detailed project report

(1) Detailed project report The term “detailed project report” means a report for a project not specifically authorized by Congress in law or otherwise that determines the feasibility of the project with a level of detail appropriate to the scope and complexity of the recommended solution and sufficient to proceed directly to the preparation of contract plans and specifications. The term includes any associated environmental impact statement and mitigation plan. For a project for which the Federal cost does not exceed $1,000,000, the term includes a planning and design analysis document.

Source

33 USC § 2215(d)(1)


Scoping language

In this section
Is this correct? or