - Friday, July 11, 2014
    1. 79 FR 40590 - Hazardous Materials: Compatibility With the Regulations of the International Atomic Energy Agency (RRR)
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Final rule.
      Effective date: October 1, 2014. Voluntary compliance date: PHMSA is authorizing voluntary compliance beginning July 11, 2014. Delayed compliance date: Unless otherwise specified, compliance with the amendments adopted in this final rule is required beginning July 13, 2015. Incorporation by reference date: The incorporation by reference of certain publications listed in this rule is approved by the Director of the Federal Register as of October 1, 2014.
      49 CFR Parts 171, 172, 173, 174, 175, 176, 177 and 178

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 49 published on 2013-10-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 49 CFR 178 after this date.

  • 2014-08-25; vol. 79 # 164 - Monday, August 25, 2014
    1. 79 FR 50742 - Hazardous Materials: Harmonization With International Standards (RRR)
      GPO FDSys XML | Text
      DEPARTMENT OF TRANSPORTATION, Pipeline and Hazardous Materials Safety Administration
      Notice of proposed rulemaking (NPRM).
      Comments must be received by October 24, 2014.
      49 CFR Parts 171, 172, 173, 175, 176, 178, and 180