7 CFR Part 1940, Subpart G, Exhibit E to Subpart G of Part 1940 - Implementation Procedures for the Wild and Scenic Rivers Act

Status message

There is 1 rule appearing in the Federal Register for 7 CFR 1940. View below or at eCFR (GPOAccess)
View PDF at GPO Pt. 1940, Subpt. G, Exh. E
Exhibit E to Subpart G of Part 1940—Implementation Procedures for the Wild and Scenic Rivers Act
1. Each application for financial assistance or subdivision approval as well as the proposed disposal of real property by FmHA or its successor agency under Public Law 103-354 shall be reviewed to determine if it will affect a river or portion of it which is either included in the National Wild and Scenic Rivers System, designated for potential addition to the system, or identified in the Nationwide Inventory prepared by the National Park Service (NPS) in the Department of the Interior. The Nationwide Inventory identifies those river segments that, after preliminary review, appear to qualify for inclusion in the system. (For purposes of this subpart, river segments in the Nationwide Inventory shall be treated the same as segments within the system with the exception of paragraph 8.) For applications subject to environmental assessments, the review shall be accomplished as part of the assessment. For applications that are excluded from an environmental assessment, this review shall be documented as part of Form FmHA or its successor agency under Public Law 103-354 1940-22, “Environmental Checklist For Categorical Exclusions,” within the reviewing office and shall be accomplished as early as possible after receipt of the application and prior to approval of the application. The FmHA or its successor agency under Public Law 103-354 official responsible for completing the environmental assessment shall accomplish this review. (See § 1940.316 of this subpart.)
2. In order to effectively implement this review, State Directors shall ensure that State, District and County Offices maintain current listings of rivers within their respective States that are included in or designated for potential addition to the system as well as those identified in the Nationwide Inventory prepared by NPS.
3. For applications for water resources projects, as defined in § 1940.302(i) of this subpart, the purpose of this review shall be to determine whether the proposal would have a direct and adverse effect on the values which served as the basis for the river's inclusion in the system or designation for potential addition. For other applications, the purpose of the review shall be to determine if the proposal would invade the river area or unreasonably diminish the scenic, recreational, and fish and wildlife values present in the area. To make these determinations, the reviewer shall consult with the appropriate regional office of NPS if the proposal (i) would be located within one-quarter mile of the banks of the river, (ii) involves withdrawing water from the river or discharging water to the river via a point source, or (iii) would be visible from the river. The appropriate regional office of the Forest Service (FS) shall be contacted under similar circumstances when the effected river is on FS lands. Consultation shall be initiated by a written request for comments on the potential impacts accompanied by a description of the project and its location. The reviewer shall consult in other instances when the likelihood of an impact on a river in the system is identified as part of the environmental review. When the reviewer determines there is no potential impact on such a river, the documentation of this determination concludes the review process, unless reinitiation is required under paragraph 10 of this exhibit. In all other cases, the review is completed as specified below in paragraphs 4 through 9 of this exhibit.
4. If the review is at the County or District Office level, the reviewer can request the State Director (see § 1940.307 of this subpart) to perform the above consultation. The State Director can in turn make a similar request of the National Office. If not requested to perform the consultation for applications approvable at the County and District Office levels, the SEC shall be informed whenever NPS or FS advises that there is a potential for an adverse impact on a river within the system or that protective measures need to be included or designed into the proposal. In all cases, consultation shall be initiated by FmHA or its successor agency under Public Law 103-354 and not the applicant. Until consultation is complete, FmHA or its successor agency under Public Law 103-354 shall not approve the application. Should the need for consultation be identified after application approval, FmHA or its successor agency under Public Law 103-354 shall, if still within its power at the time of identification, refrain from making any irreversible or irretrievable commitments of resources which would foreclose the consideration of modifications or alternatives to the project.
5. If NPS or FS advises there is no potential for an adverse effect as described in paragraph 3 of this exhibit, this review process is concluded, unless the need to reinitiate arises. (See paragraph 10 of this exhibit.)
6. Whenever the results of the consultation process include recommendations by NPS or FS to modify the proposal in order to avoid an adverse effect, as described in paragraph 3 above, the State Director shall review these recommendations and require that they be incorporated into the project as either design changes or special conditions to the offer of assistance. If the State Director does not believe that the Regional Director's recommendations can be so adopted, the Administrator shall be requested to review the recommendations and to assist in the further resolution of the matter.
7. If NPS or FS advises that the proposal will have an unavoidable adverse effect, as described in paragraph 3 of this exhibit, on a river segment which is either included in the National Wild and Scenic Rivers System or designated for potential addition to the system, the FmHA or its successor agency under Public Law 103-354 applicant will be informed by the reviewing office and the application denied on this basis. However, if the State Director disagrees with this determination, the State Director can request the Administrator to review the proposal and attempt to further resolve the matter. The specific reasons for disagreement along with supporting documentation must be included in such a request. Based upon a review of this request, the Administrator shall either inform the State Director that no further consultation is warranted and the application shall be denied or shall request the headquarters staff of NPS or FS to further review the matter. No action shall be taken by the State Director on the application until the Administrator informs the State Director of the results of this further review and consultation.
8. If NPS or FS advises that the proposal will have an adverse effect, as described in paragraph 3 of this exhibit, on a river segment identified in the Nationwide Inventory, the reviewer shall further consult with NPS or FS in order to formulate adequate measures or modification to avoid or mitigate the potential adverse effect. The purposes of such measures or modifications is to ensure that the proposal does not effectively foreclose the designation of a wild, scenic, or recreational river segment. Once concurrence is reached and documented with NPS or FS regarding modifications, the State Director shall require that they be incorporated into the proposal as either design changes or special conditions to the offer of assistance. If the State Director is not able to reach an agreement with NPS or FS on appropriate modifications, the Administrator shall be requested to assist in the further resolution of the matter.
9. If an application involves financial assistance or permit approval from another Federal Agency, the FmHA or its successor agency under Public Law 103-354 reviewer shall work with the other agency(s) to determine a lead Agency for the consultation process. When FmHA or its successor agency under Public Law 103-354 is not the lead Agency, the reviewer shall ensure that the lead Agency informs NPS or FS of FmHA or its successor agency under Public Law 103-354's involvement.
10. Once completed, the consultation process shall be reinitiated by FmHA or its successor agency under Public Law 103-354 if new information or modification of the proposal reveals impacts to a river within the System or Nationwide Inventory.

Title 7 published on 2014-01-01

The following are only the Rules published in the Federal Register after the published date of Title 7.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2014-09-18; vol. 79 # 181 - Thursday, September 18, 2014
    1. 79 FR 55965 - Eliminate the 6-Day Reservation Period Requirement for Rural Development Obligations
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Rural Utilities Service, Rural Housing Service, Farm Service Agency, Rural Business-Cooperative Services
      Direct final rule.
      This rule will become effective January 16, 2015 without further action, unless the Agency receives written adverse comments on or before November 17, 2014. If the Agency receives adverse comments, the Agency will publish a timely document in the Federal Register withdrawing the amendment. Any adverse comments received will be considered under the proposed rule published in this edition of the Federal Register in the proposed rule section. A second public comment period will not be held. Written comments must be received by the Agency or carry a postmark no later than November 17, 2014.
      7 CFR Parts 1940, 1942, 1944, 1948, and 1980

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 7 - AGRICULTURE
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

Title 7 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR 1940 after this date.

  • 2014-09-18; vol. 79 # 181 - Thursday, September 18, 2014
    1. 79 FR 55965 - Eliminate the 6-Day Reservation Period Requirement for Rural Development Obligations
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Rural Utilities Service, Rural Housing Service, Farm Service Agency, Rural Business-Cooperative Services
      Direct final rule.
      This rule will become effective January 16, 2015 without further action, unless the Agency receives written adverse comments on or before November 17, 2014. If the Agency receives adverse comments, the Agency will publish a timely document in the Federal Register withdrawing the amendment. Any adverse comments received will be considered under the proposed rule published in this edition of the Federal Register in the proposed rule section. A second public comment period will not be held. Written comments must be received by the Agency or carry a postmark no later than November 17, 2014.
      7 CFR Parts 1940, 1942, 1944, 1948, and 1980