7 CFR 1779.78 - Repurchase of loan.

Status message

There is 1 rule appearing in the Federal Register for 7 CFR 1779. View below or at eCFR (GPOAccess)
§ 1779.78 Repurchase of loan.
(a) Repurchase by lender. The lender has the option to repurchase the loan from a holder within 30 days of written demand from the holder when the borrower is in default not less than 60 days on payment. The repurchase will be for an amount equal to the unpaid guaranteed portion of principal and accrued interest less the lender's servicing fee. The guarantee does not cover the note interest to the holder on the guaranteed loan accruing after 90 days from the date of the demand letter to the lender. The holder will concurrently send a copy of the demand to the Agency. The lender will accept an assignment without recourse from the holder upon repurchase. The lender is encouraged to repurchase the loan to facilitate the accounting of funds, resolve the problem, and permit the borrower to cure the default, where reasonable. The lender will notify the holder and the Agency of its decision within 30 days of receipt of demand from the holder.
(b) Agency repurchase. (1) If the lender does not repurchase as provided in paragraph (a) of this section, the Agency will purchase from the holder the unpaid principal balance of the guaranteed portion together with accrued interest to date of repurchase (less the lender's servicing fee) within 30 days after a specific written demand directed to the Agency. The copy of the demand on the lender is not sufficient. The guarantee will not cover the note interest to the holder on the guaranteed loan accruing after 90 days from the date of the original demand letter. The lender shall not charge the Agency any servicing fees nor are any such fees collectible from the Agency.
(2) The holder's demand to the Agency must include a copy of the written demand made upon the lender. The holder or duly authorized agent must also include evidence of the right to require payment from the Agency. Such evidence will consist of either the original of the Loan Note Guarantee properly endorsed to the Agency or the original of the Assignment Guarantee Agreement properly assigned to the Agency without recourse including all rights, title, and interest in the loan. The Agency will be subrogated to all rights of the holder. The holder must include in the demand the amount due including unpaid principal, unpaid interest to date of demand, and interest subsequently accruing from the date of demand to the proposed payment date. Unless otherwise agreed to by the Agency, such proposed payment will not be later than 30 days from the date of demand.
(3) The lender must promptly provide the Agency with the information necessary for the Agency's determination of the appropriate amount due the holder upon the Agency's notification to the lender of the holder's demand for payment. This information must be certified by an authorized officer of the lender. Any discrepancy between the amount claimed by the holder and the information submitted by the lender must be resolved before payment will be approved. The Agency will notify both parties and such conflict will suspend the running of the 30-day payment requirement.
(4) Any purchase by the Agency does not change, alter, or modify any of the lender's obligations to the Agency arising from the loan or guarantee nor does it waive any of the Agency's rights against the lender. The Agency may set off against the lender all rights inuring to the Agency as the holder of the instrument against the Agency's obligation to the lender under the Loan Note Guarantee.
(c) Repurchase for servicing. When the lender determines that repurchase of the guaranteed portion of the loan is necessary to service the loan, the holder must sell the guaranteed portion to the lender for the unpaid principal and interest balance (less the lender's servicing fee). The guarantee does not cover interest accruing after 90 days from the date the lender's or Agency's letter requesting the holder to tender its guaranteed portion. The lender must not repurchase from the holder for arbitrage purposes to further its own financial gain. Any repurchase must be made only after the lender obtains the Agency written approval. If the lender does not repurchase the portion from the holder, the Agency may, at its option, purchase such guaranteed portion for servicing purposes.

Title 7 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 7.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF TRANSPORTATION, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF HEALTH AND HUMAN SERVICES, DEPARTMENT OF LABOR, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, ENVIRONMENTAL PROTECTION AGENCY, NATIONAL ENDOWMENT FOR THE HUMANITIES, DEPARTMENT OF DEFENSE, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 7 - AGRICULTURE
U.S. Code: Title 16 - CONSERVATION

Title 7 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR 1779 after this date.

  • 2014-12-19; vol. 79 # 244 - Friday, December 19, 2014
    1. 79 FR 75872 - Federal Awarding Agency Regulatory Implementation of Office of Management and Budget's Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards
      GPO FDSys XML | Text
      DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT, AGENCY FOR INTERNATIONAL DEVELOPMENT, NATIONAL SCIENCE FOUNDATION, CORPORATION FOR NATIONAL AND COMMUNITY SERVICE, NATIONAL ARCHIVES AND RECORDS ADMINISTRATION, DEPARTMENT OF TREASURY, NATIONAL ENDOWMENT FOR THE ARTS, GULF COAST ECOSYSTEM RESTORATION COUNCIL, DEPARTMENT OF TRANSPORTATION, EXECUTIVE OFFICE OF THE PRESIDENT, DEPARTMENT OF HEALTH AND HUMAN SERVICES, DEPARTMENT OF LABOR, INSTITUTE OF MUSEUM AND LIBRARY SERVICES, ENVIRONMENTAL PROTECTION AGENCY, NATIONAL ENDOWMENT FOR THE HUMANITIES, DEPARTMENT OF DEFENSE, NATIONAL AERONAUTICS AND SPACE ADMINISTRATION, DEPARTMENT OF THE INTERIOR, DEPARTMENT OF COMMERCE, DEPARTMENT OF AGRICULTURE, DEPARTMENT OF ENERGY, DEPARTMENT OF HOMELAND SECURITY, SOCIAL SECURITY ADMINISTRATION, DEPARTMENT OF STATE, DEPARTMENT OF VETERANS AFFAIRS, DEPARTMENT OF EDUCATION, DEPARTMENT OF JUSTICE, SMALL BUSINESS ADMINISTRATION, National Institute of Food and Agriculture, Rural Utilities Service, Rural Housing Service, Office of the Chief Financial Officer, Farm Service Agency, Office of National Drug Control Policy, Office of Management and Budget, Commodity Credit Corporation, Rural Business-Cooperative Service, Federal Emergency Management Agency
      Interim final rule.
      Effective date: This interim final rule is effective on December 26, 2014. The incorporation by reference of certain publications listed in the rule is approved by the Director of the Federal Register as of December 26, 2014. Implementation dates: For grants authorized under the Robert T. Stafford Disaster Relief and Emergency Assistance Act, this rule is applicable for emergency or major disaster declarations issued on or after December 26, 2014. For non-Federal entities that are nonprofit organizations or institutions of higher education (IHEs), there is a one-year grace period for implementation of the procurement standards in 2 CFR 200.317 through 200.326. As will be detailed in the 2015 OMB Compliance Supplement, non-Federal entities choosing to delay implementation for the procurement standards will need to specify in their documented policies and procedures that they continue to comply with OMB circular A-110 for one additional fiscal year which begins after December 26, 2014. Comment date: To be assured of consideration, comments must be received by OMB electronically through www.regulations.gov no later than midnight Eastern Standard Time (E.S.T.) on February 17, 2015.
      2 CFR Parts 1, 25, 170, 180, and 200