Appendix E to Subpart B of Part 4280—Feasibility Study Content
Elements in an acceptable feasibility study include, but are not necessarily limited to, the elements specified in Sections A through G, as applicable, of this Appendix. Both a technical report for the project and an economic analysis of the project are required as part of the feasibility study. The technical report to be provided must conform to that required under Appendix A, B, C, or D of this subpart, as applicable.
Section A. Executive Summary. Provide an introduction and overview of the project. In the overview, describe the nature and scope of the proposed project, including purpose, project location, design features, capacity, and estimated total capital cost. Include a summary of each of the elements of the feasibility study, including:
(1) Economic feasibility determinations;
(2) Market feasibility determinations;
(3) Technical feasibility determinations;
(4) Financial feasibility determinations;
(5) Management feasibility determinations; and
(6) Recommendations for implementation of the proposed project.
Section B. Economic Feasibility. Provide information regarding project site; the availability of trained or trainable labor; and the availability of infrastructure, including utilities, and rail, air and road service to the site. Discuss feedstock source management, including feedstock collection, pre-treatment, transportation, and storage, and provide estimates of feedstock volumes and costs. Discuss the proposed project's potential impacts on existing manufacturing plants or other facilities that use similar feedstock if the proposed technology is adopted. Provide projected impacts of the proposed project on resource conservation, public health, and the environment. Provide an overall economic impact of the project including any additional markets created (e.g., for agricultural and forestry products and agricultural waste material) and potential for rural economic development. Provide feasibility/plans of project to work with producer associations or cooperatives including estimated amount of annual feedstock and biofuel and byproduct dollars from producer associations and cooperatives.
Section C. Market Feasibility. Provide information on the sales organization and management. Discuss the nature and extent of market and market area and provide marketing plans for sale of projected output, including both the principal products and the by-products. Discuss the extent of competition including other similar facilities in the market area. Provide projected total supply of and projected competitive demand for raw materials. Describe the procurement plan, including projected procurement costs and the form of commitment of raw materials (e.g., marketing agreements, etc.). Identify commitments from customers or brokers for both the principal products and the by-products. Discuss all risks related to the industry, including industry status.
Section D. Technical Feasibility. The technical feasibility report shall be based upon verifiable data and contain sufficient information and analysis so that a determination may be made on the technical feasibility of achieving the levels of income or production that are projected in the financial statements. The project engineer or architect is considered an independent party provided neither the principals of the firm nor any individual of the firm who participates in the technical feasibility report has a financial interest in the project. If no other individual or firm with the expertise necessary to make such a determination is reasonably available to perform the function, an individual or firm that is not independent may be used.
(1) Identify any constraints or limitations in the financial projections and any other facility or design-related factors that might affect the success of the enterprise. Identify and estimate project operation and development costs and specify the level of accuracy of these estimates and the assumptions on which these estimates have been based.
(2) Discuss all risks related to construction of the project and regulation and governmental action as they affect the technical feasibility of the project.
Section E. Financial Feasibility. Discuss the reliability of the financial projections and assumptions on which the financial statements are based including all sources of project capital both private and public, such as Federal funds. Provide 3 years (minimum) projected Balance Sheets and Income Statements and cash flow projections for the life of the project. Discuss the ability of the business to achieve the projected income and cash flow. Provide an assessment of the cost accounting system. Discuss the availability of short-term credit or other means to meet seasonable business costs and the adequacy of raw materials and supplies. Provide a sensitivity analysis, including feedstock and energy costs. Discuss all risks related to the project, financing plan, the operational units, and tax issues.
Section F. Management Feasibility. Discuss the continuity and adequacy of management. Identify applicant and/or management's previous experience concerning the receipt of federal financial assistance, including amount of funding, date received, purpose, and outcome. Discuss all risks related to the applicant as a company (e.g., applicant is at the Development-Stage) and conflicts of interest, including appearances of conflicts of interest.
Section G. Qualifications. Provide a resume or statement of qualifications of the author of the feasibility study, including prior experience.

Title 7 published on 2014-01-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 7 published on 2014-01-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 7 CFR 4280 after this date.

  • 2014-04-02; vol. 79 # 63 - Wednesday, April 2, 2014
    1. 79 FR 18482 - Environmental Policies and Procedures
      GPO FDSys XML | Text
      DEPARTMENT OF AGRICULTURE, Rural Business-Cooperative Service, Rural Utilities Service, Rural Housing Service, Farm Service Agency
      Proposed rule; extension of public comment period.
      Comments on the proposed rule must be received on or before May 7, 2014.
      7 CFR Parts 1703, 1709, 1710, 1717, 1720, 1721, 1724, 1726, 1737, 1738, 1739, 1740, 1753, 1774, 1775, 1779, 1780, 1781, and 1782